 <<O>>  Difference Topic ActionPlan (r1.20 - 07 Sep 2007 - KarenONeil)
Changed:
<
<

Milestones

>
>

Major Milestones

Changed:
<
<

Original Date Modified Date Goal Date Completed
Develop Strawman Proposal (Summer 2006)
Jul 2006 24 Jul, 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 Jul, 2006
1 Jun, 2006 13 Jun, 2006 Complete strawman proposal for dynamic scheduling system 13 Jun, 2006
1 Jun, 2006 21 Jun, 2006 Present proposal to the GB staff and outside observers for comments 21 Jun, 2006
31 Aug, 2006 01 Sep, 2006 Modify proposal based on comments received 01 Sep, 2006
Stage I System (Fall/ Winter 2006)
15 Nov, 2006 28 Nov, 2006 Complete overview, selection rules for Stage I 28 Nov, 2006
22 Dec, 2006 30 Jan, 2007 Complete description of software suite 30 Jan, 2007
22 Dec, 2006 15 May, 2007 Complete plans for Stage I tests 15 May, 2007
01 Jan, 2007   Call for Sept, 2007 proposals 01 Jan, 2007
01 Apr, 2007 01 May, 2007 Complete changes in overview from 2nd round of staff comments 01 May, 2007
01 Feb, 2007 01 Jul, 2007 Complete documentation on desired PST changes  
01 Feb, 2007   Deadline for Sept, 2007 proposals 01 Feb, 2007
31 Mar, 2007   Receive graded proposals for test period 31 Mar, 2007
01 May, 2007 10 May, 2007 Complete modified selection rules 16 May, 2007
17 May, 2007   Present plans to user's committee 17 May, 2007
01 Jun, 2007   Complete software for selection rules  
06 Jun, 2007   External reveiw  
Stage II System (Spring/Summer 2007)
01 Jul, 2007   Rewrite documentation/plans based off external review  
01 Jul, 2007   Complete version I of proposal tool interface  
15 Jul, 2007   Complete stage II tests of selection rules  
15 Jul, 2007   Complete Stage II software & documentation  
15 Jul, 2007   Begin operator training for stage II tests  
01 Aug, 2007   Contact all test observers with details of test  
15 Aug, 2007   Begin Stage II tests  
01 Sep, 2007   Winter, 2008 proposal call, PST changes in place  
01 Oct, 2007   Winter, 2008 proposals due  
30 Sep, 2007   Complete Stage II tests  
Stage III System (Fall 2007 - Winter 2009)
14 Nov, 2007   Complete plans for Stage III  
15 Nov, 2007   Present plans for stage III DSS to local staff  
01 Dec, 2007   Second External Review  
01 Jan, 2008   All documentation for Stage III in place  
01 Jan, 2008   Call for proposals using complete dynamic scheduling  
01 Apr, 2008   Receive complete graded list of proposals for 1st semester of dynamic scheduling  
01 Apr, 2008   Complete Stage III software  
01 May, 2008   Begin operator and support staff training of DSS  
01 Jun, 2008   Release Stage III software for general use  
01 Sep, 2008   Version 2 of Stage III software complete, staff retraining begins  
01 Oct, 2008   Version 2 of stage III software released  
01 Oct, 2008   First high frequency semester with DSS begins  
15 Jan, 2009   Version 3 of stage III software complete  
01 Feb, 2009   First high frequency season with DSS ends  
01 Feb, 2009   Version n3 of stage III software released  
Stage IV System (Winter 2009 – Winter 2010)
28 Feb, 2009   Complete plans for Stage IV  
15 Mar, 2009   Present plans for stage IV DSS to local staff  
01 May, 2009   All documentation for Stage IV in place  
01 May, 2009   All changes to PST for Stage IV complete  
01 May, 2009   Call for proposals using stage IV dynamic scheduling  
01 Jul, 2009   Receive complete graded list of proposals for 1st semester of dynamic scheduling  
01 Sep, 2009   Complete Stage IV software  
01 Sep, 2009   Begin operator and support staff training of DSS  
01 Oct, 2009   Release Stage IV software for general use  
01 Oct, 2009   First high frequency season with DSS begins  

Flow Charts

>
>

Goal Original Date Modified Date Status
Complete straw man proposal for dynamic scheduling system 1 Jun, 2006 13 Jun, 2006 Complete
Present proposal to the GB staff and outside observers for comments 1 Jun, 2006 21 Jun, 2006 Complete
Present modified plans to GB staff for comments 01 Jan, 2007 15 Jan, 2007 Complete
Site presentation for GB staff 01 May, 2007 12 May, 2007 Complete
Present plans to user's committee 7 May, 2007 17 May, 2007 Complete
Conceptual design review 06 Jun, 2007 06 Jun, 2007 Complete
Description of test plans complete 01 Feb, 2007 01 Dec, 2007  
Call for proposals (test period) 01 Jun, 2007 01 Jan, 2008  
Stage II tests begin 15 Aug, 2007 01 Jun, 2008  
Stage II tests complete 30 Sep, 2007 30 Sep, 2008  
Complete Stage II 01 Oct, 2007 01 Oct, 2008  
Preliminary design review 01 Dec, 2007 01 Dec, 2008  
Release Stage III software for general use 01 Jun, 2008 01 Oct, 2009  
Release Stage IV software for general use 01 Oct, 2009 01 Oct, 2010  

 <<O>>  Difference Topic ActionPlan (r1.19 - 17 Jul 2007 - KarenONeil)
Added:
>
>

Flow Charts

%META:FILEATTACHMENT{name="DSS_Test_list_v3.pdf" attr="h" comment="Flow Chart for DSS Tests" date="1184683432" path="DSS_Test_list_v3.pdf" size="26101" user="KarenONeil" version="1.2"}%


 <<O>>  Difference Topic ActionPlan (r1.18 - 25 May 2007 - KarenONeil)
Changed:
<
<

01 Dec, 2008   Receive complete graded list of proposals for 1st semester of dynamic scheduling  
>
>

01 Apr, 2008   Receive complete graded list of proposals for 1st semester of dynamic scheduling  

 <<O>>  Difference Topic ActionPlan (r1.17 - 22 May 2007 - KarenONeil)
Changed:
<
<

Goals, Objectives, and Schedule

>
>

Schedule

Deleted:
<
<

Goals

Changed:
<
<

  • Long term goal is to have true dynamic scheduling on the GBT which eases the support burden and which results in high frequency projects being completed more rapidly than is currently (2006) possible.
  • All telescope activities, including science, commissioning, tests and maintenance are flexibly scheduled to:
    • Optimize use of high-frequency weather.
    • Enable timely completion of projects.
  • Achieve efficient fixed scheduling of crucial maintenance activities, VLBI/bi-static radar or other observations that require coordination with other facilities, and monitoring projects.
>
>

Description of Stages

Changed:
<
<


Objectives

  • Demonstrate increased flexibility from previous manual dynamic scheduling approach
    • High frequency projects should be completed more rapidly than is currently occurring
    • Project run should better match weather conditions
  • Demonstrate increased flexibility from previous software tools and applications
    • Eliminate GO as a production tool by October 1, 2005. DONE
  • Ease the burden of the GBT scheduler in matching weather conditions


Schedule

Description of Stages

Stage I

  • This is the proof of concept stage
>
>

Stage I - Concept Development

Changed:
<
<

Stage II

>
>

Stage II - Proof of Concept

Changed:
<
<

Stage III

>
>

Stage III - First Release

Changed:
<
<

Stage IV

>
>

Stage IV - Second Release

Changed:
<
<

Milestones

>
>

Milestones

Changed:
<
<

01 May, 2007 10 May, 2007 Complete modified selection rules  
17 May, 2007   Present plans to user's committee  
>
>

01 May, 2007 10 May, 2007 Complete modified selection rules 16 May, 2007
17 May, 2007   Present plans to user's committee 17 May, 2007
Added:
>
>

01 Dec, 2007   Second External Review  

 <<O>>  Difference Topic ActionPlan (r1.16 - 22 May 2007 - AmyShelton)
Changed:
<
<

>
>


 <<O>>  Difference Topic ActionPlan (r1.15 - 21 May 2007 - AmyShelton)
Added:
>
>

    • Primary Tests:
      • Dynamic Scheduling System policies
      • Session selection rules and weights
      • Scheduling predictions and look ahead
      • Conceptual software suite
    • Secondary Tests:
      • Proposal information page
      • Ease of user contact
Added:
>
>

Changed:
<
<

July 2006 24 July, 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 July, 2006
1 June, 2006 13 June, 2006 Complete strawman proposal for dynamic scheduling system 13 June, 2006
1 June, 2006 21 June, 2006 Present proposal to the GB staff and outside observers for comments 21 June, 2006
31 August, 2006 01 September, 2006 Modify proposal based on comments received 01 September, 2006
>
>

Jul 2006 24 Jul, 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 Jul, 2006
1 Jun, 2006 13 Jun, 2006 Complete strawman proposal for dynamic scheduling system 13 Jun, 2006
1 Jun, 2006 21 Jun, 2006 Present proposal to the GB staff and outside observers for comments 21 Jun, 2006
31 Aug, 2006 01 Sep, 2006 Modify proposal based on comments received 01 Sep, 2006

 <<O>>  Difference Topic ActionPlan (r1.14 - 02 May 2007 - KarenONeil)
Changed:
<
<

Develop Strawman Proposal (Summer 2006)
Original Date Goal Date Completed
July 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 July, 2006
1 June, 2006 Complete strawman proposal for dynamic scheduling system 13 June, 2006
1 June, 2006 Present proposal to the GB staff and outside observers for comments 21 June, 2006
31 August, 2006 Modify proposal based on comments received 01 September, 2006
Stage I System (Fall/ Winter 2006)
15 Nov, 2006 Complete overview, selection rules for Stage I 28 Nov, 2006
22 Dec, 2006 Complete description of software suite  
22 Dec, 2006 Complete plans for Stage I tests  
1 Jan, 2007 Call for Sept, 2007 proposals  
1 Feb, 2007 Complete documentation on desired PST changes  
1 Feb, 2007 Deadline for Sept, 2007 proposals  
??? Run Stage I tests (simulation)  
??? Modify documentation & based off simulation results  
??? External Review  
Stage II System (Spring/Summer 2007)
??? Rewrite documentation/plans based off external review  
01 Aug, 2007 Complete Stage II software & documentation  
01 Sept, 2007 Begin Stage II tests  
01 Sept, 2007 Winter, 2008 proposal call, PST changes in place  
01 Oct, 2007 Winter, 2008 proposals due  
30 Sept, 2007 Complete Stage II tests  
Stage III System (Fall/Early Winter 2007)
01 Jan, 2008 Complete Stage III software and documentation  
15 Jan, 2008 Complete Stage III simulation tests  
31 Jan, 2008 Complete Stage III modifications  
01 Feb, 2008 Release Stage III software for general use  
Stage IV System (Winter 2007 – Winter 2008)
June, 2008 Analyze results from Winter trimester  
Fall, 2008 Complete Stage IV modifications  
01 Sept, 2008 Winter, 2009 proposal call, PST changes in place  
01 Oct, 2008 Winter, 2009 proposals due  
01 Jan, 2009 Begin Stage simulation tests  
31 Jan, 2009 Complete Stage III modifications  
01 Feb, 2009 Release Stage IV software for general use  
>
>

Note that all milestones have slipped due to having fewer resources on the project than anticipated.

Changed:
<
<

-- KarenONeil - 02 May 2006

>
>

Original Date Modified Date Goal Date Completed
Develop Strawman Proposal (Summer 2006)
July 2006 24 July, 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 July, 2006
1 June, 2006 13 June, 2006 Complete strawman proposal for dynamic scheduling system 13 June, 2006
1 June, 2006 21 June, 2006 Present proposal to the GB staff and outside observers for comments 21 June, 2006
31 August, 2006 01 September, 2006 Modify proposal based on comments received 01 September, 2006
Stage I System (Fall/ Winter 2006)
15 Nov, 2006 28 Nov, 2006 Complete overview, selection rules for Stage I 28 Nov, 2006
22 Dec, 2006 30 Jan, 2007 Complete description of software suite 30 Jan, 2007
22 Dec, 2006 15 May, 2007 Complete plans for Stage I tests 15 May, 2007
01 Jan, 2007   Call for Sept, 2007 proposals 01 Jan, 2007
01 Apr, 2007 01 May, 2007 Complete changes in overview from 2nd round of staff comments 01 May, 2007
01 Feb, 2007 01 Jul, 2007 Complete documentation on desired PST changes  
01 Feb, 2007   Deadline for Sept, 2007 proposals 01 Feb, 2007
31 Mar, 2007   Receive graded proposals for test period 31 Mar, 2007
01 May, 2007 10 May, 2007 Complete modified selection rules  
17 May, 2007   Present plans to user's committee  
01 Jun, 2007   Complete software for selection rules  
06 Jun, 2007   External reveiw  
Stage II System (Spring/Summer 2007)
01 Jul, 2007   Rewrite documentation/plans based off external review  
01 Jul, 2007   Complete version I of proposal tool interface  
15 Jul, 2007   Complete stage II tests of selection rules  
15 Jul, 2007   Complete Stage II software & documentation  
15 Jul, 2007   Begin operator training for stage II tests  
01 Aug, 2007   Contact all test observers with details of test  
15 Aug, 2007   Begin Stage II tests  
01 Sep, 2007   Winter, 2008 proposal call, PST changes in place  
01 Oct, 2007   Winter, 2008 proposals due  
30 Sep, 2007   Complete Stage II tests  
Stage III System (Fall 2007 - Winter 2009)
14 Nov, 2007   Complete plans for Stage III  
15 Nov, 2007   Present plans for stage III DSS to local staff  
01 Jan, 2008   All documentation for Stage III in place  
01 Jan, 2008   Call for proposals using complete dynamic scheduling  
01 Dec, 2008   Receive complete graded list of proposals for 1st semester of dynamic scheduling  
01 Apr, 2008   Complete Stage III software  
01 May, 2008   Begin operator and support staff training of DSS  
01 Jun, 2008   Release Stage III software for general use  
01 Sep, 2008   Version 2 of Stage III software complete, staff retraining begins  
01 Oct, 2008   Version 2 of stage III software released  
01 Oct, 2008   First high frequency semester with DSS begins  
15 Jan, 2009   Version 3 of stage III software complete  
01 Feb, 2009   First high frequency season with DSS ends  
01 Feb, 2009   Version n3 of stage III software released  
Stage IV System (Winter 2009 – Winter 2010)
28 Feb, 2009   Complete plans for Stage IV  
15 Mar, 2009   Present plans for stage IV DSS to local staff  
01 May, 2009   All documentation for Stage IV in place  
01 May, 2009   All changes to PST for Stage IV complete  
01 May, 2009   Call for proposals using stage IV dynamic scheduling  
01 Jul, 2009   Receive complete graded list of proposals for 1st semester of dynamic scheduling  
01 Sep, 2009   Complete Stage IV software  
01 Sep, 2009   Begin operator and support staff training of DSS  
01 Oct, 2009   Release Stage IV software for general use  
01 Oct, 2009   First high frequency season with DSS begins  

 <<O>>  Difference Topic ActionPlan (r1.13 - 30 Nov 2006 - KarenONeil)
Deleted:
<
<

  • All observations are performed by the execution of Scheduling Blocks (SBs) which have been defined in advance.
Changed:
<
<

    • High frequency projects should be completed more rapidly than is currently occuring - Is there a metric we can use to judge this?
    • We should have fewer problems finding sufficient low frequency projects for the telescope - Is there a metric we can use to judge this?
>
>

    • High frequency projects should be completed more rapidly than is currently occurring
    • Project run should better match weather conditions
Changed:
<
<

    • Other???
>
>

  • Ease the burden of the GBT scheduler in matching weather conditions
Added:
>
>

Added:
>
>

Description of Stages

Changed:
<
<

Develop Phase I Proposal:

  • Interface with JCMT, other telescopes to determine dynamic scheduling "lessons"
  • Determine all selection requirements
  • Complete strawman proposal for dynamic scheduling system
  • Present proposals to the GB staff and 2 outside observers (1 LF anf 1 HF) for comments.
  • Modify strawman proposal based on comments receive

Build Stage I System (Summer/Fall/Early Winter 2006)

  • Write all software needed for the 2006/2007 tests. Note that all software for tests should be considered prototype and will be rewritten for Stage II. As such, this software could be very simplistic.:
    • Prototype query tool
    • Prototype time accounting tool
    • Prototype Metadata tool
    • Prototype User/Staff Feedback tool
  • Train select group of astronomers (and operators) for using Stage I system
  • Write documentation for all weather queue information
  • This includes determining all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 6-7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed
  • Begin operator training for, e.g. running receiver checkouts and doing pointing runs to familiarize them with the software

Test Stage I (Winter 2006/2007)

  • Choose a subset of projects for Phase I testing, get observer's agreement
  • We should choose 2 two week periods for the tests, seperated by approximately 1 month; ideally these tests will be somtime between December - early febuary
  • The system will be run as outlined in the proposal, with the exception that an extra person will be on hand at all times to insure that the dynamic scheduling program runs accurately and the system is running as it should be.

Redesign Proposal for Stage II (Winter - Spring 2007)

  • Redesign should begin as soon as tests are underway
  • Proposal for completion of redesign should be written as soon as possible after the tests
  • External review should happen in by June
  • Proposal will be sent to all NRAO staff at this time also
  • During this time the PST must be re-designed to accomodate any metadata needed in the proposing process (e.g. weather queue info)

Build Stage II System (Spring - Fall 2007)

  • Rebuilding of system should begin as soon as possible
  • Must be complete by Feb 1, 2008, with prototypes (at least) in place by Fall, 2007
  • Will include all necessary software for dynamic scheduling
  • Will likely not include all desired software for dynamic scheduling

Test Stage II (Fall/Winter 2007)

  • The Feb 1 proposal period should include all information needing for dynamic scheduling
  • Proposers should be asked if they would like to participate in testing in the fall

Begin Dynamic Scheduling (Winter 2007 - onwards)

  • The Oct 1 call for proposals should state that all proposals will be dynamically scheduled

Redesign Proposal for Stage III (Spring 2008)

  • This may include removing most peak, focus, and even calibration observations from the project SBs
  • Will include the addition of ease of use software
>
>

Stage I

  • This is the proof of concept stage
  • This stage will consist of prototype software used to simulate and test the basic concepts behind dynamic scheduling
  • During this stage we will also develop all documentation needed to continue on to Stage II
  • This stage will end with an external review of the project plans

Stage II

  • This will be the first real test of the dynamic scheduling software
  • The tests need to involve a large number and variety of projects to insure the DSS is accurately tested
  • As with all stages, simulations will also play a large role here

Stage III

  • The goal here is to complete all tools needed to begin dynamic scheduling on the GBT
  • At this point there will likely be many tools and additions which are desired for ease-of-use, but which are not necessary for the system to work

Stage IV

  • This will be modifications and additions to the Stage III DSS
  • The complete description of desired changes and additions will be made once Stage III has been run for at least 1 semester
  • During this stage we will also implement the highest priority items remaining from the ease-of-use list
Changed:
<
<

Build Stage III System (Summer-Fall 2008?)

  • Completing any/all issues for the complete software suite:
>
>


Milestones

Changed:
<
<

Test Stage III (Fall/Winter 2008?)

>
>

Develop Strawman Proposal (Summer 2006)
Original Date Goal Date Completed
July 2006 Interface with JCMT, other telescopes to determine dynamic scheduling lessons" 24 July, 2006
1 June, 2006 Complete strawman proposal for dynamic scheduling system 13 June, 2006
1 June, 2006 Present proposal to the GB staff and outside observers for comments 21 June, 2006
31 August, 2006 Modify proposal based on comments received 01 September, 2006
Stage I System (Fall/ Winter 2006)
15 Nov, 2006 Complete overview, selection rules for Stage I 28 Nov, 2006
22 Dec, 2006 Complete description of software suite  
22 Dec, 2006 Complete plans for Stage I tests  
1 Jan, 2007 Call for Sept, 2007 proposals  
1 Feb, 2007 Complete documentation on desired PST changes  
1 Feb, 2007 Deadline for Sept, 2007 proposals  
??? Run Stage I tests (simulation)  
??? Modify documentation & based off simulation results  
??? External Review  
Stage II System (Spring/Summer 2007)
??? Rewrite documentation/plans based off external review  
01 Aug, 2007 Complete Stage II software & documentation  
01 Sept, 2007 Begin Stage II tests  
01 Sept, 2007 Winter, 2008 proposal call, PST changes in place  
01 Oct, 2007 Winter, 2008 proposals due  
30 Sept, 2007 Complete Stage II tests  
Stage III System (Fall/Early Winter 2007)
01 Jan, 2008 Complete Stage III software and documentation  
15 Jan, 2008 Complete Stage III simulation tests  
31 Jan, 2008 Complete Stage III modifications  
01 Feb, 2008 Release Stage III software for general use  
Stage IV System (Winter 2007 – Winter 2008)
June, 2008 Analyze results from Winter trimester  
Fall, 2008 Complete Stage IV modifications  
01 Sept, 2008 Winter, 2009 proposal call, PST changes in place  
01 Oct, 2008 Winter, 2009 proposals due  
01 Jan, 2009 Begin Stage simulation tests  
31 Jan, 2009 Complete Stage III modifications  
01 Feb, 2009 Release Stage IV software for general use  
Deleted:
<
<

Release Stage III (Winter 2009?)


 <<O>>  Difference Topic ActionPlan (r1.12 - 11 Oct 2006 - RichardPrestage)
Changed:
<
<

  • Long term goal is to have true dynamic scheduling on the GBT which eases the support burden and which results in high frequency projects being completed more rapidly than is currently (2005) possible.
>
>

  • Long term goal is to have true dynamic scheduling on the GBT which eases the support burden and which results in high frequency projects being completed more rapidly than is currently (2006) possible.

 <<O>>  Difference Topic ActionPlan (r1.11 - 11 Oct 2006 - KarenONeil)
Changed:
<
<

Build Stage I System (Summer/Fall 2006)

>
>

Build Stage I System (Summer/Fall/Early Winter 2006)

Changed:
<
<

  • Proposal for completion of redesign should be written by mid-March
  • External review should happen in late March
>
>

  • Proposal for completion of redesign should be written as soon as possible after the tests
  • External review should happen in by June
Changed:
<
<

Build Stage II System (Spring - Summer 2007)

  • Rebuilding of system should begin April 1
  • Must be complete by Oct 1
  • Software needed for Stage II are version 1 of:
    • Query Tool
    • Time Accounting Tool
    • Web fedback page
    • Metadata tool
    • Running SBs Tool
    • Observer/Staff Feedback Tool
  • Software desired for Stage II:
    • Tool for building SBs
    • Observing Log
    • Time Accounting Tool - complete version
>
>

Build Stage II System (Spring - Fall 2007)

  • Rebuilding of system should begin as soon as possible
  • Must be complete by Feb 1, 2008, with prototypes (at least) in place by Fall, 2007
  • Will include all necessary software for dynamic scheduling
  • Will likely not include all desired software for dynamic scheduling
Changed:
<
<

Test Stage II (Fall 2007)

  • The June 1 proposal period should include all information needing for dynamic scheduling
>
>

Test Stage II (Fall/Winter 2007)

  • The Feb 1 proposal period should include all information needing for dynamic scheduling
Added:
>
>

  • Will include the addition of ease of use software
Deleted:
<
<

  • Tool for building SBs
    • Query Tool
    • Observing Log
    • Time Accounting Tool
    • Web fedback page
    • Metadata tool
    • Data Reduction
    • Quick Look Data Display
    • Running SBs Tool
    • Observer/Staff Feedback tools
Changed:
<
<

Test Stage III (Fall 2008?)

>
>

Test Stage III (Fall/Winter 2008?)

Changed:
<
<

Release Stage III (Winter 2008?)

>
>

Release Stage III (Winter 2009?)


 <<O>>  Difference Topic ActionPlan (r1.10 - 06 Oct 2006 - KarenONeil)
Changed:
<
<

Dynamic Scheduling Tasks

>
>

Goals, Objectives, and Schedule

Added:
>
>


Goals

  • Long term goal is to have true dynamic scheduling on the GBT which eases the support burden and which results in high frequency projects being completed more rapidly than is currently (2005) possible.
  • All telescope activities, including science, commissioning, tests and maintenance are flexibly scheduled to:
    • Optimize use of high-frequency weather.
    • Enable timely completion of projects.
  • Achieve efficient fixed scheduling of crucial maintenance activities, VLBI/bi-static radar or other observations that require coordination with other facilities, and monitoring projects.
  • All observations are performed by the execution of Scheduling Blocks (SBs) which have been defined in advance.


Objectives

  • Demonstrate increased flexibility from previous manual dynamic scheduling approach
    • High frequency projects should be completed more rapidly than is currently occuring - Is there a metric we can use to judge this?
    • We should have fewer problems finding sufficient low frequency projects for the telescope - Is there a metric we can use to judge this?
  • Demonstrate increased flexibility from previous software tools and applications
    • Eliminate GO as a production tool by October 1, 2005. DONE
    • Other???


Schedule


 <<O>>  Difference Topic ActionPlan (r1.9 - 13 Jun 2006 - KarenONeil)
Added:
>
>

  • Proposal will be sent to all NRAO staff at this time also

 <<O>>  Difference Topic ActionPlan (r1.8 - 08 Jun 2006 - KarenONeil)
Added:
>
>

    • Prototype User/Staff Feedback tool
Added:
>
>

    • Observer/Staff Feedback Tool
Added:
>
>

Added:
>
>

    • Observer/Staff Feedback tools

 <<O>>  Difference Topic ActionPlan (r1.7 - 07 Jun 2006 - KarenONeil)
Changed:
<
<

  • Write all software needed for the 2006/2007 tests:
>
>

  • Write all software needed for the 2006/2007 tests. Note that all software for tests should be considered prototype and will be rewritten for Stage II. As such, this software could be very simplistic.:
Changed:
<
<

  • This includes determining all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed
>
>

  • Write documentation for all weather queue information
  • This includes determining all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 6-7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed
Changed:
<
<

  • We should choose 2 two week periods for the tests, seperated by approximately 1 month; ideally these tests will be in mid-january and mid-febuary
>
>

  • We should choose 2 two week periods for the tests, seperated by approximately 1 month; ideally these tests will be somtime between December - early febuary
Changed:
<
<

  • During this time the PST must be re-designed to acomoadate all information needed for dynamic scheduling
>
>

  • During this time the PST must be re-designed to accomodate any metadata needed in the proposing process (e.g. weather queue info)

 <<O>>  Difference Topic ActionPlan (r1.6 - 01 Jun 2006 - KarenONeil)
Changed:
<
<

  • Write all software needed for the 2006/2007 tests
  • Train select group of astronomers (and oeprators?) for using Phase I
  • This includes determinetermine ing all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed
>
>

  • Write all software needed for the 2006/2007 tests:
    • Prototype query tool
    • Prototype time accounting tool
    • Prototype Metadata tool
  • Train select group of astronomers (and operators) for using Stage I system
  • This includes determining all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed
Added:
>
>

  • Software needed for Stage II are version 1 of:
    • Query Tool
    • Time Accounting Tool
    • Web fedback page
    • Metadata tool
    • Running SBs Tool
  • Software desired for Stage II:
    • Tool for building SBs
    • Observing Log
    • Time Accounting Tool - complete version
Deleted:
<
<

Added:
>
>

* Completing any/all issues for the complete software suite:

    • Tool for building SBs
    • Query Tool
    • Observing Log
    • Time Accounting Tool
    • Web fedback page
    • Metadata tool
    • Data Reduction
    • Quick Look Data Display
    • Running SBs Tool

 <<O>>  Difference Topic ActionPlan (r1.5 - 25 May 2006 - KarenONeil)
Deleted:
<
<

  • Complete proposal for testing the system in the 2006/2007 winter season
Added:
>
>

  • We should choose 2 two week periods for the tests, seperated by approximately 1 month; ideally these tests will be in mid-january and mid-febuary
  • The system will be run as outlined in the proposal, with the exception that an extra person will be on hand at all times to insure that the dynamic scheduling program runs accurately and the system is running as it should be.
Changed:
<
<

  • External review should happen about mid-way through this
>
>

  • Redesign should begin as soon as tests are underway
  • Proposal for completion of redesign should be written by mid-March
  • External review should happen in late March
  • During this time the PST must be re-designed to acomoadate all information needed for dynamic scheduling
Added:
>
>

  • Rebuilding of system should begin April 1
  • Must be complete by Oct 1
Added:
>
>

  • The June 1 proposal period should include all information needing for dynamic scheduling
  • Proposers should be asked if they would like to participate in testing in the fall
Added:
>
>

  • The Oct 1 call for proposals should state that all proposals will be dynamically scheduled

 <<O>>  Difference Topic ActionPlan (r1.4 - 16 May 2006 - KarenONeil)
Added:
>
>

  • Begin operator training for, e.g. running receiver checkouts and doing pointing runs to familiarize them with the software
Added:
>
>

  • This may include removing most peak, focus, and even calibration observations from the project SBs

 <<O>>  Difference Topic ActionPlan (r1.3 - 11 May 2006 - RichardPrestage)
Changed:
<
<

  • Interface with JCMT, other telescopes to determine synamic scheduling "lessons"
>
>

  • Interface with JCMT, other telescopes to determine dynamic scheduling "lessons"

 <<O>>  Difference Topic ActionPlan (r1.2 - 08 May 2006 - KarenONeil)
Changed:
<
<

Dynamic Scheduling Tasks

>
>

Dynamic Scheduling Tasks

Changed:
<
<

  • Present proposals to the GB staff for comments.
>
>

  • Present proposals to the GB staff and 2 outside observers (1 LF anf 1 HF) for comments.
Changed:
<
<

Build Phase I System

>
>

Build Stage I System (Summer/Fall 2006)

Changed:
<
<

Test Phase I

>
>

Test Stage I (Winter 2006/2007)

Changed:
<
<

Redesign Proposal for Phase II

>
>

Redesign Proposal for Stage II (Winter - Spring 2007)

  • External review should happen about mid-way through this
Changed:
<
<

Build Phase II System

>
>

Build Stage II System (Spring - Summer 2007)

Changed:
<
<

Test Phase II

>
>

Test Stage II (Fall 2007)

Changed:
<
<

Begin Dynamic Scheduling

>
>

Begin Dynamic Scheduling (Winter 2007 - onwards)

Redesign Proposal for Stage III (Spring 2008)

Build Stage III System (Summer-Fall 2008?)

Test Stage III (Fall 2008?)

Release Stage III (Winter 2008?)

Deleted:
<
<

We have no external review scheduled. Should we do this (probably)? When?


 <<O>>  Difference Topic ActionPlan (r1.1 - 02 May 2006 - KarenONeil)
Added:
>
>

%META:TOPICINFO{author="KarenONeil" date="1146567313" format="1.0" version="1.1"}% %META:TOPICPARENT{name="WebHome"}%

Dynamic Scheduling Tasks

Develop Phase I Proposal:

  • Interface with JCMT, other telescopes to determine synamic scheduling "lessons"
  • Determine all selection requirements
  • Complete strawman proposal for dynamic scheduling system
  • Complete proposal for testing the system in the 2006/2007 winter season
  • Present proposals to the GB staff for comments.
  • Modify strawman proposal based on comments receive

Build Phase I System

  • Write all software needed for the 2006/2007 tests
  • Train select group of astronomers (and oeprators?) for using Phase I
  • This includes determinetermine ing all weather and other (e.g. project observability, hardware requirements, etc) requirements for each project. Also in Cycle 7 we will choose a subset for projects for testing dynamic scheduling, get agreement from observers; begin training staff as needed

Test Phase I

  • Choose a subset of projects for Phase I testing, get observer's agreement

Redesign Proposal for Phase II

Build Phase II System

Test Phase II

Begin Dynamic Scheduling

We have no external review scheduled. Should we do this (probably)? When?

-- KarenONeil - 02 May 2006


Topic ActionPlan . { View | Diffs | r1.20 | > | r1.19 | > | r1.18 | More }
Revision r1.1 - 02 May 2006 - 10:55 GMT - KarenONeil
Revision r1.20 - 07 Sep 2007 - 15:13 GMT - KarenONeil