| Item | Priority | Software Status | Astronomy Status | Comments |
| Weather History | 1 | | | Dana working on this; his input is needed before the SDD group can start |
| Current Weather | 1 | | | Dana will work on this after the weather history; His input is needed before the SDD group can start |
| Observer Contact/Schedule | 2 | | | Astronomer input is needed here before the SDD can go further.Karen will begin work ASAP. |
| Fixed/Window calendar display | 2 | | N/A | To be completed after the SDD statistical analysis is done |
| User's Handbook | N/A | | Larry is working on this |
| Complete database fields | 1 | | N/A | Amy and Paul are working on this with completing the backlog |
| Clean up (crud 2.0) | 2 | | N/A | TBD after SDD statistical analysis |
| Statistical Analysis | 1 | | | Mike and Mark are working on this; Dana's work cannot start until they are done |
| Project Sessions audit | ? | ? | ? | What is this? |
| Basic Security | 3 | | N/A | Need two log-ins: One for all projects and one for the scheduling pages |
| Complete Backlog | 1 | | N/A | Paul and Amy are working on this with the database completion |
| Update time from Carl's database | 3 | | N/A | Needs to be done at the end of May |