Last Week
=========
Observations for proposals
GBT06A-054, GBT06C-053, GBT06C-032,
GBT06C-021, GBT05C-042, BU031 ,
GBT06A-014, GBT06B-047, GBT06B-015,
GBT06C-048, GBT05C-037, GBT06C-049,
GBT06C-039, GBT06C-018, GBT06B-019
Completed proposals
GBT05C-042, BU031, GBT06B-047,
GBT05C-037
Next Week
=========
Observations scheduled for **
GBT06C-051 [ P ] Lincoln Greenhill
Monitoring 2 NGC4258-like Masers: Measurement of
Distances / Constraint of LCDM
GBT06A-053 [ B] Scott Ransom
Continued Timing of the Binary and Millisecond
Pulsars in Terzan 5
GBT06C-053 [ B] Martin Zwaan
A search for molecules in CaII absorbers
GBT06C-021 [ P ] Erik Rosolowsky
A COMPLETE Census of Dense Cores in Perseus
GBT06C-032 [F B] Peter Martin
The Galactic foreground at the North Ecliptic Pole
GBT04C-031 [ P ] Paul Kondratko
Monitoring of Five NGC4258-like Water Megamasers
Discovered with the GBT and the DSN
GBT06C-035 [FP ] Jim Braatz
The Megamaser Cosmology Project: A Survey for H2O
Maser Disks in SDSS AGNs
GBT06B-037 [F ] Joel Weisberg
Probing the Small-Scale Structure of Molecular
Gas with Pulsar B1641-45
GBT06C-036 [ P ] Claudia Cyganowski
Radio mapping of infrared interstellar bubbles
GBT06C-048 [ B] Nissim Kanekar
HI 21cm absorption in strong MgII and CI
absorbers in the redshift desert
GBT06C-037 [ P ] Charlie Lada
Probing the Origin of Dense Cores and the Stellar
IMF
GBT06C-049 [ B] Karen Masters
Mapping Matter in the Nearby Universe with 2MASS
GBT06C-018 [F B] Ingrid Stairs
Continued timing of a highly relativistic binary
pulsar system
** Scheduled as F-ixed, P-rimary, B-ackup
Contact Information for 10/19/2006 - 11/02/2006
=======================================
Proposal PI Bands Email [NRAO contact]
---------- ------------------ ----- --------------------
GBT06A-054 Paul Demorest 8 demorest@astron.berkeley.edu [Scott Ransom]
GBT06A-065 Rachel Friesen K rfriesen@uvastro.phys.uvic.ca [Toney Minter]
GBT06B-042 Nissim Kanekar 4 nkanekar@nrao.edu [Larry Morgan]
GBT06C-021 Erik Rosolowsky K erosolow@cfa.harvard.edu [Ron Maddalena]
GBT06B-044 Robert Ferdman L ferdman@phas.ubc.ca [Scott Ransom]
GBT06C-032 Peter Martin L pgmartin@cita.utoronto.ca [Jay Lockman]
GBT06C-055 Martin Zwaan 6 mzwaan@eso.org [Larry Morgan]
GBT06C-011 Steve Curran L sjc@phys.unsw.edu.au [Carl Bignell]
GBT06A-014 Andrea Tarchi K a.tarchi@ira.inaf.it [Jim Braatz]
GBT06C-023 Bruce Campbell 4 campbellb@si.edu [Frank Ghigo]
GBT06C-012 Steve Curran L sjc@phys.unsw.edu.au [Carl Bignell]
GBT06C-035 Jim Braatz K jbraatz@nrao.edu [Jim Braatz]
GBT06C-036 Claudia Cyganowski K ccyganow@astro.wisc.edu [Toney Minter]
GBT06B-037 Joel Weisberg L jweisber@carleton.edu [Toney Minter]
GBT06C-037 Charlie Lada K clada@cfa.harvard.edu [Frank Ghigo]
GBT06C-048 Nissim Kanekar 4 nkanekar@nrao.edu [Toney Minter]
GBT06C-027 Walter Brisken K wbrisken@nrao.edu [Frank Ghigo]
GBT06C-016 Fernando Camilo S fernando@astro.columbia.edu [Scott Ransom]
GBT06C-049 Karen Masters L kmasters@cfa.harvard.edu [Larry Morgan]
GBT06C-039 Jim Braatz K jbraatz@nrao.edu [Jim Braatz]
GBT06B-018 Michael Kramer 8 mkramer@jb.man.ac.uk [Scott Ransom]
GBT06C-028 Brenda Matthews K brenda.matthews@nrc-cnrc.gc.ca [Ron Maddalena]
GBT06C-006 Wouter Vlemmings K wouter@jb.man.ac.uk [Frank Ghigo]
BM251 Neal Miller L nmiller@pha.jhu.edu []
GBT06C-008 Raghunathan Sriana 4 anand@iucaa.ernet.in [Toney Minter]
Scheduled hours [backup]
========================
Category/Month-> October November December January
Astronomy ~ 519 [468] 450 [373] 536 [319] 561 [345]
Maintenance ~ 83 [017] 45 [051] 52 [034] 55 [068]
Test & Comm ~ 124 172 [007] 82 54 [016]
Shutdown ~ 0 36 36 0
Un-assigned ~ 23 19 43 82
Proposal Checkouts
==================
Awaiting checkout - 0
Active checkout - 0
On Hold - 16
Schedule - 81
Completed - 555
Current backlog [hours prior to 06C*] = 1014
[2001:2(1), 2003:19(1), 2004:107(7), 2005:471(20), 2006:415(23)]
Backlog excluding 800 hrs of monitoring projects after 06C = 214
Total time to discharge [hours] = 3104
Includes 1056 hours of monitoring after trimester 06C
* Includes projects that are on hold for trimester 06C
|
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.6 - 06 Oct 2006 - BobAnderson) |
| Added: | |
| > > |
|
| Added: | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.5 - 06 Oct 2006 - RogerNorrod) |
| Deleted: | |
| < < | |
| Added: | |
| > > | Nothing other than routine work. |
| Added: | |
| > > | Q-band Receiver: Measurements of noise temperature and cal values, and gathering additional spectrometry data occupied the week. Scientific staff seem pretty happy with the spectral performance. Ka Receiver/Zpectrometer: Most of this week occupied with Zpectrometer tests. It still looks go for next week's installation. Other: C-band project still going well. Upgrades to the Converter/Filter modules continue, and fabrication of the buffered Optical Receiver dividers in process. |
| Changed: | |
| < < |
|
| > > |
|
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.4 - 06 Oct 2006 - RandyMcCullough) |
| Added: | |
| > > | Digital Group Status 30-SEP-06 THRU 06-OCT-06 |
| Changed: | |
| < < |
Operations, Problem Summary |
| > > | ***Operations, Problem Summary*** |
| Changed: | |
| < < |
Development |
| > > |
Active Surface...
No work was done on the Active Surface this week.
Quadrant Detector...
|
| Changed: | |
| < < |
Plans |
| > > | Randy |
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.3 - 06 Oct 2006 - RonMaddalena) |
| Added: | |
| > > |
A very good, productive week. We supported 16 proposals in 25 observing sessions, including a VLB run. Average setup time was 12 min (this will be the last time I will report this statistic). The telescope was scheduled for 14 hrs of maintenance, 7 hrs of PAR commissioning, and 1.5 hrs of receiver checkouts.
We had only 5 problems this week for a total of 1.7 hrs, about 1.1% of the time scheduled for tests and observing.
|
| Added: | |
| > > |
Commissioning Plans -- RonThis week, we removed Ku and repositioned X-band where Ku. This was ahead of our original plans. There were no other changes to the scheduling of any commissioning tasks. All seems to be on schedule for the Ka-band installation next week and Q-band installation the week after that.
Receiver Installation Schedules
|
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.2 - 05 Oct 2006 - GlenLangston) |
| Added: | |
| > > | Normal Spacecraft tracking continues. Completed quarterly report and preparing annual property inventory. 2007 and 2008 statement of work is being reviewed by MIT/LL. Preparing list of spacecraft tracking projects for review. |
| <<O>> Difference Topic CommissioningMeeting06Oct06 (r1.1 - 05 Oct 2006 - AmyShelton) |
| Added: | |
| > > |
%META:TOPICINFO{author="AmyShelton" date="1160076300" format="1.0" version="1.1"}%
%META:TOPICPARENT{name="CommissioningMeetings"}%
GBT Operations & Commissioning Meeting06 October 2006AGENDA
Az Track, Antennae Report -- BobObserving News -- RonScheduling Status -- CarlMicrowave Electronics Status -- RogerOperationsDevelopmentDigital Electronics Status -- RandyOperations, Problem SummaryDevelopmentPlansSoftware Status -- PaulThis ends the 1st week of 6 in the seventh development cycle of 2006 which can be viewed at PlanOfRecordC72006. We are scheduled to release at the end of January 2007. Items deemed ready for release before that time will be patched in after they have been fully tested. Operational support kept us relatively busy this week and included:
Pulsar Related -- ScottMIT/LL 43m Project -- GlenAny other Business |
| Topic CommissioningMeeting06Oct06 . { View | Diffs | r1.7 | > | r1.6 | > | r1.5 | More } |
|
Revision r1.1 - 05 Oct 2006 - 19:25 GMT - AmyShelton Revision r1.7 - 11 Oct 2006 - 11:50 GMT - CarlBignell |
Content copyright © 1999-2007 by the contributing authors. All material on this collaboration platform is the property of the contributing authors. |