  • Eric Sessoms was here this week
  • Software group worked on:
    • completing statistical reports for Dana to compare new software with proto version
    • New calendar view to help e.g. Carl with planning recevier changes, fixed sessions, etc; New view shows conflicts, relations amid windowed sessions, etc
    • Working on reorganizing and enhancing the editing of the project related information page
    • Upgraded antioch and nell for the new versions of python and TurboGears?/SQLAlchemy
  • Project meeting cancelled due to KFPA meeting
  • Current concerns
    • We need significantly more astronomy effort to pull together e.g. user's manual within the next couple months.

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.11 - 29 Feb 2008 - BobAnderson)
Changed:
<
<

>
>

Routine maintenance this week.


 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.10 - 29 Feb 2008 - MartyBloss)
Added:
>
>

  • Items/actions completed:
    • Two iterations of sponsor tests
    • Assignment and analysis work on defects raised during last round of sponsor tests.
  • Decisions made:
    • Identified the hardware work to be undertaken when the instrument is removed from telescope
  • Near-term activities (next ~2 weeks):
    • Finalize GB involvement in summer work on MUSTANG
  • Issues:
    • Small leak in cryogenics system has required two “top-offs” of helium. Simon wants to procure and install better hoses between the turret and the cryostat during summer maintenance
Changed:
<
<

PTCS program -- John

>
>

PTCS program -- Marty

Added:
>
>

    • Second round deployment straw-man review
    • Established initial servo project documentation plan

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.9 - 29 Feb 2008 - ToddHunter)
Changed:
<
<

>
>

  • Servo
  • Pointing
    • Obtained Matlab licenses needed to run pointing model on the ptcs workstation. Currently under test.
  • OOF holography
    • Heterodyne: Processed the first 4-band maps from 2008 Ka/CCB data using the new software path under development.
    • Mustang: Obtained Bill Cotton's "obit" processing of Mustang OOF scans. Need to convert it to OOF software input format.
  • Traditional holography
    • Analyzed maps from 2004-Feb-18 to confirm bookkeeping error in central row of 45 actuators.

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.8 - 29 Feb 2008 - RonMaddalena)
Added:
>
>

We supported 17 projects in 32 observing sessions including a few radar runs and a VLB run. The telescope ws also scheduled for 8 hrs of maintenance and 2 hrs of servo tests. Los time was 16.4 hrs (10.4%), of which 12.7 hrs was due to the weather. Sources of lost time were:

  • Freezing rain (3 instances) - 7.6 hrs
  • Snow (3 instances) - 5.1 hrs
  • Arecibo Transmitter (2 instances) - 1.6 hrs
  • Spectral Processor (4 instances) - 0.7 hrs
  • Archivist (5 instances) - 0.4 hrs
  • Human (wrong receiver) - 0.3 hrs
  • Astrid (3 instances) - 0.3 hrs
  • Others (Mustang manager, Spectrometer, Turret lock) - 0.5 hrs
thus, only about 2 hrs of the lost time were under our control.
Changed:
<
<

>
>

No Commissioning news to report that isn't reported elsewhere.


 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.7 - 28 Feb 2008 - GlenLangston)
Added:
>
>

  • Extensive tests of 43m HA-Dec interface files and defintions. We've taken some GPS data that are being analyzed.
  • More pointing tests Feb 29 and March 1.
  • Phil Erickson, Eric Phelps, Mike Shields (and others) and I met to discuss plans for extensive polarization mapping with the 43m in the frequency range 150 to 400 MHz.
  • Normal Spacecraft tracking.

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.6 - 28 Feb 2008 - RandyMcCullough)
Added:
>
>

Jason and J.D. took Pete Whiteis up to the Actuator Room to familiarize him with the hardware involved with the Active Surface System. While there, they experienced a problem wherein the "Master Monitor" stopped running. To correct this problem, they simply rebooted the system; which afforded Pete an excellent opportunity to see, first-hand, a real software issue which happens fairly often.


 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.5 - 28 Feb 2008 - ChrisClark)
Changed:
<
<

>
>

The allied Telesyn switch in the servo room failed 3 times in the last week. The spare switch has been installed pending the arrival of permanent replacement parts.


 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.4 - 28 Feb 2008 - AmyShelton)
Added:
>
>

Added:
>
>

  • No new items this week.

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.3 - 28 Feb 2008 - StevenWhite)
Added:
>
>

  • Nothing to report
Added:
>
>

  • Successful completion of the CDR this week with approval of the panel to proceed.
  • A report is expected early next week.

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.2 - 28 Feb 2008 - CarlBignell)
Changed:
<
<

Activities List

>
>

Activities List

Added:
>
>

Last Week =====

Added:
>
>

Observations for proposals BB240 , GBT08A-086, GBT08A-032, GBT05A-040, GBT08A-065, GBT07A-066, GBT08A-056, GBT08A-034, GBT08A-057, GBT08A-014, GBT06C-033, GBT07B-025, GBT07A-029, GBT07B-029, GBT08A-083, GBT07A-040, GBT07A-051, GBT07C-060

Completed proposals GBT08A-086, GBT08A-032, GBT08A-065, GBT08A-034

Next Week ===== Observations scheduled for ** BB240 [F ] Geoff Bower RIPL: Radio Interferometric PLanet Search GBT07C-084 [ B] Laura Kasian GBT Timing of a Young Highly Relativistic Binary Pulsar GBT05A-040 [ P ] Andrew Baker CO(1-0) Observations of Four Submillimeter Galaxies GBT08A-011 [ B] Maura McLaughlin? Continued Radio Timing Observations of RRAT Sources GBT08A-077 [ B] Fernando Camilo Studying the magnetar XTE J1810-197 GBT07A-087 [F B] Paul Demorest Detecting nHz Gravitational Radiation using a Pulsar Timing Array GBT07A-066 [FP ] Jim Braatz The Megamaser Cosmology Project GBT08A-057 [ B] Jennifer Donovan A Continuing Search for Wet Mergers in a Dry Sample GBT07C-033 [ B] Jason Hessels Follow-up Studies of Recent GBT Pulsar Discoveries GBT08A-058 [ B] Léo Barriault GBT OH Observations at high galactic latitudes GBT07B-034 [ B] Robert Ferdman Timing Binary and Millisecond Pulsars from the Parkes Multibeam Survey GBT08A-014 [F B] Jay Lockman On the Trail of Smith's Cloud GBT06C-033 [ P ] Andy Harris A CO(1-0) Survey of Dusty Galaxies with Elusive Redshifts GBT07C-024 [ P ] Nami Sakai Carbon-Chain Anions in Low-mass Star Forming Region, L1527 GBT08A-006 [ B] Tom Bania Solving "The 3-Helium Problem" GBT08A-018 [ P ] Nami Sakai Production Pathways of Sulfur-Bearing Carbon-Chain Molecules GBT05C-035 [ P ] Andrew Baker Very Good CO Detections of Submillimeter Galaxies With Pretty Good Redshifts GBT07A-029 [F ] Dick Crutcher A Definitive Test of Star Formation Theory GBT07C-060 [ B] Fernando Camilo GLAST timing at GBT: six key radio-faint pulsars GBT07A-040 [ P ] Larry Weintraub Detecting the Origin of Arcminute Scale CMB Anisotropy ** Scheduled as F-ixed, P-rimary, B-ackup

Contact Information for 03/13/2008 - 03/27/2008 =================================== Proposal PI Bands Email [NRAO contact]


------------------ ----- -------------------- GBT07C-072 Marcel Agueros 8 agueros@astro.washington.edu [Scott Ransom] BB240 Geoff Bower X gbower@astro.berkeley.edu [] GBT07C-084 Laura Kasian LS kasian@physics.ubc.ca [Scott Ransom] GBT08A-076 Nissim Kanekar 4 nkanekar@nrao.edu [Paul Ruffle] GBT07C-030 Joel Bregman K jbregman@umich.edu [D.J. Pisano] GBT08A-077 Fernando Camilo S fernando@astro.columbia.edu [Scott Ransom] GBT07A-087 Paul Demorest S pdemores@nrao.edu [Scott Ransom] GBT07B-020 Ingrid Stairs L stairs@astro.ubc.ca [Scott Ransom] GBT07A-066 Jim Braatz K jbraatz@nrao.edu [Jim Braatz] GBT08A-056 Simon Dicker P simon.dicker@gmail.com [Brian Mason] GBT07C-033 Jason Hessels 38 jhessels@science.uva.nl [Scott Ransom] GBT07A-101 Clive Dickinson B cdickins@astro.caltech.edu [Brian Mason] GBT08A-058 Léo Barriault L leo.barriault.1@ulaval.ca [Jay Lockman] GBT06C-033 Andy Harris B harris@astro.umd.edu [Karen O'Neil] GBT08A-006 Tom Bania X bania@bu.edu [Dana Balser] GBT08A-018 Nami Sakai K nami@taurus.phys.s.u-tokyo.ac.jp [Larry Morgan] GBT07C-049 Jaime Pineda K jpineda@cfa.harvard.edu [Jules Harnett] GBT07A-029 Dick Crutcher L crutcher@uiuc.edu [Toney Minter] GBT07B-029 Michael Kramer 8 mkramer@jb.man.ac.uk [Scott Ransom] GBT08A-082 Min Yun L myun@astro.umass.edu [Jules Harnett] BM270 James Miller-Jones X jmiller@nrao.edu [] GBT07A-051 Mike Hollis 3468A jan.m.hollis@nasa.gov [Larry Morgan] GBT07C-060 Fernando Camilo S fernando@astro.columbia.edu [Scott Ransom]

Scheduled hours [backup] ==================== Category/Month-> February March April May Astronomy ~ 599 659 [554] 622 [480] 599 [361] Maintenance ~ 51 4 [102] 9 [102] 42 [051] Test & Comm ~ 49 52 [034] 56 [040] 43 [032] Un-assigned ~ 0 30 34 60

Proposal Checkouts #[hrs]* ===================== Awaiting checkout - 0[0] Active checkout - 0[0] On Hold - 0[0] Schedule - 114[3031] Completed - 537[6566] * All but completed queue applies to GBT only proposals

Current backlog of Reg & RRS proposals [hours prior to 08A*] = 1415 [2005:78(5), 2006:263(10), 2007:1074(45)] Backlog includes 67 hrs of monitoring projects 292 hrs of vlbi projects Total time to discharge [hours] = 4834 Includes 114 hours++ of monitoring (not Large or Spec) after trimester 08A

        1. hours of Regular & RRS proposals
        2. hours of Large proposals
        3. hours of VLBI proposals
* Includes projects that are on hold for trimester 08A ++ Time is counted in other break down as well. 08A

 <<O>>  Difference Topic CommissioningMeeting08Feb29 (r1.1 - 28 Feb 2008 - RonMaddalena)
Added:
>
>

%META:TOPICINFO{author="RonMaddalena" date="1204231091" format="1.0" version="1.1"}%

GBT Operations & Commissioning Meeting

29 Feb 2008

GB137 and by video-con from CV-Conf

AGENDA


Upcoming Activities -- Carl

Activities List


Operations


Scheduling Status -- Carl



Observing News -- Ron


Commissioning Plans -- Ron


GBT Telescope Operations -- Bob


Mechanical Division Operations -- Dennis


Microwave Electronics Operations -- Steve


Digital Electronics Operations -- Randy


RFI Group Operations -- Carla


Software Operations -- Amy


Computing and Network Operations -- Chris


Business Services -- Mike


43m Operations -- Glen


Project and Development Work


Dynamic Scheduling -- Karen


MUSTANG -- Brian


PTCS program -- John


CICADA program -- John


Ka-band Rx / Zpectrometer -- Galen


K-band Focal Plane Array -- Steve


Other Project Notes


Any other Business

-- RonMaddalena - 28 Feb 2008


Topic CommissioningMeeting08Feb29 . { View | Diffs | r1.13 | > | r1.12 | > | r1.11 | More }
Revision r1.1 - 28 Feb 2008 - 20:38 GMT - RonMaddalena
Revision r1.13 - 29 Feb 2008 - 14:30 GMT - DennisEgan
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.