| > > | Allied Telesyn switches are removed and a new rack of media converters are in place in the servo room. Basement student room "wiring" proceeds apace, will be ready in good time for the summer students. Other basement offices will be wired soon. |
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.13 - 14 Mar 2008 - DennisEgan) |
| Added: | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.12 - 14 Mar 2008 - KarenONeil) |
| Changed: | |
| < < | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.11 - 14 Mar 2008 - GalenWatts) |
| Changed: | |
| < < | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.10 - 14 Mar 2008 - GlenLangston) |
| Added: | |
| > > |
From Mike Shields; On our agenda is the following:
1) - remove Chalmers feed and Feed Box
a) remove some electronics in Feed box
b) cut access hole in box to remove cryo-cooler, replace with cooler
with spare (NRAO) - we need to make sure the spare cooler is at NRAO.
c) - re-install electronics and test Feed box
d) - install feed box and high frequency feed into 43m
e) - measure Chalmers feed on NRAO range
f) - ship Chalmers feed to Lincoln Lab
2) - repair partially failed amplifiers in trailer
3) - review performance of system and repair / replace components as needed
4) - measure / adjust phase match of corresponding V & H channels in trailer
5) - back-up and inventory software on computer disks in trailer
6) - reconfigure trailer firewall
7) - install new KVM switch
8) - at end of second week, characterize amplitude and phase of receiver
|
| Added: | |
| > > |
|
| Changed: | |
| < < | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.9 - 14 Mar 2008 - RonMaddalena) |
| Added: | |
| > > |
A rather complicated week to report on. We supported 17 projects in 32 observing sessions. The telescope was also scheduled for 19 hrs maintenance, 4.5 hrs of Mars Phoenix tests, 4 hrs of PTCS servo tests, 3.5 hrs of SCAL/RFI scans, and 1 hrs for receiver checkout. We were at half speed due to low temperatures for 14.4 hrs. Lost time amounted to 14 hrs (9.3%), over 8 hrs due to the weather, and ~3 hrs to the man lift problems on Wed. The details on lost time are:
|
| Changed: | |
| < < | |
| > > | No news other that what might be reported for Mustang. |
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.8 - 14 Mar 2008 - ToddHunter) |
| Changed: | |
| < < |
|
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.7 - 13 Mar 2008 - JohnFord) |
| Deleted: | |
| < < | |
| Changed: | |
| < < | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.6 - 13 Mar 2008 - BobAnderson) |
| Changed: | |
| < < | |
| > > | Nothing happened this week. Oh,yeah, some folks got stuck in the GBT upper elevator, but got out okay. The elevator should be repaired next week after receipt of a new cable. |
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.5 - 13 Mar 2008 - MartyBloss) |
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.4 - 13 Mar 2008 - RandyMcCullough) |
| Changed: | |
| < < | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.3 - 13 Mar 2008 - StevenWhite) |
| Added: | |
| > > |
|
| Added: | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.2 - 13 Mar 2008 - AmyShelton) |
| Added: | |
| > > |
|
| <<O>> Difference Topic CommissioningMeeting08Mar14 (r1.1 - 13 Mar 2008 - RichardPrestage) |
| Topic CommissioningMeeting08Mar14 . { View | Diffs | r1.14 | > | r1.13 | > | r1.12 | More } |
|
Revision r1.1 - 13 Mar 2008 - 17:26 GMT - RichardPrestage Revision r1.14 - 14 Mar 2008 - 14:24 GMT - ChrisClark |
Content copyright © 1999-2007 by the contributing authors. All material on this collaboration platform is the property of the contributing authors. |