 <<O>>  Difference Topic Planning07B (r1.29 - 04 Oct 2007 - RonMaddalena)
Changed:
<
<

  • Sept 28 (originally Sept 14, four weeks after the end of track shutdown) : End of PTCS recommissioning of track
>
>

  • DONE Sept 28 (originally Sept 14, four weeks after the end of track shutdown) : End of PTCS recommissioning of track
Changed:
<
<

  • Week of Sept 24 or Oct 1: Install Zpec. Contingent on Aug 13 decision.
>
>

  • DONE Week of Sept 24 or Oct 1: Install Zpec. Contingent on Aug 13 decision.
Changed:
<
<

  • Sept 23 - Sept 30 : SDD software tests for Oct 3 release
  • Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
>
>

  • DONE Sept 23 - Sept 30 : SDD software tests for Oct 3 release
  • Week of Sept 24 (DONE), Oct 1 (DONE), and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).

 <<O>>  Difference Topic Planning07B (r1.28 - 24 Sep 2007 - RonMaddalena)
Changed:
<
<

  • Aug 31 - Sept 15 (originally Aug 17 - Aug 30, the end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. One nighttime 4 hr sessions per week. Dynamically scheduled.
>
>

  • DONE Aug 31 - Sept 15 (originally Aug 17 - Aug 30, the end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. (K-band was added after these plans were formed.) One nighttime 4 hr sessions per week. Dynamically scheduled.
Changed:
<
<

  • Week of Sept 17 or Sept 24 : Install Ka-band. Contingent on Aug 10 decision.
  • Before Sept 24 : Ku-band removed to make room for Zpec. No need to cool Ku until it is reinstalled (Nov?). Contingent on Aug 10 decision.
>
>

  • DONE Week of Sept 17 or Sept 24 : Install Ka-band. Contingent on Aug 10 decision.
  • DONE Before Sept 24 : Ku-band removed to make room for Zpec. No need to cool Ku until it is reinstalled (Nov?). Contingent on Aug 10 decision.
Changed:
<
<

  • No later than the week of Sept 24 : Q-band reinstalled and receiver checkout (8 hrs)
>
>

  • No later than the week of Sept 24 : Q-band reinstalled (DONE) and receiver checkout (8 hrs)

 <<O>>  Difference Topic Planning07B (r1.27 - 07 Sep 2007 - RonMaddalena)
Added:
>
>

  • DONE (New Item) Aug 27 Remove Q-band from telescope to investigate high Tsys in one channel.
Changed:
<
<

  • Aug 31 (originally Aug 17, the end of track shutdown) : start of PTCS recommissioning of the track
  • No later than Sept. 3 : K-band pumped and cooled
  • No later than Sept. 10 but no sooner than 1 week after K-band is cold: K-band receiver checkout. Dynamically scheduled.
  • No later than Sept 7 : Mustang removed
  • Sept 14 : End of PTCS recommissioning of track
>
>

  • DONE Aug 31 (originally Aug 17, the end of track shutdown) : start of PTCS recommissioning of the track
  • DONE No later than Sept. 3 : K-band pumped and cooled
  • DONE No later than Sept. 10 but no sooner than 1 week after K-band is cold: K-band receiver checkout. Dynamically scheduled.
  • DONE No later than Sept 7 : Mustang removed
  • Sept 28 (originally Sept 14, four weeks after the end of track shutdown) : End of PTCS recommissioning of track
Changed:
<
<

  • Week of Sept 24 : Q-band project checkout (8 hrs)
>
>

  • No later than the week of Sept 24 : Q-band reinstalled and receiver checkout (8 hrs)

 <<O>>  Difference Topic Planning07B (r1.26 - 17 Aug 2007 - RonMaddalena)
Changed:
<
<

  • (DONE)July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
  • Aug 1 through Aug 31 (originally Aug 17, the end of track shutdown) : Reinstall Q-band; pump and cool.
  • (DONE) Aug 6 : Install Mustang
  • Aug 6 through no later than Sept 7 : Mustang tests
  • By Aug 13 (Originally Aug 10) : Decision as to whether we will use this fall the one polarization configuration of Ka-band.
  • (DONE) By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 31 (originally Aug 17, the end of track shutdown) : receiver checkouts for (DONE) S-, (DONE) X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
>
>

  • DONE July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
  • DONE Aug 1 through Aug 31 (originally Aug 17, the end of track shutdown) : Reinstall Q-band; pump and cool.
  • DONE Aug 6 : Install Mustang
  • DONE Aug 6 through no later than Sept 7 : Mustang tests
  • DONE By Aug 13 (Originally Aug 10) : Decision as to whether we will use this fall the one polarization configuration of Ka-band.
  • DONE By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • DONE By Aug 31 (originally Aug 17, the end of track shutdown) : receiver checkouts for S-, X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.

 <<O>>  Difference Topic Planning07B (r1.25 - 13 Aug 2007 - RonMaddalena)
Changed:
<
<

  • Aug 17 (originally Aug 17, the end of track shutdown) : start of PTCS recommissioning of the track
>
>

  • Aug 31 (originally Aug 17, the end of track shutdown) : start of PTCS recommissioning of the track

 <<O>>  Difference Topic Planning07B (r1.24 - 10 Aug 2007 - RonMaddalena)
Changed:
<
<

  • DONE July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
  • Aug 1 through Aug 17 (end of track shutdown) : Reinstall Q-band; pump and cool.
  • Aug 6 : Install Mustang
>
>

  • (DONE)July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
  • Aug 1 through Aug 31 (originally Aug 17, the end of track shutdown) : Reinstall Q-band; pump and cool.
  • (DONE) Aug 6 : Install Mustang
Changed:
<
<

  • By Aug 10 : Decision as to whether we will use this fall the one polarization configuration of Ka-band.
  • DONE By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 17 (end of track shutdown) : receiver checkouts for S- DONE, X- DONE, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
  • Aug 17 - Sept 1 (end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. One nighttime 4 hr sessions per week. Dynamically scheduled.
  • Aug 17 (end of track shutdown) : start of PTCS recommissioning of the track
>
>

  • By Aug 13 (Originally Aug 10) : Decision as to whether we will use this fall the one polarization configuration of Ka-band.
  • (DONE) By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 31 (originally Aug 17, the end of track shutdown) : receiver checkouts for (DONE) S-, (DONE) X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
  • Aug 31 - Sept 15 (originally Aug 17 - Aug 30, the end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. One nighttime 4 hr sessions per week. Dynamically scheduled.
  • Aug 17 (originally Aug 17, the end of track shutdown) : start of PTCS recommissioning of the track
Changed:
<
<

  • Week of Sept 24 or Oct 1: Install Zpec. Contingent on Aug 10 decision.
>
>

  • Week of Sept 24 or Oct 1: Install Zpec. Contingent on Aug 13 decision.

 <<O>>  Difference Topic Planning07B (r1.23 - 03 Aug 2007 - RonMaddalena)
Changed:
<
<

  • July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
>
>

  • DONE July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
Changed:
<
<

  • By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 17 (end of track shutdown) : receiver checkouts for S-, X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
>
>

  • DONE By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 17 (end of track shutdown) : receiver checkouts for S- DONE, X- DONE, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
Deleted:
<
<

  • Week of Sept 10 : Install C-band (same location where Mustang was mounted).
Deleted:
<
<

  • Sept 17-30 : C-band astronomical commissioning, C-class weather (need to check this with Dana)

 <<O>>  Difference Topic Planning07B (r1.22 - 01 Aug 2007 - StevenWhite)
Deleted:
<
<

  • Week of Sept 10 -- Install C-band.

 <<O>>  Difference Topic Planning07B (r1.21 - 17 Jul 2007 - RonMaddalena)
Added:
>
>

The following time-line is a master summary of the all the tasks listed below. It folds in our discussion on July 17 concerning the various interactions and dependencies of the various projects. The time-line also includes targets that we discussed on July 17 but that are missing in the discussion below.

This plan assumes that the Ka/Zpec tests in the 1st week of August are successful and that the track shutdown finishes on Aug 17. Within the next two weeks, I will add the contingency plan if the test prove unsuccessful.

Please don't edit the following time-line since it reflects a fair number of inter-dependencies. If you see something that needs to be changed or added, please send an email with your changes to Ron Maddalena.

  • July 17 through Aug 1 : L-Band refrigerator work. Must be completed for Governor's school
  • Aug 1 through Aug 17 (end of track shutdown) : Reinstall Q-band; pump and cool.
  • Aug 6 : Install Mustang
  • Aug 6 through no later than Sept 7 : Mustang tests
  • By Aug 10 : Decision as to whether we will use this fall the one polarization configuration of Ka-band.
  • By Aug 10 (1 week before end of track shutdown) : Install S-band and X-band. The receivers will already be cold when they are installed. Due date is set by the end of the track repairs and so may slip forward or backward. Installing by Aug 10 is preferable since that will give us time for receiver checkouts during the track shutdown.
  • By Aug 17 (end of track shutdown) : receiver checkouts for S-, X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined.
  • Aug 17 - Sept 1 (end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. One nighttime 4 hr sessions per week. Dynamically scheduled.
  • Aug 17 (end of track shutdown) : start of PTCS recommissioning of the track
  • No later than Sept. 3 : K-band pumped and cooled
  • No later than Sept. 10 but no sooner than 1 week after K-band is cold: K-band receiver checkout. Dynamically scheduled.
  • No later than Sept 7 : Mustang removed
  • Week of Sept 10 : Install C-band (same location where Mustang was mounted).
  • Sept 14 : End of PTCS recommissioning of track
  • Week of Sept 17 or Sept 24 : Install Ka-band. Contingent on Aug 10 decision.
  • Sept 17-30 : C-band astronomical commissioning, C-class weather (need to check this with Dana)
  • Before Sept 24 : Ku-band removed to make room for Zpec. No need to cool Ku until it is reinstalled (Nov?). Contingent on Aug 10 decision.
  • Week of Sept 24 or Oct 1: Install Zpec. Contingent on Aug 10 decision.
  • Week of Sept 24 : Q-band project checkout (8 hrs)
  • Sept 23 - Sept 30 : SDD software tests for Oct 3 release
  • Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
Added:
>
>

  • Week of Sept 10 -- Install C-band.
Deleted:
<
<

Added:
>
>

Receiver commissioning and checkouts
  • By end of track shutdown : receiver checkouts for S-, X-, and Q-band. Includes pulsar checks of new S-band filters. Two nighttime 4 hr sessions per week, the LST is to be determined. Need to involve Scott.
  • Aug 17 - Sept 1 (end of shutdown to 2 weeks later) : Contingency test time for any remaining S-, X-, and Q-band receiver checkouts. One nighttime 4 hr sessions per week, dynamically scheduled.
  • No later than Sept. 10 but no sooner than 1 week after K-band is cold: K-band receiver checkout. One 4-hr, dynamically scheduled session
  • Sept 17-30 : C-band astronomical commissioning. Three 8-hr C-weather sessions (need to check this with Dana)
  • Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).

-- Ron Maddalena


 <<O>>  Difference Topic Planning07B (r1.20 - 17 Jul 2007 - GalenWatts)
Added:
>
>

  • Week of Sept 17-21 -- Ka RX Installation on a full Maintenance day.
  • Week of Sept 24-28 -- Ka RX Installation Back up, on a full Maintenance day.
  • Week of Sept 24-28 -- Zpectrometer Installation on a full Maintenance day.

 <<O>>  Difference Topic Planning07B (r1.19 - 17 Jul 2007 - BrianMason)
Added:
>
>

  • Mon August 6 -- install MUSTANG on GBT. We need 8h of access this day, and two days of at least 4h access later in the week.
  • Fri August 17 -- nominal date to remove MUSTANG. 8h access needed. We'd like to have the option to stay on a week further, however, should more extensive tests be necessary
  • Fri August 24 -- backup date to remove MUSTANG. 8h access
Changed:
<
<

  • MUSTANG fit check -- (8h/day, 3 days/wk access) tentatively in the Aug 1 - Aug 14 timeframe.
>
>

  • MUSTANG fit check -- (16h/wk access needed) tentatively in the Aug 6-19 timeframe, possibly running to the end of the next week.

 <<O>>  Difference Topic Planning07B (r1.18 - 16 Jul 2007 - ScottRansom)
Added:
>
>

Spigot 8-bit Calibration tests

  • Need ~8 hours of time in total. Antenna is not required for all of it, but would be useful for the last ~2 hours for testing.


 <<O>>  Difference Topic Planning07B (r1.17 - 16 Jul 2007 - CarlBignell)
Changed:
<
<

  • 24 April: Proposal Selection Committee meets (NEW note change)
>
>

  • 24 April: Proposal Selection Committee meets (NEW note change) (DONE)

 <<O>>  Difference Topic Planning07B (r1.16 - 12 Jul 2007 - JimBraatz)
Changed:
<
<

    • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the four hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the four hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.
>
>

    • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the six hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the six hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.

 <<O>>  Difference Topic Planning07B (r1.15 - 12 Jul 2007 - AmyShelton)
Changed:
<
<

  • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time.
>
>

  • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time. Preferably during a weekday.

 <<O>>  Difference Topic Planning07B (r1.14 - 07 Jun 2007 - BrianMason)
Changed:
<
<

  • ?

>
>

  • MUSTANG fit check -- (8h/day, 3 days/wk access) tentatively in the Aug 1 - Aug 14 timeframe.
  • MUSTANG sky check -- if we can get a shift or two of nighttime full motion that would be great, but not mandatory for our purposes

 <<O>>  Difference Topic Planning07B (r1.13 - 05 Jun 2007 - ToddHunter)
Added:
>
>

X SERVO   B   Measure following error during traditional holography map rates

 <<O>>  Difference Topic Planning07B (r1.12 - 04 Jun 2007 - ToddHunter)
Changed:
<
<

Semester 07A - 1st February through 30th April (finishes one month early)
>
>

Recommissioning time - 7th August through 31st August
Changed:
<
<

X PNT   A Pref Feb/March Pointing checks under benign conditions, schedule ~ two weeks apart.
X PNT   C Pref March/April Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
Ka/Q OOF   A Pref March/April Test new OOF techniques under thernally benign conditions
Ka/Q OOF   B Pref March/April Test new OOF techniques under thernally extreme conditions
>
>

none TILT   D Aug 7-10 Slow azimuth scans to measure new track tilt, at different elevations
X PNT   B Aug 13-17 24-hour all-sky pointing runs under benign conditions
X SSTRACK   B Aug 20-24 Single source pointing tracks to confirm model
X HALFPOW   B Aug 27-31 Long half-power tracks to confirm track model
           
Semester 07B - 01 September through 30 September
X PNT 2 C   Pointing checks under all conditions, 2 x 8hr, two weeks apart.
Ka/Q OOF 1 A   Test new OOF techniques under thermally benign conditions, 8hr
Ka/Q OOF 1 B   Test new OOF techniques under thernally extreme conditions, 8hr

 <<O>>  Difference Topic Planning07B (r1.11 - 11 May 2007 - CarlBignell)
Changed:
<
<

      • priority of paired day possibilities: Tue/Thu, Wed/Fri, Mon/wed (confirm)
    • Every Friday morning 08:00-12:00 fixed or dynamically scheduled
>
>

      • scheduled on alternating weeks
      • priority of paired day possibilities: Tue/Thu, Wed/Fri, Mon/wed
    • Two maintenance days (08:00-16:30) per week dynamically scheduled (Tue/Thu)
      • scheduled on alternating weeks
      • priority of paired day possibilities: Mon/wed, Tue/Thu

 <<O>>  Difference Topic Planning07B (r1.10 - 11 May 2007 - AmyShelton)
Added:
>
>

  • Cycle 6: Aug 16 - Sep 30 - Requested release date: 03 October 2007
  • Changed:
    <
    <

    -- AmyShelton - 05 Mar 2007

    >
    >

    Only assign integration and regression testing outside of maintenance hours during the track shutdown if telescope motion is allowed. Otherwise, we will do our integration and regression testing during maintenance days.

    -- AmyShelton - 11 May 2007


     <<O>>  Difference Topic Planning07B (r1.9 - 11 May 2007 - CarlBignell)
    Changed:
    <
    <

    • 4 May: Proposal dispositions emailed
    • 1 May: Draft call for proposals
    • 7 May: Call for proposals released
    • 15 May: Start constructing June through September astronomical schedule
    >
    >

    • 4 May: Proposal dispositions emailed (DONE 4/25/7)
    • 1 May: Draft call for proposals (DONE)
    • 7 May: Call for proposals released (DONE 5/8/7)
    • 15 May: Start constructing June through September astronomical schedule (DONE)

     <<O>>  Difference Topic Planning07B (r1.8 - 21 Mar 2007 - CarlBignell)
    Changed:
    <
    <

    • 5 March: Test (hardware, software, etc) and Commissioning trimester time estimates due
    • 12 March: Proposal reviews (scientific and technical) deadline
    • 3 April: Proposal Selection Committee meets
    • 20 April: Proposal dispositions emailed
    >
    >

    • 5 March: Test (hardware, software, etc) and Commissioning trimester time estimates due (DONE)
    • 12 March: Proposal reviews (scientific and technical) deadline (DONE)
    • 24 April: Proposal Selection Committee meets (NEW note change)
    • 4 May: Proposal dispositions emailed
    Changed:
    <
    <

    • 15 April: Start constructing (May)June through Sep astronomical schedule
    • 30 April: September schedule finalized
    >
    >

    • 15 May: Start constructing June through September astronomical schedule
    • 30 May: September schedule finalized (n/a - ?)

     <<O>>  Difference Topic Planning07B (r1.7 - 05 Mar 2007 - AmyShelton)
    Changed:
    <
    <

  • Cycle ?: ?-> Requested release date: ?
  • >
    >

  • Cycle 4: May 16 - Jun 30 - Requested release date: 27 June 2007
  • Cycle 5: Jul 01 - Aug 15 - Requested release date: 15 August 2007
  • Changed:
    <
    <

    • We will schedule our release for a scheduled maintenance day. No additional time required. Ideally, it would be good to have a "sympathetic" observer scheduled to use the system directly after maintenance that day.
    >
    >

    • We will schedule our release for a scheduled maintenance day. No additional time required. Ideally, it would be good to have a "sympathetic" observer scheduled to use the system directly after maintenance that day. If we have a dedicated release time rather than releasing during maintenance, we only need 2 hours.
    Changed:
    <
    <

    -- AmyShelton - 02 Nov 2006

    >
    >

    -- AmyShelton - 05 Mar 2007


     <<O>>  Difference Topic Planning07B (r1.6 - 05 Mar 2007 - CarlBignell)
    Changed:
    <
    <

    Planning cycles for 07A include:

    >
    >

    Planning cycles for 07B include:

    Changed:
    <
    <

  • Cycle 1: Jan 1 - Feb 15 -> Requested release date: 14 Feb 2007
  • Cycle 2: Feb 16 - Mar 31 -> Requested release date: 28 March 2007
  • Cycle 3: Apr 1 - May 15 -> Requested release date: 16 May 2007
  • >
    >

  • Cycle ?: ?-> Requested release date: ?
  • Changed:
    <
    <

    • PF1 - Two weeks in the lab May 07.
    • C band
      • Assuming the Penn Array is on the GBT starting about Sept 1, we would like to do the C-band upgrade in two phases: Phase 1 consists of the refrigerator upgrade and would be accomplished Sept 1 - Oct 15. RCO on the GBT after Oct 15 (or when the Penn Array comes off). RCO should be straightforward (2-3 hrs) since none of the electronics components change, only some cabling. The receiver could then be available for astronomy during November and December, including the global VLBI run in November. (Note: Phase 1 began about Sept 1, and the refrigerator upgrade has been accomplished. The receiver will be installed the week of November 13 - the Penn Array time was extended until that week. RDN 13Nov06)

      • Phase 2 consists of the replacement of the room-temperature RF electronics with an integrated package designed by Mike Stennes. We could begin that on Jan 2, and would like 5 weeks in the lab for installation and thorough testing, including with the Lab Spectrometer - so RCO would fall in 07A. Note that there might be some minor receiver manager (a few digital control bits) and Cleo changes needed during this phase - the details are not yet defined. (Note: The Penn Array will not be reinstalled in January 07, and perhaps not until the fall of 07. Hence, phase 2 will likely be pushed back until the 07 summer shutdown or later. RDN 13NOV06)
    >
    >

    • PF1 - Two weeks in the lab in fall.
    Changed:
    <
    <

    • February 1 - April 30
    >
    >

    • Sep 1 - 30
    Deleted:
    <
    <

    • April 30 - July 31 (inclusive)
      • No antenna movement - see schedule
    • August 1 - 31
      • Antenna recalibration
      • limited observing (?)
    Changed:
    <
    <

    • Twelve hours are requested for collecting gain calibration data once per month
      • Every other month, a contiguous 12-hour session LST 0500 to 1500, in good weather.
      • In alternate months, the 12 hours can be in 4-hour segments scheduled as convenient.

    The good weather sessions will be for determining gain curves, the other sessions for SCALs

    >
    >

    ?


     <<O>>  Difference Topic Planning07B (r1.5 - 05 Mar 2007 - CarlBignell)
    Changed:
    <
    <

    X PNT 2 A Pref Feb/March Pointing checks under benign conditions, schedule ~ two weeks apart.
    X PNT 3 C Pref March/April Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
    Ka/Q OOF 1 A Pref March/April Test new OOF techniques under thernally benign conditions
    Ka/Q OOF 1 B Pref March/April Test new OOF techniques under thernally extreme conditions
    >
    >

    X PNT   A Pref Feb/March Pointing checks under benign conditions, schedule ~ two weeks apart.
    X PNT   C Pref March/April Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
    Ka/Q OOF   A Pref March/April Test new OOF techniques under thernally benign conditions
    Ka/Q OOF   B Pref March/April Test new OOF techniques under thernally extreme conditions
    Changed:
    <
    <

    Total 07A requirements: 64 hours.

    >
    >

    Total 07B requirements: 16 hours.

    Changed:
    <
    <

    • PF1 - Two weeks in the lab Jan or Feb 07.
    >
    >

    • PF1 - Two weeks in the lab May 07.

     <<O>>  Difference Topic Planning07B (r1.4 - 04 Mar 2007 - CarlBignell)
    Changed:
    <
    <

    • 10 February: Proposals distributed to scientific and technical referees
    >
    >

    • 10 February: Proposals distributed to scientific and technical referees (DONE)
    Changed:
    <
    <

    • 3 April: Proposal Selection COmmittee meets
    >
    >

    • 3 April: Proposal Selection Committee meets

     <<O>>  Difference Topic Planning07B (r1.3 - 05 Feb 2007 - CarlBignell)
    Changed:
    <
    <

    • 16 March: Proposal reviews (scientific and technical) deadline
    >
    >

    • 12 March: Proposal reviews (scientific and technical) deadline

     <<O>>  Difference Topic Planning07B (r1.2 - 05 Feb 2007 - CarlBignell)
    Changed:
    <
    <

    • 1 February: Call for Proposal Deadline
    >
    >

    • 1 February: Call for Proposal Deadline (DONE 2/1/7)
    Changed:
    <
    <

    • 15 April: Start constructing February through April schedule
    >
    >

    • 15 April: Start constructing (May)June through Sep astronomical schedule

     <<O>>  Difference Topic Planning07B (r1.1 - 17 Jan 2007 - CarlBignell)
    Added:
    >
    >

    %META:TOPICINFO{author="CarlBignell" date="1169035860" format="1.0" version="1.1"}% %META:TOPICPARENT{name="WebHome"}%

    GBT Test/Maintenance Requirements for Trimester 07B

    (June 1, 2007 - September 30, 2007)


    Deadlines:

    • 1 February: Call for Proposal Deadline
    • 10 February: Proposals distributed to scientific and technical referees
    • 5 March: Test (hardware, software, etc) and Commissioning trimester time estimates due
    • 16 March: Proposal reviews (scientific and technical) deadline
    • 3 April: Proposal Selection COmmittee meets
    • 20 April: Proposal dispositions emailed
    • 1 May: Draft call for proposals
    • 7 May: Call for proposals released
    • 15 April: Start constructing February through April schedule
    • 30 April: September schedule finalized


    Commissioning Summary & Milestones: June 1 - September 30


    Receiver Installation Schedules: June 1 - September 30


    Test / Maintenance Time Requests

    All activities which will impact the amount of astronomical time available for this trimester should be briefly outlined below. This includes commissioning, specific equipment tests, and all maintenance requirements as well as receiver and backend availability during this period.

    PTCS Tests

    Semester 07A - 1st February through 30th April (finishes one month early)
    Band Task Shifts Conditions Tentative Dates Comments
    X PNT 2 A Pref Feb/March Pointing checks under benign conditions, schedule ~ two weeks apart.
    X PNT 3 C Pref March/April Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
    Ka/Q OOF 1 A Pref March/April Test new OOF techniques under thernally benign conditions
    Ka/Q OOF 1 B Pref March/April Test new OOF techniques under thernally extreme conditions
    X SERVO 0.5 * 4 D Any Four hour chunks to test servo improvements, need to move antenna

    NOTE: in the above table "1 shift" means one 8 hour observing shift, on average.

    A - clear skies (low opacity), low wind (less than 2.5 m/s), thermally stable (00:00 - 08:00)
    B - clear skies (low opacity), low wind (less than 2.5 m/s).
    C - clear skies (low opacity)
    D - any observing weather.
    E - can be done in parallel with maintenance, but needs antenna at access and M&C available. When scheduled this work may exceed the time required for other maintenance activities.

    Total 07A requirements: 64 hours.

    High Frequency Instrumentation (Ka, Q, Zpectrometer, CCB, Penn Array) Tests

    • ?

    Spectral Baseline Tests

    • ?

    Other Electronics Tests
    • ?
    Software Tests
    Planning cycles for 07A include:
    • Cycle 1: Jan 1 - Feb 15 -> Requested release date: 14 Feb 2007
    • Cycle 2: Feb 16 - Mar 31 -> Requested release date: 28 March 2007
    • Cycle 3: Apr 1 - May 15 -> Requested release date: 16 May 2007

    Approximately 6-10 days prior to release date:

    • Two blocks of 4 hours each for integration tests; full system and antenna. Preferably during a weekday.

    Approximately 2-6 days prior to release date:

    • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time.
      • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the four hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the four hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.

    Within +/- 2 business days of end of development cycle:

    • One block of 4 hours for integration tests (to resolve/test any issues/solutions found during regression testing).
    • We will schedule our release for a scheduled maintenance day. No additional time required. Ideally, it would be good to have a "sympathetic" observer scheduled to use the system directly after maintenance that day.

    Averages 18 hours of time per cycle.

    -- AmyShelton - 02 Nov 2006

    Receiver Maintenance
    • PF1 - Two weeks in the lab Jan or Feb 07.
    • C band
      • Assuming the Penn Array is on the GBT starting about Sept 1, we would like to do the C-band upgrade in two phases: Phase 1 consists of the refrigerator upgrade and would be accomplished Sept 1 - Oct 15. RCO on the GBT after Oct 15 (or when the Penn Array comes off). RCO should be straightforward (2-3 hrs) since none of the electronics components change, only some cabling. The receiver could then be available for astronomy during November and December, including the global VLBI run in November. (Note: Phase 1 began about Sept 1, and the refrigerator upgrade has been accomplished. The receiver will be installed the week of November 13 - the Penn Array time was extended until that week. RDN 13Nov06)

      • Phase 2 consists of the replacement of the room-temperature RF electronics with an integrated package designed by Mike Stennes. We could begin that on Jan 2, and would like 5 weeks in the lab for installation and thorough testing, including with the Lab Spectrometer - so RCO would fall in 07A. Note that there might be some minor receiver manager (a few digital control bits) and Cleo changes needed during this phase - the details are not yet defined. (Note: The Penn Array will not be reinstalled in January 07, and perhaps not until the fall of 07. Hence, phase 2 will likely be pushed back until the 07 summer shutdown or later. RDN 13NOV06)

    General Maintenance
    • February 1 - April 30
      • One maintenance day (08:00-16:30) per week dynamically scheduled (Tue/Thu)
        • priority of paired day possibilities: Tue/Thu, Wed/Fri, Mon/wed (confirm)
      • Every Friday morning 08:00-12:00 fixed or dynamically scheduled
    Track Refurbishment
    • April 30 - July 31 (inclusive)
      • No antenna movement - see schedule
    • August 1 - 31
      • Antenna recalibration
      • limited observing (?)
    Gain Calibration
    • Twelve hours are requested for collecting gain calibration data once per month
      • Every other month, a contiguous 12-hour session LST 0500 to 1500, in good weather.
      • In alternate months, the 12 hours can be in 4-hour segments scheduled as convenient.

    The good weather sessions will be for determining gain curves, the other sessions for SCALs

    -- Frank Ghigo and Ron Maddalena

    Scheduling Constraints
    • Avoid scheduling project changes exactly at 0700 or 1900 ET to minimize operator overload
      • Attempt to have project changes around 0730 and 1930 ET instead of at 0700 and 1900 exactly
      • If not possible, attempt a half hour earlier around 0630 and 1830 ET

    -- CarlBignell - 17 Jan 2007


    Topic Planning07B . { View | Diffs | r1.29 | > | r1.28 | > | r1.27 | More }
    Revision r1.1 - 17 Jan 2007 - 12:11 GMT - CarlBignell
    Revision r1.29 - 04 Oct 2007 - 19:44 GMT - RonMaddalena