 <<O>>  Difference Topic Planning07C (r1.32 - 05 Nov 2007 - RonMaddalena)
Changed:
<
<

  • Week of Sept 24 (DONE), Oct 1 (DONE), and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
  • Oct 1 - Oct 13 : Zpec commissioning, A and B weather, dynamically scheduled. Contingent on Aug 10 decision.
  • Oct 7 - 15 : CCB/Ka testing, A-class weather (nighttime, dynamically scheduled).
  • No later than week of Oct 15 : Install C-band .
  • Oct 18 : Decision as to whether to continue using the Ka-band single-pol configuration. Whether to schedule 100 hrs of Zpec observing. Whether to remove Ka and convert back to old configuration. Whether to proceed with Ka/Spec/CCB observing.
  • Oct 21-Nov 2 : C-band astronomical commissioning, C-class weather
>
>

  • DONE Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
  • DONE Oct 1 - Oct 13 : Zpec commissioning, A and B weather, dynamically scheduled. Contingent on Aug 10 decision.
  • DONE Oct 7 - 15 : CCB/Ka testing, A-class weather (nighttime, dynamically scheduled).
  • DONE No later than week of Oct 15 : Install C-band .
  • DONE Oct 18 : Decision as to whether to continue using the Ka-band single-pol configuration. Whether to schedule 100 hrs of Zpec observing. Whether to remove Ka and convert back to old configuration. Whether to proceed with Ka/Spec/CCB observing.
  • DONE Oct 21-Nov 2 : C-band astronomical commissioning, C-class weather

 <<O>>  Difference Topic Planning07C (r1.31 - 04 Oct 2007 - RonMaddalena)
Changed:
<
<

  • Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
>
>

  • Week of Sept 24 (DONE), Oct 1 (DONE), and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).

 <<O>>  Difference Topic Planning07C (r1.30 - 21 Sep 2007 - CarlBignell)
Changed:
<
<

  • 1 September: Draft call for 08A proposals
  • 1 September: Start constructing October through January astronomical schedule
  • 7 September: 08A Call for proposals released
>
>

  • 1 September: Draft call for 08A proposals (DONE)
  • 1 September: Start constructing October through January astronomical schedule (DONE)
  • 7 September: 08A Call for proposals released (DONE)

 <<O>>  Difference Topic Planning07C (r1.29 - 29 Aug 2007 - CarlBignell)
Changed:
<
<

  • 17 August: Proposal dispositions emailed
>
>

  • 17 August: Proposal dispositions emailed (DONE)

 <<O>>  Difference Topic Planning07C (r1.28 - 08 Aug 2007 - CarlBignell)
Changed:
<
<

  • 1 August: First draft of fall commissioning strategy
  • 3 August: Proposal Selection Committee meets
>
>

  • 1 August: First draft of fall commissioning strategy (DONE)
  • 3 August: Proposal Selection Committee meets (DONE)

 <<O>>  Difference Topic Planning07C (r1.27 - 03 Aug 2007 - RonMaddalena)
Deleted:
<
<

  • Oct 1-30 : C-band baseline tests, C weather, dynamically scheduled.
  • Oct 1-30 : X-band baseline tests, B weather, dynamically scheduled.
Added:
>
>

  • No later than week of Oct 15 : Install C-band .
Added:
>
>

  • Oct 21-Nov 2 : C-band astronomical commissioning, C-class weather
  • Nov 2 : C-Band observing can start
Added:
>
>

  • Nov 2-15 : C-band baseline tests, C weather, and X-band baseline tests, B weather, dynamically scheduled.

 <<O>>  Difference Topic Planning07C (r1.26 - 02 Aug 2007 - RonMaddalena)
Changed:
<
<

  • Week of Dec 3 : Mustang installed
>
>

  • Week of Dec 3 : C-band removed, Mustang installed
Changed:
<
<

  • Dec 8 - Jan 15 : Mustang tests -- dynamically scheduled, A weather, nighttime.
>
>

  • Dec 8 - week of Jan 15 : Mustang tests -- dynamically scheduled, A weather, nighttime.
  • Week of Jan 21 : Mustang removed, C-band installed

 <<O>>  Difference Topic Planning07C (r1.25 - 01 Aug 2007 - StevenWhite)
Added:
>
>

  • Install C band week of October 1

 <<O>>  Difference Topic Planning07C (r1.24 - 17 Jul 2007 - RonMaddalena)
Added:
>
>

The following time-line is a master summary of the all the tasks listed below. It folds in our discussion on July 17 concerning the various interactions and dependencies of the various projects. The time-line also includes targets that we discussed on July 17 but that are missing in the discussion below.

This plan assumes that the Ka/Zpec tests in the 1st week of August are successful, that the Zpec tests at the start of Oct are successful, and that the track shutdown finishes on Aug 17. Within the next two weeks, I will add the contingency plan if the test prove unsuccessful.

Please don't edit the following time-line since it reflects a fair number of inter-dependencies. If you see something that needs to be changed or added, please send an email with your changes to Ron Maddalena.

  • Week of Sept 24, Oct 1, and Oct 8: Ka-band/Spectrometer recommissioning. Contingent on Aug 10 decision. One 8 hr sessions per week of A-class weather (nighttime, dynamically scheduled).
  • Oct 1 - Oct 13 : Zpec commissioning, A and B weather, dynamically scheduled. Contingent on Aug 10 decision.
  • Oct 1-30 : C-band baseline tests, C weather, dynamically scheduled.
  • Oct 1-30 : X-band baseline tests, B weather, dynamically scheduled.
  • Oct 7 - 15 : CCB/Ka testing, A-class weather (nighttime, dynamically scheduled).
  • Oct 18 : Decision as to whether to continue using the Ka-band single-pol configuration. Whether to schedule 100 hrs of Zpec observing. Whether to remove Ka and convert back to old configuration. Whether to proceed with Ka/Spec/CCB observing.
  • Nov 2 : Decision on how to proceed with traditional holography. Which receiver will we remove? When will tests start? Do we need to cut a mounting plate?
  • Week of Dec 3 : Mustang installed
  • Dec 7 : Telescope at access for Mustang
  • Dec 8 - Jan 15 : Mustang tests -- dynamically scheduled, A weather, nighttime.
  • Feb 3-13: SDD software tests for Feb 13 release

See PTCS, Gain calibration, and SCAL sections for details on tasks that repeat throughout the trimester but that have no definite due dates.

Changed:
<
<

  • Zpectrometer Removal, Week of Novemer 26-30 (possibly sooner) on a full maintenance day.
  • Tuesday December 4th (or Thurs depending on dyn sched)-- install MUSTANG. 8h access. 4h access requested during day on Friday Decemer 7th.
>
>

  • Zpectrometer Removal, Week of November 26-30 (possibly sooner) on a full maintenance day.
  • Tuesday December 4th (or Thurs depending on dyn sched)-- install MUSTANG. 8h access. 4h access requested during day on Friday December 7th.
Changed:
<
<

  • Ka-band/Spectrometer recommisioning : 32 hrs of "A" weather (using PTCS definitions). - Ron Maddalena
>
>

  • Ka-band/Spectrometer recommissioning : Three 8-hr "A" weather nighttime sessions (using PTCS definitions), dynamically scheduled. - Ron Maddalena

 <<O>>  Difference Topic Planning07C (r1.23 - 17 Jul 2007 - GalenWatts)
Changed:
<
<

  • Possible Ka installation in early-mid October if necessary, Zpectrometer installation following, each requiring a full maintenance day.
>
>

  • Possible Ka installation in early-mid October if necessary (due to Zpec failure), requiring a full maintenance day.
Added:
>
>

  • Zpectrometer Removal, Week of Novemer 26-30 (possibly sooner) on a full maintenance day.
Changed:
<
<

  • Zpectrometer Checkout/Commisioning, weeks of 7-13, 14-20 October, two sessions of 6 hours (estimated), A or B weather(?)
>
>

  • Zpectrometer Checkout/Commissioning: 1-13 October, two sessions of 6 hours , "A" weather, preferably not during Tuesday AM through Thursday prior to midnight.

 <<O>>  Difference Topic Planning07C (r1.22 - 17 Jul 2007 - GalenWatts)
Changed:
<
<

  • Possible Ka installation in early-mid October if necessary.
>
>

  • Possible Ka installation in early-mid October if necessary, Zpectrometer installation following, each requiring a full maintenance day.
  • Zpectrometer Installation back up, Week of October 1-5 on a full maintenance day.
Added:
>
>

  • Zpectrometer Checkout/Commisioning, weeks of 7-13, 14-20 October, two sessions of 6 hours (estimated), A or B weather(?)


 <<O>>  Difference Topic Planning07C (r1.21 - 17 Jul 2007 - BrianMason)
Added:
>
>

  • Tuesday December 4th (or Thurs depending on dyn sched)-- install MUSTANG. 8h access. 4h access requested during day on Friday Decemer 7th.
Changed:
<
<

  • Ka Receiver, CCB Checkout/Re-Commissioning time in Oct - Nov. (Note: Brian is unavailable Nov 3 - Nov 19)
>
>

  • Ka Receiver, CCB Checkout/Re-Commissioning time in Oct - Nov. (Note: Brian is unavailable Nov 3 - Nov 19; we should ensure that Jules is available to look, help, and learn). CCB will need two 5h chunks, in LST ranges that allow 3c48, 3c147, or 3c286 to be seen. This is "A" weather, day or night.
Changed:
<
<

  • 5x8h MUSTANG commissioning runs, dynamically scheduled for the best weather. We'd like these in December 2007 and Jan 2008, in one or two denselyl scheduled chunks allowing the UPenn guys to come for the runs and be home on Christmas and New Years'
>
>

  • 5x8h MUSTANG commissioning runs, dynamically scheduled for the best weather. We'd like these in December the period December 8th-December 22nd; and Jan 1+. This is "A" weather, nighttime only.

 <<O>>  Difference Topic Planning07C (r1.20 - 16 Jul 2007 - ScottRansom)
Added:
>
>

Pulsar Dream Machine Testing
We will need ~8 hours of on-sky (with antenna) testing of the incoherent modes of the new digital backend:

  • Check characteristics for bright slow and fast pulsars
  • Check for and characterize self-generated RFI
  • Measure absolute timing characteristics using Spigot and/or GASP using high-precision MSPs
  • Measurements will need PF1 (for 50-60MHz tests at 350MHz or 820MHz) and S-band (for wide-band tests)

-- ScottRansom - 16 Jul 2007


 <<O>>  Difference Topic Planning07C (r1.19 - 16 Jul 2007 - FrankGhigo)
Changed:
<
<

tr>

>
>

Gain Calibration Measurements
12 hrs every 2 months of "A", "B", or "C" weather (using PTCS's definitions).

-- F. Ghigo


 <<O>>  Difference Topic Planning07C (r1.18 - 16 Jul 2007 - RonMaddalena)
Added:
>
>

  • 1 August: First draft of fall commissioning strategy
Added:
>
>

  • Ka-band/Spectrometer recommisioning : 32 hrs of "A" weather (using PTCS definitions). - Ron Maddalena

Changed:
<
<

Gain Calibration
>
>

SCAL Measurements
Changed:
<
<

? -- Frank Ghigo and Ron Maddalena

>
>

4 hrs per month of "A" or "B" weather (using PTCS's definitions), 4 hrs per month of "C" weather

-- Ron Maddalena & Jules Harnett


 <<O>>  Difference Topic Planning07C (r1.17 - 16 Jul 2007 - ToneyMinter)
Added:
>
>

tr>

Balancing
A few hours of time will be needed to test the new balancing routines. These tests will require telescope motion since we need to test balancing at the half power point between an off and on position. -- Toney Minter

Added:
>
>


 <<O>>  Difference Topic Planning07C (r1.16 - 16 Jul 2007 - CarlBignell)
Changed:
<
<

  • 5 July: Test (hardware, software, etc) and Commissioning trimester time estimates due
  • 13 July: Proposal reviews (scientific and technical) deadline
  • 7 August: Proposal Selection Committee meets
>
>

  • 5 July: Test (hardware, software, etc) and Commissioning trimester time estimates due (DONE 7/12/07)
  • 13 July: Proposal reviews (scientific and technical) deadline (DONE)
  • 3 August: Proposal Selection Committee meets

 <<O>>  Difference Topic Planning07C (r1.15 - 12 Jul 2007 - JimBraatz)
Changed:
<
<

    • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the four hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the four hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.
>
>

    • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the six hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the six hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.

 <<O>>  Difference Topic Planning07C (r1.14 - 12 Jul 2007 - AmyShelton)
Changed:
<
<

  • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time.
>
>

  • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time. Preferably during a weekday.

 <<O>>  Difference Topic Planning07C (r1.13 - 06 Jul 2007 - BrianMason)
Changed:
<
<

  • Ka Receiver, CCB Checkout/Re-Commissioning time in Oct - Nov.
>
>

  • Ka Receiver, CCB Checkout/Re-Commissioning time in Oct - Nov. (Note: Brian is unavailable Nov 3 - Nov 19)
Changed:
<
<

  • 5x8h MUSTANG commissioning runs, dynamically scheduled for the best weather. Probably we'd like the first one to be in early December but that's TBD.
>
>

  • 5x8h MUSTANG commissioning runs, dynamically scheduled for the best weather. We'd like these in December 2007 and Jan 2008, in one or two denselyl scheduled chunks allowing the UPenn guys to come for the runs and be home on Christmas and New Years'

 <<O>>  Difference Topic Planning07C (r1.12 - 06 Jul 2007 - GalenWatts)
Added:
>
>

  • Possible Ka installation in early-mid October if necessary.
Added:
>
>

  • Ka Receiver, CCB Checkout/Re-Commissioning time in Oct - Nov.

 <<O>>  Difference Topic Planning07C (r1.11 - 05 Jul 2007 - ToddHunter)
Changed:
<
<

Ku HOLO 2 A Jan Traditional holography maps in good conditions
>
>

Ku HOLO 1 A Jan Traditional holography maps in good conditions
Changed:
<
<

Total 07C requirements: 20 x 8 hours = 160 hours.

>
>

Total 07C requirements: (15 x 8 hours) + (10 x 4 hours)= 160 hours.


 <<O>>  Difference Topic Planning07C (r1.10 - 29 Jun 2007 - ToddHunter)
Changed:
<
<

Ka/Q OOF 4 A Dec/Jan? Test new OOF techniques under thermally benign conditions
Ka/Q OOF 4 B Dec/Jan? Test new OOF techniques under thermally extreme conditions
>
>

Ka/Q OOF 3 A Oct,Nov,Dec Test new OOF techniques under thermally benign conditions
Ka/Q OOF 3 B Nov,Dec,Jan Test new OOF techniques under thermally extreme conditions
Ku HOLO 0.5 * 2 B Dec Test traditional holography system integrity and phase stability
Ku HOLO 2 A Jan Traditional holography maps in good conditions

 <<O>>  Difference Topic Planning07C (r1.9 - 22 Jun 2007 - RichardPrestage)
Changed:
<
<

X PNT   A Pref Pointing checks under benign conditions, schedule ~ two weeks apart.
X PNT   C Pref Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
Ka/Q OOF   A Pref Test new OOF techniques under thermally benign conditions
Ka/Q OOF   B Pref Test new OOF techniques under thermally extreme conditions
>
>

X PNT 4 A one per month Pointing checks under benign conditions
X PNT 4 C one per month Pointing checks under all conditions
Ka/Q OOF 4 A Dec/Jan? Test new OOF techniques under thermally benign conditions
Ka/Q OOF 4 B Dec/Jan? Test new OOF techniques under thermally extreme conditions
Changed:
<
<

Total 07C requirements: 0 hours.

>
>

Total 07C requirements: 20 x 8 hours = 160 hours.


 <<O>>  Difference Topic Planning07C (r1.8 - 19 Jun 2007 - AmyShelton)
Changed:
<
<

Planning cycles for 07B include:

>
>

Planning cycles for 07C include:

Changed:
<
<

  • Cycle 7: - *Requested release date: *
  • Cycle 8: - *Requested release date: *
  • Cycle 9: - *Requested release date: *
  • >
    >

  • Cycle 7: - Requested release date: 14 November 2007
  • Cycle 8: - Requested release date: None
  • Cycle 1: - Requested release date: 13 February 2007
  • Changed:
    <
    <

    Only assign integration and regression testing outside of maintenance hours during the track shutdown if telescope motion is allowed. Otherwise, we will do our integration and regression testing during maintenance days.

    -- AmyShelton - 11 May 2007

    >
    >

    -- AmyShelton - 19 Jun 2007


     <<O>>  Difference Topic Planning07C (r1.7 - 15 Jun 2007 - RogerNorrod)
    Changed:
    <
    <

    • ?
    >
    >

    • C-band: Two 4 hour sessions separated by >2 weeks. October preferred. Dry weather required. - rnorrod

    • X-band: Two 4 hour sessions separated by >2 weeks. October preferred. Dry weather required. - rnorrod
    Changed:
    <
    <

    • ?
    >
    >

    • 20m - BYU Test Coordination: A team from BYU will be here in the Fall to do tests on the 20m with an L-band Focal Plane Array. One of the primary areas of investigation is testing Dynamic Interference Rejection algorithims while tracking astronomical sources. As part of this there will be the need to setup low-power L-band radiators on and near the site for brief periods. The hope is to find periods (3-4 hours per day for 3-4 days spread over a week) when GBT and 43m operations will not be affected (not observing in L-band). Dates have not been set - the primary driver for the date is when the 20m de-mothball activities are completed - but the target is mid-October. - rnorrod

     <<O>>  Difference Topic Planning07C (r1.6 - 08 Jun 2007 - CarlBignell)
    Changed:
    <
    <

    • 1 June: Call for Proposal Deadline
    • 10 June: Proposals distributed to scientific and technical referees
    >
    >

    • 1 June: Call for Proposal Deadline (DONE)
    • 10 June: Proposals distributed to scientific (DONE 06/08/07) and technical referees
    Changed:
    <
    <

    • 16 July: Proposal reviews (scientific and technical) deadline
    >
    >

    • 13 July: Proposal reviews (scientific and technical) deadline

     <<O>>  Difference Topic Planning07C (r1.5 - 07 Jun 2007 - BrianMason)
    Deleted:
    <
    <

    Changed:
    <
    <

    • ?
    >
    >

    • 5x8h MUSTANG commissioning runs, dynamically scheduled for the best weather. Probably we'd like the first one to be in early December but that's TBD.

     <<O>>  Difference Topic Planning07C (r1.4 - 14 May 2007 - CarlBignell)
    Changed:
    <
    <

        • priority of paired day possibilities: Mon/wed, Tue/Thu
    >
    >

        • priority of paired day possibilities: Mon/Tue, Tue/Thu otherwise Tue/Thu, Wed/Fri

     <<O>>  Difference Topic Planning07C (r1.3 - 14 May 2007 - JohnFord)
    Changed:
    <
    <

    Ka/Q OOF   A Pref Test new OOF techniques under thernally benign conditions
    Ka/Q OOF   B Pref Test new OOF techniques under thernally extreme conditions
    X SERVO 0.5 * 4 D Any Four hour chunks to test servo improvements, need to move antenna
    >
    >

    Ka/Q OOF   A Pref Test new OOF techniques under thermally benign conditions
    Ka/Q OOF   B Pref Test new OOF techniques under thermally extreme conditions
    X SERVO 0.5 * 8 D Any Four hour chunks to test servo improvements, need to move antenna
    Added:
    >
    >


     <<O>>  Difference Topic Planning07C (r1.2 - 11 May 2007 - CarlBignell)
    Changed:
    <
    <

    Deadlines:

    >
    >

    Proposal and Scheduling Milestones:


     <<O>>  Difference Topic Planning07C (r1.1 - 11 May 2007 - CarlBignell)
    Added:
    >
    >

    %META:TOPICINFO{author="CarlBignell" date="1178889480" format="1.0" version="1.1"}% %META:TOPICPARENT{name="WebHome"}%

    GBT Test/Maintenance Requirements for Trimester 07C

    (October 1, 2007 - January 31, 2008)


    Deadlines:

    • 1 June: Call for Proposal Deadline
    • 10 June: Proposals distributed to scientific and technical referees
    • 5 July: Test (hardware, software, etc) and Commissioning trimester time estimates due
    • 16 July: Proposal reviews (scientific and technical) deadline
    • 7 August: Proposal Selection Committee meets
    • 17 August: Proposal dispositions emailed
    • 1 September: Draft call for 08A proposals
    • 1 September: Start constructing October through January astronomical schedule
    • 7 September: 08A Call for proposals released
    • 30 September: January schedule finalized


    Commissioning Summary & Milestones: October 1 - January 31


    Receiver Installation Schedules: October 1 - January 31


    Test / Maintenance Time Requests

    All activities which will impact the amount of astronomical time available for this trimester should be briefly outlined below. This includes commissioning, specific equipment tests, and all maintenance requirements as well as receiver and backend availability during this period.

    PTCS Tests

    Semester 07C - 1st October through 31th January
    Band Task Shifts Conditions Tentative Dates Comments
    X PNT   A Pref Pointing checks under benign conditions, schedule ~ two weeks apart.
    X PNT   C Pref Pointing checks under all conditions, schedule after above, and ~ two weeks apart.
    Ka/Q OOF   A Pref Test new OOF techniques under thernally benign conditions
    Ka/Q OOF   B Pref Test new OOF techniques under thernally extreme conditions
    X SERVO 0.5 * 4 D Any Four hour chunks to test servo improvements, need to move antenna

    NOTE: in the above table "1 shift" means one 8 hour observing shift, on average.

    A - clear skies (low opacity), low wind (less than 2.5 m/s), thermally stable (00:00 - 08:00)
    B - clear skies (low opacity), low wind (less than 2.5 m/s).
    C - clear skies (low opacity)
    D - any observing weather.
    E - can be done in parallel with maintenance, but needs antenna at access and M&C available. When scheduled this work may exceed the time required for other maintenance activities.

    Total 07C requirements: 0 hours.

    High Frequency Instrumentation (Ka, Q, Zpectrometer, CCB, Penn Array) Tests

    • ?

    Spectral Baseline Tests

    • ?

    Other Electronics Tests
    • ?
    Software Tests
    Planning cycles for 07B include:
    • Cycle 7: - *Requested release date: *
    • Cycle 8: - *Requested release date: *
    • Cycle 9: - *Requested release date: *

    Approximately 6-10 days prior to release date:

    • Two blocks of 4 hours each for integration tests; full system and antenna. Preferably during a weekday.

    Approximately 2-6 days prior to release date:

    • One block of 6 hours for regression tests (full system and antenna) followed by around 8 hours of commissioning time.
      • Notes: The commissioning time could be used for calibration tests, pointing, etc. The theory is that if the four hours of regression tests went horribly wrong, we'd revert to the current M&C version, the commissioning tests would then use the old version, and we could re-schedule. If the four hours of regression testing went well, the next eight hours would be a "sympathetic" observer using the new version, and a chance to catch/fix trivial problems. We'd revert to the current M&C version at the end of the commissioning tests.

    Within +/- 2 business days of end of development cycle:

    • One block of 4 hours for integration tests (to resolve/test any issues/solutions found during regression testing).
    • We will schedule our release for a scheduled maintenance day. No additional time required. Ideally, it would be good to have a "sympathetic" observer scheduled to use the system directly after maintenance that day. If we have a dedicated release time rather than releasing during maintenance, we only need 2 hours.

    Averages 18 hours of time per cycle.

    Only assign integration and regression testing outside of maintenance hours during the track shutdown if telescope motion is allowed. Otherwise, we will do our integration and regression testing during maintenance days.

    -- AmyShelton - 11 May 2007

    Receiver Maintenance
    • PF1 - Two weeks in the lab in fall.
    General Maintenance
    • Oct 1 - Jan 31
      • One maintenance day (08:00-16:30) per week dynamically scheduled (Tue/Thu)
        • scheduled on alternating weeks
        • priority of paired day possibilities: Tue/Thu, Wed/Fri, Mon/wed
      • Two maintenance days (08:00-16:30) per week dynamically scheduled
        • scheduled on alternating weeks
        • priority of paired day possibilities: Mon/wed, Tue/Thu
    Gain Calibration
    ? -- Frank Ghigo and Ron Maddalena

    Scheduling Constraints
    • Avoid scheduling project changes exactly at 0700 or 1900 ET to minimize operator overload
      • Attempt to have project changes around 0730 and 1930 ET instead of at 0700 and 1900 exactly
      • If not possible, attempt a half hour earlier around 0630 and 1830 ET

    -- CarlBignell - 11 May 2007


    Topic Planning07C . { View | Diffs | r1.32 | > | r1.31 | > | r1.30 | More }
    Revision r1.1 - 11 May 2007 - 13:18 GMT - CarlBignell
    Revision r1.32 - 05 Nov 2007 - 15:16 GMT - RonMaddalena