  • primary X-band checkout after bandwidth and polarization switch upgrade. Who? How much? When?
  • primary K-band checkout after repair of noisy channel. Who? How much? When?
  • primary Q-band checkout after reinstallation. Who? How much? When?
>
>

  • primary X-band checkout after bandwidth and polarization switch upgrade. Who? 6 x 8h Aug 15 - Sep30
Changed:
<
<

  • backup S-band calibration. Who? How much? When?
  • primary?? 8 hours per month for system calibration (ending at 4 or 23 LST). Frank Ghigo
>
>

  • backup S-band calibration. Who? How much? When? (combine with sys cal?)
  • primary/backup 8 hours per month for system calibration (ending at 4 or 23 LST). Frank Ghigo
Deleted:
<
<

  • I.F. Balancing / Spectral Baselines testing?
Added:
>
>

Changed:
<
<

  • Total Amount for 04B currently undetermined.
  • 1A4 test time at X band 8 hours @21 LST
>
>

  • Proposal checkouts for 04B ~ 12h/mo+.
  • Proposal checkouts for 04C ~ 12h/mo+.
+(concentrated in first half of trimester)
Changed:
<
<

  • 04C Program checkouts
>
>

  • RFI tests. Fisher 4h (3-15 LST)

 <<O>>  Difference Topic GbtTestTimeRequirements (r1.8 - 07 Apr 2004 - RichardPrestage)
Added:
>
>

Any work which requires a moving antenna must be entered on this page.

Added:
>
>

Trimesters: 04A: Feb 2004 - May 2004; 04B: June 2004 - Sep 2004; 04C: Oct 2004 - Jan 2005; 05A: 2005 - May 2005

Changed:
<
<

Recuring (Periodic) Tests

>
>

Recurring (Periodic) Tests

Changed:
<
<

Each six week cycle:

>
>

Primary Each six week cycle:

Added:
>
>

Averages 40 hours primary time per month.

Changed:
<
<

Software Development

>
>

Software Development / Ease of Use Project

Changed:
<
<

Each six week cycle (in the following order):

>
>

backup Each six week cycle (in the following order):

Added:
>
>

Averages 15 hours backup time per month.

backup Observing/Configuration API testing (Frank Ghigo):

  • C4: May 15 - June 30 8 hr/wk
  • C5: July 1 - Aug 15 6 hr/wk
  • C6: Aug 15 - Sept 30 4 hr/wk
Averages: 32 backup hpm June, 24 hpm July, 20 hpm August, 16 hpm September.

New Instrument Commissioning
  • backup PF2 ~40 hours backup time May. Who?
  • primary Ka-band: 40 hours for the months of April and May 2004, dynamically scheduled. Brian Mason, Frank Ghigo
  • primary Ka band, CCB & MMConverter 8h/week dynamically scheduled at night from Oct 1, 04 - Feb 01, 05. Brian Mason and Ron Maddalena

Averages 40 hours primary and 40 hours backup time in May.
Averages 32 hours per month primary time October 2004 through February 2005

Changed:
<
<

Commissioning

>
>

Existing Receiver Checkout

Changed:
<
<

  • 40 hours for the months of April and May 2004, dynamically scheduled. Brian Mason
  • Ka band, CCB & MMConverter 8h/week dynamically scheduled at night from Oct 1, 04 - Feb 01, 05. Brian Mason and Ron Maddalena
>
>

  • primary X-band checkout after bandwidth and polarization switch upgrade. Who? How much? When?
  • primary K-band checkout after repair of noisy channel. Who? How much? When?
  • primary Q-band checkout after reinstallation. Who? How much? When?
Changed:
<
<

  • 8 hours per month for system calibration (ending at 4 or 23 LST). Frank Ghigo
>
>

  • backup S-band calibration. Who? How much? When?
  • primary?? 8 hours per month for system calibration (ending at 4 or 23 LST). Frank Ghigo
Changed:
<
<

  • Four hours per week for API testing. Frank Ghigo
  • Spigot tests: 12-15 hours per month through July to test new modes, preferably in
>
>

  • I.F. Balancing / Spectral Baselines testing?
  • Spigot tests: 12-15 hours backup per month through July to test new modes, preferably in
Changed:
<
<

 
>
>

  • 04C Program checkouts
Changed:
<
<

Last Updated on April 6, 2004.

>
>

Last Updated on April 7, 2004.

Added:
>
>

-- RichardPrestage - 07 Apr 2004


 <<O>>  Difference Topic GbtTestTimeRequirements (r1.7 - 06 Apr 2004 - KarenONeil)
Added:
>
>

  • Spigot tests: 12-15 hours per month through July to test new modes, preferably in 4-6 hours blocks separated by a week or more
  • Spectral line cross correlation tests of approximately 20 hours in September (dependent, of course, on having the modes ready to go by then)
Changed:
<
<

Last Updated on April 2, 2004.

>
>

Last Updated on April 6, 2004.


 <<O>>  Difference Topic GbtTestTimeRequirements (r1.6 - 05 Apr 2004 - JohnFord)
Changed:
<
<

  • One block of 12 hours for regression tests; full system and enatenna. Jim Braatz
  • One block of 4 hours for integration tests. David FLeming
>
>

  • One block of 12 hours for regression tests; full system and antenna. Jim Braatz
  • One block of 4 hours for integration tests. David Fleming

 <<O>>  Difference Topic GbtTestTimeRequirements (r1.5 - 05 Apr 2004 - RichardPrestage)
Changed:
<
<

Softeware Development

>
>

Software Development

Changed:
<
<

  • 40 hours for the months of April and May 204, dynamically scheduled. Brian Mason
>
>

  • 40 hours for the months of April and May 2004, dynamically scheduled. Brian Mason

 <<O>>  Difference Topic GbtTestTimeRequirements (r1.4 - 02 Apr 2004 - CarlBignell)
Changed:
<
<

  • 40 hours for the months of April and May, dynamically scheduled. Brian Mason
>
>

  • 40 hours for the months of April and May 204, dynamically scheduled. Brian Mason
  • Ka band, CCB & MMConverter 8h/week dynamically scheduled at night from Oct 1, 04 - Feb 01, 05. Brian Mason and Ron Maddalena

 <<O>>  Difference Topic GbtTestTimeRequirements (r1.3 - 02 Apr 2004 - CarlBignell)
Added:
>
>

  • 1A4 test time at X band 8 hours @21 LST

 <<O>>  Difference Topic GbtTestTimeRequirements (r1.2 - 02 Apr 2004 - CarlBignell)
Changed:
<
<

>
>

Changed:
<
<

Some of the tests requirements are based on the six week planning cycle. The six week planning cycles for 2004 end on: Mon Feb16, Mon Mar 31, Mon May 17, Wed June 30, Mon Aug 16, Thu Sep 30, Mon Nov 15, 2004 and Mon Jan 3, 2005

>
>

Some of the tests requirements are based on the six week planning cycle. The six week planning cycles for 2004 end on: Mon Feb16, Mon Mar 31, Mon May 17, Wed June 30, Mon Aug 16, Thu Sep 30, Mon Nov 15, 2004 and Mon Jan 3, 2005.

Changed:
<
<

>
>

Recuring (Periodic) Tests

Single Event Tests

Added:
>
>

Other

  • Four hours per week for API testing. Frank Ghigo
Changed:
<
<

Amount for 04B currently undetermined.

>
>

  • 4B25 & 4B17 checkouts
  • Total Amount for 04B currently undetermined.
Changed:
<
<

  • Four hours per week for API testing. Frank Ghigo
>
>

 
Changed:
<
<

Last Updated on March 31, 2004.
>
>

Last Updated on April 2, 2004.
Added:
>
>


 <<O>>  Difference Topic GbtTestTimeRequirements (r1.1 - 31 Mar 2004 - CarlBignell)
Added:
>
>

%META:TOPICINFO{author="CarlBignell" date="1080750660" format="1.0" version="1.1"}% %META:TOPICPARENT{name="WebHome"}%

GBT Test Requirements for 2004

Some of the tests requirements are based on the six week planning cycle. The six week planning cycles for 2004 end on: Mon Feb16, Mon Mar 31, Mon May 17, Wed June 30, Mon Aug 16, Thu Sep 30, Mon Nov 15, 2004 and Mon Jan 3, 2005

PTCS
Each six week cycle:
  • At least two 24 hour periods, dynamically scheduled.
  • An additional 12 hours; could be used in smaller blocks (e.g. 3 x 4 hours) as necessary.
Softeware Development
Each six week cycle (in the following order):
  • Two blocks of 4 hours each for integration tests; full system and no antenna. David Fleming
  • One block of 12 hours for regression tests; full system and enatenna. Jim Braatz
  • One block of 4 hours for integration tests. David FLeming
  • One block of 2 hours for regression tests and release. David Fleming
Commissioning
  • 40 hours for the months of April and May, dynamically scheduled. Brian Mason
GBT Calibration
  • 8 hours per month for system calibration (ending at 4 or 23 LST). Frank Ghigo
Proposal Checkouts
Amount for 04B currently undetermined.
Other
  • Four hours per week for API testing. Frank Ghigo

Last Updated on March 31, 2004.

-- CarlBignell - 31 Mar 2004


Topic GbtTestTimeRequirements . { View | Diffs | r1.9 | > | r1.8 | > | r1.7 | More }
Revision r1.1 - 31 Mar 2004 - 16:31 GMT - CarlBignell
Revision r1.9 - 07 Apr 2004 - 17:19 GMT - CarlBignell
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.