Project Close Out Punch List:

Fool/Idiot/Bullet-proof the data analysis code for GBT Spectrometer data

  • Wagg, 10-20 hours

Write up instructions for the analysis code

  • Wagg, 10-20 hours

Final version of GBT Spectrometry Memo

  • Complete

CCB Commissioning Memo

  • Mason, 10 hours

Update Tcal and Tsys values (continuum) in the calibration database with recent measurements.

  • Waiting on data reduction to produce Tcal and Tsys values.

List of 'To Do' items left unfinished... MR's, hardware, etc.

  • MR's:
    • Proper Setting of LO1 B Frequency To Avoid Interference, 10C107
    • Ka Manager Changes, 1C507
    • config_tool Changes Related to Ka Manager Changes, 7C507
    • IF Manager Changes Related to Ka Manager Changes, 8C507
    • config_tool Changes Regarding LO1B/mm-wave Converters, 10C507
    • Fix GFM's Processing of Ka Data, 9C507
    • Update AIPS++ Filler to Handle Ka Changes, 1C607
  • Hardware:
    • Conversion Mixers Noise Figure >36 GHz
    • Possible Zpec Path Compression
    • Tone Cal level amp





Important Dates

(Partly from the Trimester 07C Planning page.)

  • September 19: Ka Receiver installed on the telescope.
  • September 27: Zpectrometer installed on telescope.
  • September 24-October 12: Ka Receiver/Spectrometer Commissioning
  • October 1-13: Zpectrometer Commissioning
  • October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
    Minutes: KaMtgOct172007 Decision: No changes for 07C, 08A.
>
>

This page is being moved to https://wikio.nrao.edu/bin/view/GBT/KaBandReceiver

Deleted:
<
<

  • November 19-23: Thanksgiving
Changed:
<
<

  • November 30: Project Close Out Meeting

Recent meeting minutes

>
>

2007 Modification Meeting Minutes

Deleted:
<
<

Software Modification Requests

See Software Plan of Record Cycle 6, 2007

 <<O>>  Difference Topic KaBandReceiver (r1.152 - 15 Jan 2008 - GalenWatts)
Changed:
<
<

  • Pisano, Maddelena, 5 hours
>
>

  • Complete

 <<O>>  Difference Topic KaBandReceiver (r1.151 - 20 Dec 2007 - GalenWatts)
Added:
>
>

  • Waiting on data reduction to produce Tcal and Tsys values.
Deleted:
<
<

    • update Tcal and Tsys values (spectral and continuum) in the calibration database with recent measurements

 <<O>>  Difference Topic KaBandReceiver (r1.150 - 13 Dec 2007 - GalenWatts)
Added:
>
>

Update Tcal and Tsys values (continuum) in the calibration database with recent measurements.


 <<O>>  Difference Topic KaBandReceiver (r1.149 - 07 Dec 2007 - GalenWatts)
Added:
>
>

    • Tone Cal level amp

 <<O>>  Difference Topic KaBandReceiver (r1.148 - 05 Dec 2007 - BrianMason)
Added:
>
>

    • update Tcal and Tsys values (spectral and continuum) in the calibration database with recent measurements

 <<O>>  Difference Topic KaBandReceiver (r1.147 - 04 Dec 2007 - GalenWatts)
Changed:
<
<

    • Conversion Mixers Noise Figure <36 GHz
>
>

    • Conversion Mixers Noise Figure >36 GHz

 <<O>>  Difference Topic KaBandReceiver (r1.146 - 04 Dec 2007 - GalenWatts)
Changed:
<
<

Project Close Out Punch List

  • Bullet proof the data analysis code for GBT Spectrometer data
>
>

Project Close Out Punch List:

Fool/Idiot/Bullet-proof the data analysis code for GBT Spectrometer data

Changed:
<
<

  • Write up instructions for the analysis code
>
>

Write up instructions for the analysis code

Changed:
<
<

  • Final version of GBT Spectrometry Memo
>
>

Final version of GBT Spectrometry Memo

Changed:
<
<

  • CCB Commissioning Memo
>
>

CCB Commissioning Memo

Changed:
<
<

  • List of 'To Do' items left unfinished... MR's, hardware, etc.
    • Collaborative effort.
>
>

List of 'To Do' items left unfinished... MR's, hardware, etc.

  • MR's:
    • Proper Setting of LO1 B Frequency To Avoid Interference, 10C107
    • Ka Manager Changes, 1C507
    • config_tool Changes Related to Ka Manager Changes, 7C507
    • IF Manager Changes Related to Ka Manager Changes, 8C507
    • config_tool Changes Regarding LO1B/mm-wave Converters, 10C507
    • Fix GFM's Processing of Ka Data, 9C507
    • Update AIPS++ Filler to Handle Ka Changes, 1C607
  • Hardware:
    • Conversion Mixers Noise Figure <36 GHz
    • Possible Zpec Path Compression






 <<O>>  Difference Topic KaBandReceiver (r1.145 - 04 Dec 2007 - GalenWatts)
Added:
>
>

  • List of 'To Do' items left unfinished... MR's, hardware, etc.
    • Collaborative effort.

 <<O>>  Difference Topic KaBandReceiver (r1.144 - 03 Dec 2007 - GalenWatts)
Added:
>
>

  • Final version of GBT Spectrometry Memo
    • Pisano, Maddelena, 5 hours
  • CCB Commissioning Memo
    • Mason, 10 hours

 <<O>>  Difference Topic KaBandReceiver (r1.143 - 03 Dec 2007 - GalenWatts)
Added:
>
>

Project Close Out Punch List

  • Bullet proof the data analysis code for GBT Spectrometer data
    • Wagg, 10-20 hours
  • Write up instructions for the analysis code
    • Wagg, 10-20 hours

 <<O>>  Difference Topic KaBandReceiver (r1.142 - 03 Dec 2007 - GalenWatts)
Changed:
<
<

>
>

  • November 30: Project Close Out Meeting
Changed:
<
<

  • No further meetings planned at this time.
>
>

  • KaMtgNov302007 : November 30 Project Close Out Meeting, Unsuccessful

 <<O>>  Difference Topic KaBandReceiver (r1.141 - 30 Nov 2007 - GalenWatts)
Deleted:
<
<

Problems

  • 19 Sep 2007 - Ka receiver failed to talk to MCB until MCB was reset.
Added:
>
>

Information pertaining to the modifications done during the Summer of 2007 is located at KaMods2007.


 <<O>>  Difference Topic KaBandReceiver (r1.140 - 27 Nov 2007 - GalenWatts)
Changed:
<
<

  • September 2007: The receiver is installed on the GBT. Modifications have been made, see KaMods2007, that changed the receiver to two beams, one linear polarization per beam.
>
>

  • September 2007: The receiver is installed on the GBT. Modifications have been made that changed the receiver to two beams, one linear polarization per beam. See KaMods2007.

 <<O>>  Difference Topic KaBandReceiver (r1.139 - 27 Nov 2007 - GalenWatts)
Changed:
<
<

Status Reports

>
>

Status

  • September 2007: The receiver is installed on the GBT. Modifications have been made, see KaMods2007, that changed the receiver to two beams, one linear polarization per beam.

 <<O>>  Difference Topic KaBandReceiver (r1.138 - 19 Nov 2007 - GalenWatts)
Added:
>
>

Changed:
<
<

>
>


 <<O>>  Difference Topic KaBandReceiver (r1.137 - 16 Nov 2007 - GalenWatts)
Added:
>
>

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="KaFeedPatters.pdf" attr="" comment="Feed patterns at 26, 32 and 40 GHz" date="1195235468" path="KaFeedPatters.pdf" size="296959" user="GalenWatts" version="1.1"}%


 <<O>>  Difference Topic KaBandReceiver (r1.136 - 22 Oct 2007 - GalenWatts)
Changed:
<
<

  • October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
    Minutes: KaMtgOct172007 Decision: No changes for 7C, 8A.
>
>

  • October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
    Minutes: KaMtgOct172007 Decision: No changes for 07C, 08A.

 <<O>>  Difference Topic KaBandReceiver (r1.135 - 18 Oct 2007 - GalenWatts)
Changed:
<
<

  • September 19: Ka Receiver installed on the telescope!
  • September 27: Zpectrometer installed on telescope!
>
>

  • September 19: Ka Receiver installed on the telescope.
  • September 27: Zpectrometer installed on telescope.
Changed:
<
<

October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
Agenda: KaMtgOct172007

  • 1vs2Deltas.pdf: Ratios in dB of OMT path measurements made with the lab VNA. 1 and 2 are Side/Thru of the corresponding OMT, 3-6 are ratios of paths of each OMT in combinations that could be implemented in the receiver in the dual beam/dual circular configuration. Plot 6 looks promising for Zpectrometry.
>
>

  • October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
    Minutes: KaMtgOct172007 Decision: No changes for 7C, 8A.
Added:
>
>

Added:
>
>

  • 1vs2Deltas.pdf: Ratios in dB of OMT path measurements made with the lab VNA. 1 and 2 are Side/Thru of the corresponding OMT, 3-6 are ratios of paths of each OMT in combinations that could be implemented in the receiver in the dual beam/dual circular configuration. Plot 6 looks promising for Zpectrometry.

 <<O>>  Difference Topic KaBandReceiver (r1.134 - 17 Oct 2007 - GalenWatts)
Added:
>
>

  • 1vs2Deltas.pdf: Ratios in dB of OMT path measurements made with the lab VNA. 1 and 2 are Side/Thru of the corresponding OMT, 3-6 are ratios of paths of each OMT in combinations that could be implemented in the receiver in the dual beam/dual circular configuration. Plot 6 looks promising for Zpectrometry.
Added:
>
>

%META:FILEATTACHMENT{name="1vs2Deltas.pdf" attr="" comment="Ratios of OMT measurements" date="1192621693" path="1vs2Deltas.pdf" size="564727" user="GalenWatts" version="1.1"}%


 <<O>>  Difference Topic KaBandReceiver (r1.133 - 16 Oct 2007 - GalenWatts)
Changed:
<
<

October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?

>
>

October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?
Agenda: KaMtgOct172007


 <<O>>  Difference Topic KaBandReceiver (r1.132 - 12 Oct 2007 - GalenWatts)
Changed:
<
<

September 19: Ka Receiver installed on the telescope!

September 27: Zpectrometer installed on telescope!

>
>

  • September 19: Ka Receiver installed on the telescope!
  • September 27: Zpectrometer installed on telescope!
Changed:
<
<

October 17 : Ka-band single-pol configuration decision meeting: Continue or Revert?

>
>

October 17, 3:00 PM GB137 : Ka-band single-pol configuration decision meeting: Continue or Revert?


 <<O>>  Difference Topic KaBandReceiver (r1.131 - 12 Oct 2007 - GalenWatts)
Changed:
<
<

  • October 18 : Ka-band single-pol configuration decision: Continue or Revert?
>
>

October 17 : Ka-band single-pol configuration decision meeting: Continue or Revert?


 <<O>>  Difference Topic KaBandReceiver (r1.130 - 27 Sep 2007 - GalenWatts)
Changed:
<
<

September 19: Ka Receiver Installed on the telescope!

  • September 27: Zpectrometer installed on telescope
>
>

September 19: Ka Receiver installed on the telescope!

September 27: Zpectrometer installed on telescope!


 <<O>>  Difference Topic KaBandReceiver (r1.129 - 25 Sep 2007 - GalenWatts)
Added:
>
>

Important Dates

(Partly from the Trimester 07C Planning page.)

September 19: Ka Receiver Installed on the telescope!

  • September 27: Zpectrometer installed on telescope
  • September 24-October 12: Ka Receiver/Spectrometer Commissioning
  • October 1-13: Zpectrometer Commissioning
  • October 18 : Ka-band single-pol configuration decision: Continue or Revert?
  • November 19-23: Thanksgiving
Changed:
<
<

Upcoming meeting agendas

>
>

Deleted:
<
<

Important Dates

(Partly from the Trimester 07C Planning page.)
Deleted:
<
<

September 19: Ka Receiver Installed on the telescope!

  • September 27: Zpectrometer installed on telescope
  • September 24-October 12: Ka Receiver/Spectrometer Commissioning
  • October 1-13: Zpectrometer Commissioning
  • October 18 : Ka-band single-pol configuration decision: Continue or Revert?
  • November 19-23: Thanksgiving
Added:
>
>

  • KaMods2007 -- Information pertaining to the modifications done during the Summer of 2007.

 <<O>>  Difference Topic KaBandReceiver (r1.128 - 24 Sep 2007 - GalenWatts)
Changed:
<
<

  • September 24 (week of): Zpectrometer installed on telescope
>
>

  • September 27: Zpectrometer installed on telescope

 <<O>>  Difference Topic KaBandReceiver (r1.127 - 20 Sep 2007 - GalenWatts)
Changed:
<
<

Software Modification Requests for this project, in order of priority. Completed MR's are listed at the bottom of the table.

>
>

Software Modification Requests

See Software Plan of Record Cycle 6, 2007
Deleted:
<
<

MR rankings are:

  1. Must be complete for fall observing to commence
  2. Highly desired for fall observing
  3. Desired for fall observing
  4. Desired to complete the project

Vector Tcals are out of scope of this project

Updated at 8:50 AM EDT, September 20 but recent changes since SPoRC6 v1.60 may not be shown here, see Software Plan of Record Cycle 6, 2007

Rank MR Description Responsible Status Comments
2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Most implementation and unit testing completed, still need to retrofit focus scans. Final simulation testint will start next week.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Approved Waiting for completion of SubMotion? building blocks (17C507)
2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Another round of feedback send back to Ron and others. Dependant on 2C407
2 MR4C507 Indicate Subreflector Position in Data Maddelena/Garwood Submitted for review Written except for one possible item that would be useful to test during if possible. The checking step can begin now.
3 MR10C107 Proper Setting of LO1B Frequency To Avoid Interference Watts Being written Initial MR by Minter.
4 MR1C507 Ka Manager Changes Watts Being written  
4 MR7C507 config_tool Changes Related to Ka Manager Changes Watts Being written Dependant on 1C507
4 MR8C507 IF Manager Changes Related to Ka Manager Changes Watts Not started, need 1C507 first. Dependant on 1C507
4 MR10C507 config_tool Changes Regarding LO1B/mm-wave Converters Watts Being written Hacked together an MR last fall to address that 4 GHz of Ka-band could not be observed with the implemented, wrong algorithm. MR was implemented but LO1B is still being set to a value outside of a filter's range for most of Ka-band. Subsequently, Roger Norrod has been asked (by Maddelena) to write an MR that uses the correct algorithm, using notes he distributed in January. MR should be done by July 20.
4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano MR complete.  
4 MR9C507? Fix GFM's Processing of Ka Data Maddelena Not started Very little paper trail on the current implementation -- mostly emails. Supposedly this worked at one time but now doesn't. An annoyance -- requires losing telescope time at Astrid startup. Not started.
4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Code merge (GBTIDL and sparrow) finished, working on new organization of /home/sdfits.  
4 MR1C607? Update AIPS++ Filler to Handle Ka Changes ONeil   Nothing done yet
1 MR2C507 Auto-Clearing of Subreflector Commands Pisano DONE DONE  
1 MR11C507 Ka FITS Message Angle Comment ONeil DONE DONE  
2 MR6C507 Ka FITS Message Angle Keyword ONeil DONE DONE  
3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena DONE DONE  
4 Finalize Ka FITS File Specification Finalize Ka Rx fits specs O'Neil DONE DONE  

 <<O>>  Difference Topic KaBandReceiver (r1.126 - 20 Sep 2007 - GalenWatts)
Changed:
<
<

  • August 15: Commence Receiver Tcal, Trx, Lab Spectrometer and Software Manager testing
  • September 17 (week of): Receiver installed on telescope.
Dates following are contingent on scheduled week of September 17 receiver installation.
>
>

September 19: Ka Receiver Installed on the telescope!

Added:
>
>

Problems

  • 19 Sep 2007 - Ka receiver failed to talk to MCB until MCB was reset.
Changed:
<
<

Updated at 9:50 AM EDT, September 14 but recent changes since SPoRC6? v1.54 may not be shown here, see Software Plan of Record Cycle 6, 2007

>
>

Updated at 8:50 AM EDT, September 20 but recent changes since SPoRC6 v1.60 may not be shown here, see Software Plan of Record Cycle 6, 2007

Changed:
<
<

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Signed by CCC.  
>
>

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Code merge (GBTIDL and sparrow) finished, working on new organization of /home/sdfits.  

 <<O>>  Difference Topic KaBandReceiver (r1.125 - 14 Sep 2007 - GalenWatts)
Changed:
<
<

Upcoming meeting agendas

>
>

Added:
>
>

Upcoming meeting agendas


 <<O>>  Difference Topic KaBandReceiver (r1.124 - 14 Sep 2007 - GalenWatts)
Changed:
<
<

Updated at 10:10 AM EDT, September 10 but recent changes may not be shown here, see Software Plan of Record Cycle 6, 2007

>
>

Updated at 9:50 AM EDT, September 14 but recent changes since SPoRC6? v1.54 may not be shown here, see Software Plan of Record Cycle 6, 2007

Changed:
<
<

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Implementation has commenced.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Approved Dependant on 17C507
>
>

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Most implementation and unit testing completed, still need to retrofit focus scans. Final simulation testint will start next week.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Approved Waiting for completion of SubMotion? building blocks (17C507)
Changed:
<
<

4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano Under CCC review  
>
>

4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano MR complete.  
Changed:
<
<

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Awaiting Baker's signature  
>
>

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Signed by CCC.  

 <<O>>  Difference Topic KaBandReceiver (r1.123 - 12 Sep 2007 - GalenWatts)
Changed:
<
<

  • Lab Spectrometer data from the tests of September 7-11 is in /home/labdata/TKA070907, .../TKA070909, .../TKA070910, .../TKA070910B, .../TKA070911.
  • Beam 1, 39/0.8 GHz
>
>

  • Lab Spectrometer data from the tests of September 7-11 is in /home/labdata/TKA070907, .../TKA070909, .../TKA070910, .../TKA070910B, .../TKA070911. Each directory has a text file, 'Notes,' that explains the details of particular scans.
Added:
>
>

Lab Spectrometer Waterfall Baseline Plots from September, 2007

Each trace is (Scan B - Scan A)/Scan A, earlier scan are towards the bottom.
  • Beam 2, 27.5/0.8 GHz:
    B2G275.png

  • Beam 2, 33/0.8 GHz:
    B2G33.png

  • Beam 2, 36.5/0.8 GHz:
    B2G365.png

  • Beam 1, 39/0.8 GHz
Added:
>
>

%META:FILEATTACHMENT{name="B2G33.png" attr="h" comment="Beam 2, 33/0.8 GHz" date="1189616800" path="B2G33.png" size="111967" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="B2G275.png" attr="h" comment="Beam 2, 27.5/0.8 GHz" date="1189616832" path="B2G275.png" size="115530" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="B2G365.png" attr="h" comment="Beam 2, 36.5/0.8 GHz" date="1189616863" path="B2G365.png" size="114241" user="GalenWatts" version="1.1"}%


 <<O>>  Difference Topic KaBandReceiver (r1.122 - 12 Sep 2007 - GalenWatts)
Added:
>
>

  • Beam 1, 39/0.8 GHz

B1G39.png

Added:
>
>

  • B1G39: Beam 1, 39/0.8 GHz
Added:
>
>

%META:FILEATTACHMENT{name="B1G39" attr="h" comment="Beam 1, 39/0.8 GHz" date="1189611471" path="B1G39" size="69155" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="B1G39.png" attr="h" comment="Beam 1, 39/0.8 GHz" date="1189612348" path="B1G39.png" size="113268" user="GalenWatts" version="1.2"}%


 <<O>>  Difference Topic KaBandReceiver (r1.121 - 12 Sep 2007 - GalenWatts)
Added:
>
>

  • Lab Spectrometer data from the tests of September 7-11 is in /home/labdata/TKA070907, .../TKA070909, .../TKA070910, .../TKA070910B, .../TKA070911.

 <<O>>  Difference Topic KaBandReceiver (r1.120 - 10 Sep 2007 - GalenWatts)
Deleted:
<
<

  • July 28-Aug 4: K. O'Neil, Marganian out of town
  • August 1: B. Garwood in GB
  • August 3: Need Zpectrometer astronomy decision for Oct 1-Jan30 period.
  • August 6, AM: CCB Testing.
  • August 6-10: Andy Harris et al in GB, Ka-Z Testing.
  • August 9-14: Galen out of town.
  • August 15: Track shutdown complete.
  • August 15: B. Garwood in GB
Changed:
<
<

Software Modification Requests for this project, in order of priority

>
>

Software Modification Requests for this project, in order of priority. Completed MR's are listed at the bottom of the table.

Changed:
<
<

Updated at 8:15 AM EDT, August 31 but recent changes may not be shown here, see Software Plan of Record C6, 2007

>
>

Updated at 10:10 AM EDT, September 10 but recent changes may not be shown here, see Software Plan of Record Cycle 6, 2007

Changed:
<
<

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Under CCC review  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being checked Dependant on 17C507
>
>

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Implementation has commenced.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Approved Dependant on 17C507
Changed:
<
<

4 MR9C507? Fix GFM's Processing of Ka Data Maddelena Not started Very little paper trail on the current implementation -- mostly emails. Supposedly this worked at one time but now doesn't. An annoyance -- requires losing telescope time at Astrid startup.
>
>

4 MR9C507? Fix GFM's Processing of Ka Data Maddelena Not started Very little paper trail on the current implementation -- mostly emails. Supposedly this worked at one time but now doesn't. An annoyance -- requires losing telescope time at Astrid startup. Not started.

 <<O>>  Difference Topic KaBandReceiver (r1.119 - 04 Sep 2007 - GalenWatts)
Deleted:
<
<

Upcoming meeting agendas

Added:
>
>

Upcoming meeting agendas


 <<O>>  Difference Topic KaBandReceiver (r1.118 - 31 Aug 2007 - GalenWatts)
Added:
>
>

Pictures

Changed:
<
<

Updated at 11:50 AM EDT, August 17 but recent changes may not be shown here, see Software Plan of Record C6, 2007

>
>

Updated at 8:15 AM EDT, August 31 but recent changes may not be shown here, see Software Plan of Record C6, 2007

Changed:
<
<

2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Awaiting comments, Dependant on 2C407
2 MR4C507 Indicate Subreflector Position in Data Maddelena/Garwood Submitted for review MR to be submitted for checking by July 20 - Status?
>
>

2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Another round of feedback send back to Ron and others. Dependant on 2C407
2 MR4C507 Indicate Subreflector Position in Data Maddelena/Garwood Submitted for review Written except for one possible item that would be useful to test during if possible. The checking step can begin now.
Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="Front.jpg" attr="" comment="Inside view of dewar, modified version." date="1188561910" path="Front.jpg" size="592313" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="Side.jpg" attr="" comment="Side view of dewar internal components." date="1188562143" path="Side.jpg" size="201037" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="50Kabsorber.jpg" attr="" comment="50K radiation shield with absorber." date="1188562204" path="50Kabsorber.jpg" size="214220" user="GalenWatts" version="1.1"}%


 <<O>>  Difference Topic KaBandReceiver (r1.117 - 31 Aug 2007 - KarenONeil)
Changed:
<
<

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Being written  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being rewritten Dependant on 17C507
>
>

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Under CCC review  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being checked Dependant on 17C507
Changed:
<
<

4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano   Tests in the lab showed that the simulation in the IFManager were based on outdated documentation. Ran experiments on the simulator to attempt to verify this was the problem on the telescope. Resolution is somewhat complex since the observing on the telescope was performed with two errors: wrong receiver simulation and wrong cabling file. We cannot be completely certain that we are reproducing the environment that was on the telescope.
>
>

4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano Under CCC review  
Changed:
<
<

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker First draft of MR written.  
4 MR1C607? Update AIPS++ Filler to Handle Ka Changes ONeil   MR number changed! Status?
>
>

4 MR15C507 Merge Zpectrometer code branch into main trunk ONeil, Baker Awaiting Baker's signature  
4 MR1C607? Update AIPS++ Filler to Handle Ka Changes ONeil   Nothing done yet

 <<O>>  Difference Topic KaBandReceiver (r1.116 - 29 Aug 2007 - GalenWatts)
Changed:
<
<

>
>


 <<O>>  Difference Topic KaBandReceiver (r1.115 - 17 Aug 2007 - GalenWatts)
Deleted:
<
<

Upcoming meeting agendas

Added:
>
>

Upcoming meeting agendas

Changed:
<
<

Updated at 11:50 AM EDT, August 16 but recent changes may not be shown here, see Software Plan of Record C6, 2007

>
>

Updated at 11:50 AM EDT, August 17 but recent changes may not be shown here, see Software Plan of Record C6, 2007

Deleted:
<
<

1 MR2C507 Auto-Clearing of Subreflector Commands Pisano DONE DONE  
1 MR11C507 Ka FITS Message Angle Comment ONeil DONE DONE  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being rewritten  
Added:
>
>

2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being rewritten Dependant on 17C507
2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Awaiting comments, Dependant on 2C407
Deleted:
<
<

2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Awaiting comments
2 MR6C507 Ka FITS Message Angle Keyword ONeil DONE DONE  
3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena DONE DONE  
Deleted:
<
<

4 Finalize Ka FITS File Specification Finalize Ka Rx fits specs O'Neil DONE DONE  
Changed:
<
<

4 MR7C507 config_tool Changes Related to Ka Manager Changes Watts Being written  
4 MR8C507 IF Manager Changes Related to Ka Manager Changes Watts Not started, need 1C507 first.  
>
>

4 MR7C507 config_tool Changes Related to Ka Manager Changes Watts Being written Dependant on 1C507
4 MR8C507 IF Manager Changes Related to Ka Manager Changes Watts Not started, need 1C507 first. Dependant on 1C507
Added:
>
>

1 MR2C507 Auto-Clearing of Subreflector Commands Pisano DONE DONE  
1 MR11C507 Ka FITS Message Angle Comment ONeil DONE DONE  
2 MR6C507 Ka FITS Message Angle Keyword ONeil DONE DONE  
3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena DONE DONE  
4 Finalize Ka FITS File Specification Finalize Ka Rx fits specs O'Neil DONE DONE  

 <<O>>  Difference Topic KaBandReceiver (r1.114 - 17 Aug 2007 - AmyShelton)
Changed:
<
<

2 MR17C07 Subreflector Nodding Observing API Building Block Pisano Being written  
>
>

2 MR17C507 Subreflector Nodding Observing API Building Block Pisano Being written  

 <<O>>  Difference Topic KaBandReceiver (r1.113 - 17 Aug 2007 - AmyShelton)
Changed:
<
<

Updated at 11:50 AM EDT, August 16 but recent changes may not be shown here, see Software Plan of Record C5, 2007

>
>

Updated at 11:50 AM EDT, August 16 but recent changes may not be shown here, see Software Plan of Record C6, 2007

Added:
>
>

2 MR17C07 Subreflector Nodding Observing API Building Block Pisano Being written  
Changed:
<
<

4 MR16C507 Update AIPS++ Filler to Handle Ka Changes ONeil   MR number changed! Status?
>
>

4 MR1C607? Update AIPS++ Filler to Handle Ka Changes ONeil   MR number changed! Status?

 <<O>>  Difference Topic KaBandReceiver (r1.112 - 17 Aug 2007 - KarenONeil)
Changed:
<
<

4 Finalize Ka FITS File Specification Finalize Ka Rx fits specs O'Neil Submitted for review  
>
>

4 Finalize Ka FITS File Specification Finalize Ka Rx fits specs O'Neil DONE DONE  

 <<O>>  Difference Topic KaBandReceiver (r1.111 - 17 Aug 2007 - KarenONeil)
Changed:
<
<

1 MR2C507 Auto-Clearing of Subreflector Commands Pisano Awaiting sponsor tests  
1 MR11C507 Ka FITS Message Angle Comment ONeil Needs testing on telescope.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Submitted for review MR written, need resolution of design, meeting held Aug 9 to decide..
2 MR4C507 Indicate Subreflector Position in Data Maddelena/Garwood Submitted for review MR to be submitted for checking by July 20
2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena To be written MR to be submitted for review no later than August 15
2 MR6C507 Ka FITS Message Angle Keyword ONeil Submitted to CCC MR to be submitted for checking by July 18
3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena Waiting for sponsor approval. Waiting for sponsor approval. Promised for August 2
>
>

1 MR2C507 Auto-Clearing of Subreflector Commands Pisano DONE DONE  
1 MR11C507 Ka FITS Message Angle Comment ONeil DONE DONE  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Being rewritten  
2 MR4C507 Indicate Subreflector Position in Data Maddelena/Garwood Submitted for review MR to be submitted for checking by July 20 - Status?
2 MR5C507 Implement GBTIDL Reduction Procedure for Subreflector Nodding Pisano & Maddelena submitted for review Awaiting comments
2 MR6C507 Ka FITS Message Angle Keyword ONeil DONE DONE  
3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena DONE DONE  
Changed:
<
<

4 MR16C507 Update AIPS++ Filler to Handle Ka Changes ONeil    
>
>

4 MR16C507 Update AIPS++ Filler to Handle Ka Changes ONeil   MR number changed! Status?

 <<O>>  Difference Topic KaBandReceiver (r1.110 - 16 Aug 2007 - GalenWatts)
Changed:
<
<

>
>


 <<O>>  Difference Topic KaBandReceiver (r1.109 - 16 Aug 2007 - GalenWatts)
Added:
>
>

Changed:
<
<

Updated at 9:30 AM EDT, August 2nd but recent changes may not be shown here, see Software Plan of Record C5, 2007

>
>

Updated at 11:50 AM EDT, August 16 but recent changes may not be shown here, see Software Plan of Record C5, 2007

Changed:
<
<

1 MR11C507 Ka FITS Message Angle Comment ONeil Awaiting sponsor tests  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Submitted for review MR written, need resolution of design, scheduled to be decided by end of July. Discussions continuing apparently from the email traffic.
>
>

1 MR11C507 Ka FITS Message Angle Comment ONeil Needs testing on telescope.  
2 MR2C407 Control of Subreflector Nodding by Astrid Pisano Submitted for review MR written, need resolution of design, meeting held Aug 9 to decide..
Changed:
<
<

4 MR8C507 IF Manager Changes Related to Ka Manager Changes Watts Being written  
4 MR10C507 config_tool Changes Regarding LO1B/mm-wave Converters Watts Being written Hacked together an MR last fall to address that 4 GHz of Ka-band could not be obsrved with the implementd, wrong algorithm. MR was implemented but LO1B is still being set to a value outside of a filter's range for most of Ka-band. Subsequently, Roger Norrod has been asked (by Maddelena) to write an MR that uses the correct algorithm, using notes he distributed in January. MR should be done by July 20.
4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano   Tests in the lab showed that the simulation in the IFManager were based on outdated documentation. Ran experiments on the simulator to attempt to verify this was the problem on the telescope. Resolution is somewhat complext since the observing on the telescope was performed with two errors: wrong receiver simulation and wrong cabling file. We cannot be completely certain that we are reproducing the environment that was on the telescope.
>
>

4 MR8C507 IF Manager Changes Related to Ka Manager Changes Watts Not started, need 1C507 first.  
4 MR10C507 config_tool Changes Regarding LO1B/mm-wave Converters Watts Being written Hacked together an MR last fall to address that 4 GHz of Ka-band could not be observed with the implemented, wrong algorithm. MR was implemented but LO1B is still being set to a value outside of a filter's range for most of Ka-band. Subsequently, Roger Norrod has been asked (by Maddelena) to write an MR that uses the correct algorithm, using notes he distributed in January. MR should be done by July 20.
4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano   Tests in the lab showed that the simulation in the IFManager were based on outdated documentation. Ran experiments on the simulator to attempt to verify this was the problem on the telescope. Resolution is somewhat complex since the observing on the telescope was performed with two errors: wrong receiver simulation and wrong cabling file. We cannot be completely certain that we are reproducing the environment that was on the telescope.

 <<O>>  Difference Topic KaBandReceiver (r1.108 - 03 Aug 2007 - GalenWatts)
Deleted:
<
<

Upcoming meeting agendas

Added:
>
>

Upcoming meeting agendas

Added:
>
>

(Partly from the Trimester 07C Planning page.)

Changed:
<
<

  • August 20: Commence Receiver Tcal, Trx, Lab Spectrometer and Software Manager testing
>
>

  • August 15: Commence Receiver Tcal, Trx, Lab Spectrometer and Software Manager testing

 <<O>>  Difference Topic KaBandReceiver (r1.107 - 02 Aug 2007 - GalenWatts)
Added:
>
>

Deleted:
<
<

  • August 14-17: Ka-CCB Testing.
Changed:
<
<

  • September 17 (week of): Receiver installed on telescope (Desired)
>
>

  • September 17 (week of): Receiver installed on telescope.
Dates following are contingent on scheduled week of September 17 receiver installation.
Changed:
<
<

  • September 24-October 6: Ka Receiver Commissioning
>
>

  • September 24-October 12: Ka Receiver/Spectrometer Commissioning
Added:
>
>

  • October 18 : Ka-band single-pol configuration decision: Continue or Revert?
Changed:
<
<

Recent changes may not be shown here, see Software Plan of Record C5, 2007

>
>

Updated at 9:30 AM EDT, August 2nd but recent changes may not be shown here, see Software Plan of Record C5, 2007

Changed:
<
<

3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena Waiting for sponsor approval. MR to be submitted for review no later than August 15
>
>

3 MR3C507 Set GFM's Processing of Ka Data to Raw Maddelena Waiting for sponsor approval. Waiting for sponsor approval. Promised for August 2
Changed:
<
<

4 MR3C407 Correct Labeling of Ka-band Hybrid-switched Signals Pisano   Paul Marganian and Bob Garwood are filling in sections of MR on sdfits and gfm. Nature of the problem still being worked on, will be running some tests on the simulator this week.
4 MR9C507? Fix GFM's Processing of Ka Data Maddelena To be written Very little paper trail on the current implementation -- mostly emails. Supposedly this worked at one time but now doesn't. An annoyance -- requires losing telescope time at Astrid startup.
>
>