 <<O>>  Difference Topic ProjectGoals (r1.45 - 28 Feb 2008 - CarlaBeaudet)
Changed:
<
<

GBT RFI MS Gimbal Installed on GBT 4/31/07 5/12/07  
GBT RFI MS antennas and electronics Installed on GBT 5/31/07    
GBT RFI MS systems checkout 6/31/07    
>
>

GBT RFI MS Gimbal Installed on GBT 4/31/07 5/12/07 Complete
GBT RFI MS antennas and electronics Installed on GBT 5/31/07   Complete
GBT RFI MS systems checkout 6/31/07   Complete

 <<O>>  Difference Topic ProjectGoals (r1.44 - 13 Jul 2007 - KarenONeil)
Changed:
<
<

Modification requests - All Sections Complete 3/31/07 5/15/07 Design and testing sections will be complete upon deployment.
>
>

Modification requests - All Sections Complete 3/31/07 9/1/07 Design and testing sections will be complete upon deployment.
Changed:
<
<

Review panel 04/24/2007    
>
>

Review panel 04/24/2007   Complete
Changed:
<
<

Project complete 02/15/07 04/15/06  
>
>

Project complete 02/15/07 04/15/06 Complete
Changed:
<
<

Version 2.0 of Observing Manual completed 04/01/07 4/20/07  
>
>

Version 2.0 of Observing Manual completed 04/01/07 4/20/07 Complete
Changed:
<
<

Proposal review 06/01/07    
Final proposal complete 06/30/07    
Stage I tools complete, Dynamic scheduling commences 06/01/08    
Stage II tools complete 06/01/09    
>
>

Proposal review 06/01/07 06/06/07 Complete
Final proposal complete 06/30/07 08/15/07 Implementing changes from the reviews; Delayed due to less staff than anticipated
Stage I tools complete, Dynamic scheduling commences 06/01/08 10/01/08 Delayed due to less staff than anticipated
Stage II tools complete 06/01/09 10/01/09 Delayed due to less staff than anticipated
Changed:
<
<

Main Servo complete 06/30/07 08/30/07  
>
>

Main Servo complete 06/30/07 08/30/07  
Changed:
<
<

Subreflector nod tests memo released 04/01/07    
>
>

Subreflector nod tests memo released 04/01/07 05/03/07 Complete
Changed:
<
<

Test YGOR manager on MUSTANG on GBT 01/30/08    
Write up results from 2nd engineering run 03/30/08    
>
>

Test YGOR manager on MUSTANG on GBT 01/30/08    
Document results from 2nd engineering run 03/30/08    
Changed:
<
<

Upgrade of pointing model with track terms 09/30/07    
Transfer of pointing model generation ability to Green Bank 12/31/07    
Streamlining of OOF Holography procedure 02/01/08    
Upgrade of traditional Holography Manager 10/31/07    
>
>

Upgrade of pointing model with track terms 09/30/07    
Transfer of pointing model generation ability to Green Bank 04/01/07 12/31/07  
Streamlining of OOF Holography procedure 02/01/08    
Upgrade of traditional Holography Manager 10/31/07    

 <<O>>  Difference Topic ProjectGoals (r1.43 - 12 Jul 2007 - BrianMason)
Changed:
<
<

Complete recharacterization of current array in the fixed dewar 06/05/07    
Complete haracterization of the test array in the fixed dewar 06/20/07    
>
>

Complete recharacterization of current array in the fixed dewar 06/05/07 06/01/07 Complete
Complete haracterization of the test array in the fixed dewar 06/20/07 06/15/07 Complete
Added:
>
>

Install on GBT for engineering & early science run 12/15/07    
Test YGOR manager on MUSTANG on GBT 01/30/08    
Write up results from 2nd engineering run 03/30/08    

 <<O>>  Difference Topic ProjectGoals (r1.42 - 09 Jul 2007 - AmyShelton)
Changed:
<
<

Deploy BOS to Socorro and Green Bank 5/15/07    
>
>

Deploy BOS to Socorro and Green Bank 5/15/07 9/1/07 Getting sponsor feedback and the sponsor testing process has been slower than expected.
Changed:
<
<

Subreflector nod tests memo released 04/01/07  
>
>

Subreflector nod tests memo released 04/01/07    
Changed:
<
<

Upgrade of pointing model with track terms 09/30/07  
>
>

Upgrade of pointing model with track terms 09/30/07    
Changed:
<
<

Streamlining of OOF Holography procedure 02/01/08  
Upgrade of traditional Holography Manager 10/31/07  
Recommissioning of traditional holography receiver 04/01/08  
>
>

Streamlining of OOF Holography procedure 02/01/08    
Upgrade of traditional Holography Manager 10/31/07    
Recommissioning of traditional holography receiver 04/01/08    
Changed:
<
<

Project assesment complete 08/31/07    
>
>

Project assesment complete 08/31/07   This is on-hold indefinitely pending resource allocation.

 <<O>>  Difference Topic ProjectGoals (r1.41 - 06 Jul 2007 - RonMaddalena)
Changed:
<
<

Final 10 units complete 12/01/06 04/30/07  
>
>

Final 10 units complete 12/01/06 04/30/07 Complete

 <<O>>  Difference Topic ProjectGoals (r1.40 - 06 Jul 2007 - ToddHunter)
Deleted:
<
<

Ability to generate pointing and track model in place 04/01/07    
Changed:
<
<

Laser Range Finder V2 development complete 09/31/07 03/01/08  
>
>

Laser Range Finder V2 development complete 09/30/07 03/01/08  
Upgrade of pointing model with track terms 09/30/07  
Transfer of pointing model generation ability to Green Bank 12/31/07    
Streamlining of OOF Holography procedure 02/01/08  
Upgrade of traditional Holography Manager 10/31/07  
Recommissioning of traditional holography receiver 04/01/08  

 <<O>>  Difference Topic ProjectGoals (r1.39 - 06 Jul 2007 - JohnFord)
Changed:
<
<

Upgrade Complete 02/15/07 07/31/07 Will be performed during summer shutdown
>
>

Upgrade Complete 02/15/07 08/31/07 Will be performed during summer shutdown
Changed:
<
<

First version of the iBob and ADC modules produced and documented 06/01/07    
>
>

First version of the iBob and ADC modules produced and documented 06/01/07 06/28/07 Complete
Changed:
<
<

Initial PLC Design Complete 01/15/07 02/28/07  
PLC Programming Complete 02/28/07 03/30/07  
PLC Interface Cards Procured 02/28/07    
Panels wired and tested 04/30/07    
All programming complete 05/31/07    
Main Servo installation begins 06/01/07    
Main Servo complete 06/30/07    
Secondary Servo installation begins 07/01/07    
Secondary Servo installation complete 07/31/07    
Project cleanup 08/01/07    
Project Complete 08/31/07    
>
>

Initial PLC Design Complete 01/15/07 02/28/07 Complete
PLC Programming Complete 02/28/07 07/30/07  
PLC Interface Cards Procured 02/28/07   Complete
Panels wired and tested 04/30/07   07/30/07
All programming complete 05/31/07   07/30/07
Main Servo installation begins 06/01/07 08/07/07  
Main Servo complete 06/30/07 08/30/07  
Secondary Servo installation begins 07/01/07 05/01/08  
Secondary Servo installation complete 07/31/07 05/31/08  
Project cleanup 08/01/07 08/01/08  
Project Complete 08/31/07 08/31/08  
Changed:
<
<

Trajectory Generations and Servo improvements complete 12/31/06 4/30/2007 Only slow-speed tracking improvements
Short-term slow-speed tracking improvements complete 09/30/06 3/15/2007  
>
>

Trajectory Generations and Servo improvements complete 12/31/06 8/30/2007 Only slow-speed tracking improvements
Short-term slow-speed tracking improvements complete 09/30/06 8/15/2007  
Changed:
<
<

Wind measuring instruments design complete 07/10/07    
PLC interlock system installed 08/31/07    
>
>

Wind measuring instruments design complete 07/10/07   On Hold
PLC interlock system installed 08/31/08    
Changed:
<
<

Laser Range Finder V2 development complete 09/31/07    
>
>

Laser Range Finder V2 development complete 09/31/07 03/01/08  
Changed:
<
<

Control System upgrade complete 10/01/06 03/31/07  
>
>

Control System upgrade complete 10/01/06 03/31/07 Complete
Changed:
<
<

LTA fix Complete 10/01/07 07/15/07  
>
>

LTA fix Complete 10/01/07 09/15/07  

 <<O>>  Difference Topic ProjectGoals (r1.38 - 06 Jul 2007 - GlenLangston)
Changed:
<
<

Improved CITECH system health reporting 02/28/07    
>
>

Improved CITECH system health reporting 02/28/07 06/01/07 Complete

 <<O>>  Difference Topic ProjectGoals (r1.37 - 06 Jul 2007 - BobAnderson)
Changed:
<
<

Next 24 wear and base plates manufactured 03/30/07 4/2/07  
All components on site 03/30/07 4/5/07  
Refurbishment starts 05/01/07 4/30/07  
First set plate installations complete 07/05/07    
Second set of plate installations complete 08/04/07    
Installation phase complete 08/04/07    
>
>

Next 24 wear and base plates manufactured 03/30/07 4/2/07 Complete
All components on site 03/30/07 4/5/07 Complete
Refurbishment starts 05/01/07 4/30/07 Complete
First set plate installations complete 07/05/07 6/28/07 Complete
Second set of plate installations complete 08/04/07 8/17/07  
Installation phase complete 08/04/07 8/17/07  

 <<O>>  Difference Topic ProjectGoals (r1.36 - 09 Apr 2007 - CarlaBeaudet)
Added:
>
>

GBT RFI MS Gimbal Installed on GBT 4/31/07 5/12/07  
GBT RFI MS antennas and electronics Installed on GBT 5/31/07    
GBT RFI MS systems checkout 6/31/07    

 <<O>>  Difference Topic ProjectGoals (r1.35 - 06 Apr 2007 - KarenONeil)
Added:
>
>

Complete recharacterization of current array in the fixed dewar 06/05/07    
Complete haracterization of the test array in the fixed dewar 06/20/07    
Verify improved noise & cryogenic performance on the GBT 08/30/07    

 <<O>>  Difference Topic ProjectGoals (r1.34 - 06 Apr 2007 - KarenONeil)
Deleted:
<
<

Changed:
<
<

Work Plan and Schedule complete 10/01/06 10/10/06 10/10/06
First 24 wear and base plates manufactured 01/31/07 03/01/07 3/13/07
Next 24 wear and base plates manufactured 03/30/07 4/2/07  
All components on site 03/30/07 4/5/07  
Refurbishment starts 05/01/07 4/30/07  
>
>

Work Plan and Schedule complete 10/01/06 10/10/06 Complete
First 24 wear and base plates manufactured 01/31/07 03/13/07 Complete
Next 24 wear and base plates manufactured 03/30/07 4/2/07  
All components on site 03/30/07 4/5/07  
Refurbishment starts 05/01/07 4/30/07  
Changed:
<
<

Documentation of current calibration procedures complete 10/31/06 2/16/06 Complete and available on the GBTIDL web page
>
>

Documentation of current calibration procedures complete 10/31/06 2/16/06 Complete
Added:
>
>

Review panel 04/24/2007    
Changed:
<
<

Version 2.0 of Observing Manual completed 04/01/07   Will be available by 4/20/07
>
>

Version 2.0 of Observing Manual completed 04/01/07 4/20/07  
Changed:
<
<

Test Phase Complete 04/31/07 10/31/07 Test phase moved to fall to ease burden on GBT observers
>
>

Test Phase I Complete 04/31/07 9/31/07 Test phase moved to fall to ease burden on GBT observers
Changed:
<
<

Stage I tools complete, Dynamic scheduling commences 02/01/08    
Stage II tools complete 02/01/09    
>
>

Stage I tools complete, Dynamic scheduling commences 06/01/08    
Stage II tools complete 06/01/09    
FPGA Development Project
First version of the iBob and ADC modules produced and documented 06/01/07    
Changed:
<
<

Subreflector NOD tests 2/15/07 03/01/06 Complete, memo by 4/1/07
>
>

Subreflector NOD tests 2/15/07 03/01/06 Complete
Subreflector nod tests memo released 04/01/07  
Deleted:
<
<

The remaining Spectrometer milestones need to be replaced by new ones in light of the change to simply fix the FPGA socket problem
Changed:
<
<

LTA upgrade schedule available 9/01/06 11/09/06  
DSP analysis complete 11/15/06    
Cross correlation MRs complete 11/15/06 2/15/07 (12/21/06)  
>
>

Cross correlation MRs complete 11/15/06 2/15/07  
Changed:
<
<

LTA upgrade complete 10/01/07 07/15/07  
>
>

LTA fix Complete 10/01/07 07/15/07  
Changed:
<
<

Science validation complete 05/31/07    
>
>

Science validation complete 06/01/08    
Changed:
<
<

Control System Upgrades
(Inter-scan Latency Reduction Project, Unified Messaging, Fits data streams)
>
>

Control System Upgrades
(Inter-scan Latency Reduction Project, Unified Messaging, Fits data streams)

 <<O>>  Difference Topic ProjectGoals (r1.33 - 05 Apr 2007 - RonMaddalena)
Changed:
<
<

Documentation of current calibration procedures complete 10/31/06 2/16/06 Complete, still to be circulated
>
>

Documentation of current calibration procedures complete 10/31/06 2/16/06 Complete and available on the GBTIDL web page
Changed:
<
<

Chapter 3: Observing Strategies; released for comment 01/12/07   To be released with Cptr 1
Chapter 6: Tutorial on Weather and Dyn Sched; released for comment 01/26/07    
Chapter 1: Intro to Astrid; released for comment 02/09/07    
Chapter 4: GBT IF System; released for comment 02/16/07    
Chapter 5: RFI; released for comment 03/2/07    
Chapter 7: Before your Observing; released for comment 03/9/07    
Chapter 8: After your Observing; released for comment 03/9/07    
Version 2.0 of Observing Manual completed 04/01/07    
>
>

Chapter 3: Observing Strategies; released for comment 01/12/07 3/6/07 Complete
Chapter 6: Tutorial on Weather and Dyn Sched; released for comment 01/26/07 3/6/07 Complete
Chapter 1: Intro to Astrid; released for comment 02/09/07 3/6/07 Complete
Chapter 4: GBT IF System; released for comment 02/16/07 3/6/07 Complete
Chapter 5: RFI; released for comment 03/2/07 3/6/07 Complete
Chapter 7: Before your Observing; released for comment 03/9/07 3/6/07 Complete
Chapter 8: After your Observing; released for comment 03/9/07 3/6/07 Complete
Version 2.0 of Observing Manual completed 04/01/07   Will be available by 4/20/07
Changed:
<
<

Subreflector NOD tests 2/15/07 03/01/06 New commissioning exercise
>
>

Subreflector NOD tests 2/15/07 03/01/06 Complete, memo by 4/1/07

 <<O>>  Difference Topic ProjectGoals (r1.32 - 05 Apr 2007 - RogerNorrod)
Changed:
<
<

Final 10 units complete 12/01/06 03/31/07  
>
>

Final 10 units complete 12/01/06 04/30/07  
Changed:
<
<

LTA circuit built 06/01/07 04/15/07  
>
>

LTA circuit built 06/01/07 04/02/07 Complete, bench tests underway

 <<O>>  Difference Topic ProjectGoals (r1.31 - 05 Apr 2007 - AmyShelton)
Changed:
<
<

Welding plan and schedule complete 08/31/06 /08/31/06 Complete
>
>

Welding plan and schedule complete 08/31/06 08/31/06 Complete
Changed:
<
<

Modification requests - Requirements & Sponsor Test Sections Complete 3/16/07    
Modification requests - All Sections Complete 3/31/07    
>
>

Modification requests - Requirements & Sponsor Test Sections Complete 3/16/07   Complete
Modification requests - All Sections Complete 3/31/07 5/15/07 Design and testing sections will be complete upon deployment.
Deploy BOS to Socorro and Green Bank 5/15/07    
Changed:
<
<

Fix faulty self test in spectrometer 08/15/06 TBD Not scheduled - waiting for MR to be signed
>
>

Fix faulty self test in spectrometer 08/15/06 TBD Not scheduled

 <<O>>  Difference Topic ProjectGoals (r1.30 - 05 Apr 2007 - JohnFord)
Changed:
<
<

Trajectory Generations and Servo improvements complete 12/31/06 4/30/2007  
>
>

Trajectory Generations and Servo improvements complete 12/31/06 4/30/2007 Only slow-speed tracking improvements

 <<O>>  Difference Topic ProjectGoals (r1.29 - 05 Apr 2007 - AmyShelton)
Changed:
<
<

| First 24 wear and base plates manufactured | 01/31/07 | 03/01/07 | 3/13/07

>
>

First 24 wear and base plates manufactured 01/31/07 03/01/07 3/13/07
Changed:
<
<

Final 10 units complete 12/01/06 03/31/07    
>
>

Final 10 units complete 12/01/06 03/31/07  

 <<O>>  Difference Topic ProjectGoals (r1.28 - 05 Apr 2007 - BrianMason)
Changed:
<
<

Document results from Fall Commissioning 12/31/06 03/31/07  
>
>

Document results from Fall Commissioning 12/31/06 03/31/07 Complete

 <<O>>  Difference Topic ProjectGoals (r1.27 - 05 Apr 2007 - BobAnderson)
Changed:
<
<

Work Plan and Schedule complete 10/01/06 10/10/06 10/10/06
First 24 wear and base plates manufactured 01/31/07 03/01/07  
Next 24 wear and base plates manufactured 03/30/07    
All components on site 03/30/07    
Refurbishment starts 05/01/07    
>
>

Work Plan and Schedule complete 10/01/06 10/10/06 10/10/06
| First 24 wear and base plates manufactured | 01/31/07 | 03/01/07 | 3/13/07
Next 24 wear and base plates manufactured 03/30/07 4/2/07  
All components on site 03/30/07 4/5/07  
Refurbishment starts 05/01/07 4/30/07  

 <<O>>  Difference Topic ProjectGoals (r1.26 - 20 Feb 2007 - RandyMcCullough)
Changed:
<
<

LTA circuit board layout complete 04/01/07    
LTA circuit built 06/01/07    
LTA upgrade complete 10/01/07    
>
>

LTA circuit board layout complete 04/01/07 02/15/07 Complete
LTA circuit built 06/01/07 04/15/07  
LTA upgrade complete 10/01/07 07/15/07  

 <<O>>  Difference Topic ProjectGoals (r1.25 - 15 Feb 2007 - KarenONeil)
Changed:
<
<

43m regular Space craft tracking 05/01/06 On-going  
MLLN tunable receiver up/down-converter installed 08/18/06 11/30/06 Complete
Cooled (70K) Dewar installed 01/30/07      
Improved CITECH system health reporting 02/28/07    
>
>

MLLN tunable receiver installed 08/18/06 11/30/06 Complete
Cooled (70K) Dewar installed 01/30/07 01/07/07 Complete
Improved CITECH system health reporting 02/28/07    
Changed:
<
<

All components on site 03/30/07    
Begin track replacement field work 05/01/07    
Welding plan and schedule complete 08/31/06   Complete
Contractor work/safety plan and schedule complete 10/10/06   Complete
First 24 wear and base plates manufactured 01/31/07    
>
>

Welding plan and schedule complete 08/31/06 /08/31/06 Complete
Contractor work/safety plan and schedule complete 10/01/06 10/01/06 Complete
Work Plan and Schedule complete 10/01/06 10/10/06 10/10/06
First 24 wear and base plates manufactured 01/31/07 03/01/07  
Changed:
<
<

Refurbishment starts 04/30/07    
>
>

All components on site 03/30/07    
Refurbishment starts 05/01/07    
Changed:
<
<

3rd CCB Detector finished 09/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
4th CCB Detector finished 10/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
Project Complete 10/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
>
>

3rd CCB Detector finished 09/01/06 01/12/07 Complete
4th CCB Detector finished 10/01/06 N/A Not to be built
Project Complete 10/01/06 01/26/07 Complete - Completion delayed due to work on spectrometer LTA cards
Changed:
<
<

Documentation of current calibration procedures complete 10/31/06 12/29/06 Complete, still to be circulated
>
>

Documentation of current calibration procedures complete 10/31/06 2/16/06 Complete, still to be circulated
Changed:
<
<

Project complete 02/15/07    
>
>

Project complete 02/15/07 04/15/06  
Changed:
<
<

Chapter 3: Observing Strategies; released for comment 01/12/07    
>
>

Chapter 3: Observing Strategies; released for comment 01/12/07   To be released with Cptr 1
Changed:
<
<

Initial PLC Design Complete 01/15/07    
PLC Programming Complete 02/28/07    
>
>

Initial PLC Design Complete 01/15/07 02/28/07  
PLC Programming Complete 02/28/07 03/30/07  
Changed:
<
<

Qband comissioning complete 10/31/06 12/14/06 Moved to accomodate astronomoical observing; Complete
>
>

Qband comissioning complete 10/31/06 12/14/06 Moved to accomodate astronomical observing; Complete
Changed:
<
<

Subreflector NOD tests 2/15/07   New commissioning exercise
>
>

Subreflector NOD tests 2/15/07 03/01/06 New commissioning exercise
Changed:
<
<

Document results from Fall Commissioning 12/31/06    
>
>

Document results from Fall Commissioning 12/31/06 03/31/07  
Changed:
<
<

Short-term slow-speed tracking improvements complete 09/30/06 1/31/2007 (12/21/2006)  
>
>

Short-term slow-speed tracking improvements complete 09/30/06 3/15/2007  
Changed:
<
<

Final 10 units complete 12/01/06 2/15/07    
New GBT fits format
Project plan complete 08/31/07    
>
>

Final 10 units complete 12/01/06 03/31/07    
Changed:
<
<

Control System upgrade complete 10/01/06 12/29/06  
>
>

Control System upgrade complete 10/01/06 03/31/07  
Changed:
<
<

GBT RFI monitoring Station Complete 09/01/06 1/31/07 (12/20/06) Complete on ground.
>
>

GBT RFI monitoring Station Complete 09/01/06 1/31/07 Complete on ground.

 <<O>>  Difference Topic ProjectGoals (r1.24 - 13 Feb 2007 - AmyShelton)
Changed:
<
<

Next 24 wear and base plates manufactured 04/30/07    
>
>

Next 24 wear and base plates manufactured 03/30/07    
Added:
>
>

Modification requests - Requirements & Sponsor Test Sections Complete 3/16/07    
Modification requests - All Sections Complete 3/31/07    
Changed:
<
<

Trajectory Generations and Servo improvements complete 12/31/06 3/31/2007  
>
>

Trajectory Generations and Servo improvements complete 12/31/06 4/30/2007  

 <<O>>  Difference Topic ProjectGoals (r1.23 - 27 Dec 2006 - JohnFord)
Changed:
<
<

Initial PLC Design Complete 01/15/07    
PLC Programming Complete 02/28/07    
PLC Interface Cards Procured 02/28/07    
Panels wired and tested 04/30/07    
All programming complete 05/31/07    
Main Servo installation begins 06/01/07    
Main Servo complete 06/30/07    
Secondary Servo installation begins 07/01/07    
Secondary Servo installation complete 07/31/07    
Project cleanup 08/01/07    
Project Complete 08/31/07    
>
>

Initial PLC Design Complete 01/15/07    
PLC Programming Complete 02/28/07    
PLC Interface Cards Procured 02/28/07    
Panels wired and tested 04/30/07    
All programming complete 05/31/07    
Main Servo installation begins 06/01/07    
Main Servo complete 06/30/07    
Secondary Servo installation begins 07/01/07    
Secondary Servo installation complete 07/31/07    
Project cleanup 08/01/07    
Project Complete 08/31/07    

 <<O>>  Difference Topic ProjectGoals (r1.22 - 27 Dec 2006 - JohnFord)
Added:
>
>

Initial PLC Design Complete 01/15/07    
PLC Programming Complete 02/28/07    
PLC Interface Cards Procured 02/28/07    
Panels wired and tested 04/30/07    
All programming complete 05/31/07    
Main Servo installation begins 06/01/07    
Main Servo complete 06/30/07    
Secondary Servo installation begins 07/01/07    
Secondary Servo installation complete 07/31/07    
Project cleanup 08/01/07    

 <<O>>  Difference Topic ProjectGoals (r1.21 - 22 Dec 2006 - GlenLangston)
Changed:
<
<

43m (140') MIT Lincoln Labs
Ongoing project, in maintenance phase      
>
>

43m (140') MIT-Lincoln Labs-NRAO (MLLN)
43m regular Space craft tracking 05/01/06 On-going  
MLLN tunable receiver up/down-converter installed 08/18/06 11/30/06 Complete
Cooled (70K) Dewar installed 01/30/07      
Improved CITECH system health reporting 02/28/07    
Deleted:
<
<

140' MLLN tunable receiver installed 08/18/06 11/30/06  

 <<O>>  Difference Topic ProjectGoals (r1.20 - 22 Dec 2006 - RichardPrestage)
Changed:
<
<

3rd CCB Detector finished 09/01/06 12/29/06 Delayed due to work on ALMA and Spectrometer LTA
4th CCB Detector finished 10/01/06 12/29/06 Delayed due to work on ALMA and Spectrometer LTA
Project Complete 10/01/06 12/29/06 Delayed due to work on ALMA and Spectrometer LTA
>
>

3rd CCB Detector finished 09/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
4th CCB Detector finished 10/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
Project Complete 10/01/06 03/31/07 Delayed due to work on ALMA and Spectrometer LTA
Changed:
<
<

Documentation of current calibration procedures complete 10/31/06 12/29/06 Complete
>
>

Documentation of current calibration procedures complete 10/31/06 12/29/06 Complete, still to be circulated
Changed:
<
<

Upgrade Complete 02/15/07   Actual start date depends on the winter Penn Array schedule
Comissioning Complete 03/01/07   Actual start date depends on the winter Penn Array schedule
>
>

Upgrade Complete 02/15/07 07/31/07 Will be performed during summer shutdown
Comissioning Complete 03/01/07 09/30/07 Will be commissioned after summer shutdown
Changed:
<
<

Quadrant Detector samplers graphic screen complete 12/29/06   Complete
Trajectory Generations and Servo improvements complete 12/31/06 3/30/2007  
>
>

Quadrant Detector samplers graphic screen complete 12/29/06 12/29/06 Complete
Trajectory Generations and Servo improvements complete 12/31/06 3/31/2007  
Added:
>
>

The remaining Spectrometer milestones need to be replaced by new ones in light of the change to simply fix the FPGA socket problem

 <<O>>  Difference Topic ProjectGoals (r1.19 - 21 Dec 2006 - AmyShelton)
Changed:
<
<

Project MRs written and reviewed 11/15/06 12/29/2006  
>
>

Project MRs written and reviewed 11/15/06 12/29/2006 Complete
Changed:
<
<

Project charter written 10/01/06 12/29/06 Delayed due to needing feedback from the business offices
>
>

Project charter written 10/01/06 12/29/06 Complete
Changed:
<
<

Subreflector NOD tests 2/15/07   Proposed New Project?
>
>

Subreflector NOD tests 2/15/07   New commissioning exercise
Changed:
<
<

Quadrant Dector manger complete 08/15/06 09/27/06  
Quadrant Detector samplers graphic screen complete 12/29/06    
Trajectory Generations and Servo improvements complete 12/31/06    
Short-term slow-speed tracking improvements complete 09/30/06 12/31/06  
>
>

Quadrant Dector manager complete 08/15/06 09/27/06 Complete
Quadrant Detector samplers graphic screen complete 12/29/06   Complete
Trajectory Generations and Servo improvements complete 12/31/06 3/30/2007  
Short-term slow-speed tracking improvements complete 09/30/06 1/31/2007 (12/21/2006)  
Changed:
<
<

Cross correlation MRs complete 11/15/06 12/29/06  
>
>

Cross correlation MRs complete 11/15/06 2/15/07 (12/21/06)  
Changed:
<
<

Comissioning tests complete 12/01/06    
>
>

Comissioning tests complete 12/01/06 12/01/06 Complete
Changed:
<
<

GBT RFI monitoring Station Complete 09/01/06 12/31/06  
>
>

GBT RFI monitoring Station Complete 09/01/06 1/31/07 (12/20/06) Complete on ground.
Changed:
<
<

Automatic Updating of zernike Coefficients 10/06/06 09/29/06 Complete
>
>

Automatic Updating of Zernike Coefficients 10/06/06 09/29/06 Complete
Changed:
<
<

Repair astrid "hang-ups" problem 11/15/06 12/1/06  
Turtle/GFM communication upgrade 11/15/06 12/1/06  
>
>

Repair astrid "hang-ups" problem 11/15/06 12/31/06 (12/20/06)  
Turtle/GFM communication upgrade 11/15/06 12/31/06 (12/20/06)  

 <<O>>  Difference Topic ProjectGoals (r1.18 - 21 Dec 2006 - RonMaddalena)
Changed:
<
<

Documentation of current calibration procedures complete 10/31/06 12/29/06  
>
>

Documentation of current calibration procedures complete 10/31/06 12/29/06 Complete
Changed:
<
<

Chapter 2: Intro to SBs and Observing Scripts; released for comment 12/8/06    
GBTIDL User's Guide Complete 12/21/06    
>
>

Chapter 2: Intro to SBs and Observing Scripts; released for comment 12/8/06 12/18/06 Complete
GBTIDL User's Guide Complete 12/21/06 12/22/06 Complete
Changed:
<
<

Qband comissioning complete 10/31/06 12/14/06 Moved to accomodate astronomoical observing
>
>

Qband comissioning complete 10/31/06 12/14/06 Moved to accomodate astronomoical observing; Complete
Changed:
<
<

Ka comissioning complete 11/31/06 12/14/06 Moved to accomodate astronomoical observing & Qband commisioning
>
>

Ka comissioning complete 11/31/06 12/14/06 Moved to accomodate astronomoical observing & Qband commisioning; Complete
Subreflector NOD tests 2/15/07   Proposed New Project?
Changed:
<
<

10 units complete 09/01/06 11/15/06  
Final 10 units complete 12/01/06 12/31/06    
>
>

10 units complete 09/01/06 11/15/06 Complete
Final 10 units complete 12/01/06 2/15/07