Currently the Ka Receiver and the Zpectrometer are on the GBT and undergoing Commissioning exercises.

Changed:
<
<

Currently work is being done on two fronts - the Ka receiver is being worked on to improve is correlation architecture, and a number of different pieces of the Zpectrometer software are being worked on.

>
>

During summer 2007 work was being done on two fronts - the Ka receiver was worked on to improve is correlation architecture, and a number of different pieces of the Zpectrometer software were worked on.


 <<O>>  Difference Topic ZpectProject (r1.50 - 01 Jun 2007 - KarenONeil)
Added:
>
>

Status

Currently work is being done on two fronts - the Ka receiver is being worked on to improve is correlation architecture, and a number of different pieces of the Zpectrometer software are being worked on.

Work on the Ka receiver is captured on the Ka receiver page.

Work on the software issues is captured in the Plans for 2007

Deleted:
<
<

(see also ZpectProjectSched for project deadlines)

Changed:
<
<

Plan for 2007

>
>

Detailed plans

  • Plans for 2007
  • Original Project Schedule
  • Original schedule of GB tasks:
    • 10 Feb 2006 : Determine placement of Zpectrometer machine (R. Norrod - 2005 Oct, Nov) [ DONE ]
    • 17 Apr, 2006 : Fit Dummy zpectrometer to turret for tests (Egan/Cromer) [ DONE ]
    • 31 May, 2006 : Microcode & controller deliveredd to GBT software group
    • 01 Jun, 2006 : Ship Zpectrometer rack to UMd (Egan/Cromer - 2006 April - May)
    • 15 August, 2006 : Ka receiver software manger changes (Creager/A. Shelton - 2006 May - Aug)
    • 15 August, 2006 : GBT software control manager built (Creager/A. Shelton - 2006 May - Aug)
    • 15 August, 2006 : SDFITS keyword/GBTIDL index changes made to accomodate zpectrometer data
    • 15 August, 2006 : Ka-band receiver modifications complete (G. Watts - 2006 Jun - Aug)
    • 14-18 August, 2006 : Zpectrometer in GB for RFI and software testing. (Will be hooked up to KA receiver iff possible)
    • 5-8 September, 2006 : Zpectrometer/Ka Lab tests
    • 1 October, 2006 : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD - 2006 May - Oct)
    • 09 Oct, 2006 : Install Ka Receiver
    • 16 Oct, 2006 : Install Zpectrometer
    • 31 Nov, 2006 : 10-20 hours of Zpectromter Functional tests (2006 17 Oct - 17 Nov)
Changed:
<
<

Zpectrometer Meetings

>
>

Zpectrometer Meeting Minutes

Added:
>
>

Changed:
<
<

GBT Resource schedule and requests

Schedule of GB tasks:

  • 10 Feb 2006 : Determine placement of Zpectrometer machine (R. Norrod - 2005 Oct, Nov) [ DONE ]
  • 17 Apr, 2006 : Fit Dummy zpectrometer to turret for tests (Egan/Cromer) [ DONE ]
  • 31 May, 2006 : Microcode & controller deliveredd to GBT software group
  • 01 Jun, 2006 : Ship Zpectrometer rack to UMd (Egan/Cromer - 2006 April - May)
  • 15 August, 2006 : Ka receiver software manger changes (Creager/A. Shelton - 2006 May - Aug)
  • 15 August, 2006 : GBT software control manager built (Creager/A. Shelton - 2006 May - Aug)
  • 15 August, 2006 : SDFITS keyword/GBTIDL index changes made to accomodate zpectrometer data
  • 15 August, 2006 : Ka-band receiver modifications complete (G. Watts - 2006 Jun - Aug)
  • 14-18 August, 2006 : Zpectrometer in GB for RFI and software testing. (Will be hooked up to KA receiver iff possible)
  • 5-8 September, 2006 : Zpectrometer/Ka Lab tests
  • 1 October, 2006 : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD - 2006 May - Oct)
  • 09 Oct, 2006 : Install Ka Receiver
  • 16 Oct, 2006 : Install Zpectrometer
  • 31 Nov, 2006 : 10-20 hours of Zpectromter Functional tests (2006 17 Oct - 17 Nov)
  • 2006/7 Nov - Feb : Data analysis software written (A. Baker/Radziwill)
  • 2007 Feb - May : Science validation (should be through referee approved proposal)
  • 2007 Oct 01 : Limited call for outside observers (for Feb 1 observing season)

GBT Resource Requests for Cycle 2 (Q1 2006) (February 15 - March 31, 2006)

Budget Responsibilities

>
>

Budget Responsibilities

Changed:
<
<

Zpectrometer Rack

Documents:

>
>

Documents:

Added:
>
>

Changed:
<
<

Links:

>
>

Links

Deleted:
<
<

Deleted:
<
<

-- KarenONeil - 12 Aug 2005


 <<O>>  Difference Topic ZpectProject (r1.49 - 11 Dec 2006 - KarenONeil)
Changed:
<
<

>
>

  • GB Project Team: KarenONeil, AmyShelton, Galen Watts, Roger Norrod, Ray Creager, Bob Garwood, Paul Marganian
Added:
>
>

Plan for 2007


 <<O>>  Difference Topic ZpectProject (r1.48 - 11 Dec 2006 - GalenWatts)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.47 - 28 Sep 2006 - PaulMarganian)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.46 - 02 Aug 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.45 - 18 Jul 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.44 - 13 Jul 2006 - RogerNorrod)
Deleted:
<
<

Deleted:
<
<

Deleted:
<
<


 <<O>>  Difference Topic ZpectProject (r1.43 - 13 Jul 2006 - RogerNorrod)
Added:
>
>

Zpectrometer Rack


 <<O>>  Difference Topic ZpectProject (r1.42 - 12 Jul 2006 - KarenONeil)
Added:
>
>

Deleted:
<
<

Added:
>
>

%META:FILEATTACHMENT{name="100_1071.JPG" attr="h" comment="Zpectrometer crate - Photo 1" date="1152729756" path="100_1071.JPG" size="459912" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="100_1072.JPG" attr="h" comment="Zpectrometer crate - Photo 2" date="1152729800" path="100_1072.JPG" size="408926" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="100_1073.JPG" attr="h" comment="Zpectrometer crate - Photo 3" date="1152729818" path="100_1073.JPG" size="422126" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="100_1074.JPG" attr="h" comment="Zpectrometer crate - Photo 4" date="1152729836" path="100_1074.JPG" size="425142" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.41 - 06 Jul 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.40 - 21 Jun 2006 - KarenONeil)
Added:
>
>

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="zpectrometer-idl-2006.06.13.pdf" attr="h" comment="IDL routines expected to needed" date="1150884503" path="zpectrometer-idl-2006.06.13.pdf" size="48795" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.39 - 12 Jun 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.38 - 17 May 2006 - KarenONeil)
Added:
>
>

Added:
>
>

Changed:
<
<

%META:FILEATTACHMENT{name="26t40BlockDiagZpec-Model.jpg" attr="" comment="Ka RX Block Diagram" date="1147798612" path="26t40BlockDiagZpec-Model.jpg" size="226478" user="GalenWatts" version="1.1"}%

>
>

%META:FILEATTACHMENT{name="26t40BlockDiagZpec-Model.jpg" attr="h" comment="Ka RX Block Diagram" date="1147798612" path="26t40BlockDiagZpec-Model.jpg" size="226478" user="GalenWatts" version="1.1"}% %META:FILEATTACHMENT{name="zpec-data-2006.05.14.pdf" attr="h" comment="First draft of data/calibraiton memo (A. Baker)" date="1147874438" path="zpec-data-2006.05.14.pdf" size="146242" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.37 - 16 May 2006 - GalenWatts)
Changed:
<
<

>
>

Added:
>
>

%META:FILEATTACHMENT{name="26t40BlockDiagZpec-Model.jpg" attr="" comment="Ka RX Block Diagram" date="1147798612" path="26t40BlockDiagZpec-Model.jpg" size="226478" user="GalenWatts" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.36 - 16 May 2006 - GalenWatts)
Changed:
<
<

>
>

Added:
>
>

Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.35 - 16 May 2006 - KarenONeil)
Changed:
<
<

>
>

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="intermed-levdataacqint.pdf" attr="h" comment="intermediate level data acquisition interface" date="1147786517" path="intermed-lev data acq int.pdf" size="37000" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.34 - 25 Apr 2006 - KarenONeil)
Changed:
<
<

>
>

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="zpectrometer-earlyobs-2006.04.24.pdf" attr="h" comment="memo on early observations with Zpectrometer" date="1145999461" path="zpectrometer-earlyobs-2006.04.24.pdf" size="24791" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.33 - 24 Apr 2006 - KarenONeil)
Added:
>
>

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="zpectrometer-earlyobs-2006.04.14.pdf" attr="h" comment="memo on early observations with Zpectrometer" date="1145870100" path="zpectrometer-earlyobs-2006.04.14.pdf" size="24843" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.32 - 14 Apr 2006 - KarenONeil)
Changed:
<
<

  • 17 Apr, 2006 : Fit Dummy zpectrometer to turret for tests (Egan/Cromer)
>
>

  • 17 Apr, 2006 : Fit Dummy zpectrometer to turret for tests (Egan/Cromer) [ DONE ]
Changed:
<
<

  • 1 October, 2006 : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD - 2006 May - Oct)
  • 15 August : Ka-band receiver modifications complete (G. Watts - 2006 Jun - Aug)
>
>

  • 15 August, 2006 : SDFITS keyword/GBTIDL index changes made to accomodate zpectrometer data
  • 15 August, 2006 : Ka-band receiver modifications complete (G. Watts - 2006 Jun - Aug)
Added:
>
>

  • 1 October, 2006 : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD - 2006 May - Oct)

 <<O>>  Difference Topic ZpectProject (r1.31 - 13 Apr 2006 - DennisEgan)
Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="zpectmockup1.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951823" path="zpect mockup 1.jpg" size="199175" user="DennisEgan" version="1.1"}% %META:FILEATTACHMENT{name="zpectmockup2.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951846" path="zpect mockup 2.jpg" size="201122" user="DennisEgan" version="1.1"}% %META:FILEATTACHMENT{name="zpectmockup3.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951686" path="zpect mockup 3.jpg" size="179278" user="DennisEgan" version="1.1"}% %META:FILEATTACHMENT{name="zpectmockup4.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951702" path="zpect mockup 4.jpg" size="176581" user="DennisEgan" version="1.1"}% %META:FILEATTACHMENT{name="zpectmockup5.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951723" path="zpect mockup 5.jpg" size="188823" user="DennisEgan" version="1.1"}% %META:FILEATTACHMENT{name="zpectmockup6.jpg" attr="h" comment="zpectrometer mockup feed room test fit" date="1144951741" path="zpect mockup 6.jpg" size="216573" user="DennisEgan" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.30 - 10 Apr 2006 - KarenONeil)
Added:
>
>

  • Zpectrometer Face-to-face meeting 4 (15 May, 2006) - ZpectMeeting4
Changed:
<
<

  • 2005 Oct, Nov: Determine placement of Zpectrometer machine (R. Norrod)
  • 2006 May - Aug : Ka receiver software manger changes (Creager/A. Shelton)
  • 2006 May - Oct : GBT software control manager built (Creager/A. Shelton)
  • 2006 May - Oct : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD)
  • 2006 Jun - Aug : Ka-band receiver modifications complete (sooner if possible) (G. Watts)
  • 2006 Late Sept/Early Oct : Place Zpectrometer on GBT (Norrod)
  • 2006 Oct - Dec : 10-20 hours of functional test on GBT (Harris/Norrod/O'Neil)
>
>

  • 10 Feb 2006 : Determine placement of Zpectrometer machine (R. Norrod - 2005 Oct, Nov) [*DONE*]
  • 17 Apr, 2006 : Fit Dummy zpectrometer to turret for tests (Egan/Cromer)
  • 31 May, 2006 : Microcode & controller deliveredd to GBT software group
  • 01 Jun, 2006 : Ship Zpectrometer rack to UMd (Egan/Cromer - 2006 April - May)
  • 15 August, 2006 : Ka receiver software manger changes (Creager/A. Shelton - 2006 May - Aug)
  • 15 August, 2006 : GBT software control manager built (Creager/A. Shelton - 2006 May - Aug)
  • 1 October, 2006 : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD - 2006 May - Oct)
  • 15 August : Ka-band receiver modifications complete (G. Watts - 2006 Jun - Aug)
  • 14-18 August, 2006 : Zpectrometer in GB for RFI and software testing. (Will be hooked up to KA receiver iff possible)
  • 5-8 September, 2006 : Zpectrometer/Ka Lab tests
  • 09 Oct, 2006 : Install Ka Receiver
  • 16 Oct, 2006 : Install Zpectrometer
  • 31 Nov, 2006 : 10-20 hours of Zpectromter Functional tests (2006 17 Oct - 17 Nov)

 <<O>>  Difference Topic ZpectProject (r1.29 - 07 Apr 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.28 - 06 Apr 2006 - KarenONeil)
Changed:
<
<

  • Zpectrometer Face-to-face meeting 2 (4 Feb, 2005) - ZpectMeeting2
>
>

  • Zpectrometer Face-to-face meeting 2 (4 Feb, 2006) - ZpectMeeting2
  • Zpectrometer Face-to-face meeting 3 (10 Apr, 2006) - ZpectMeeting3

 <<O>>  Difference Topic ZpectProject (r1.27 - 14 Feb 2006 - AmyShelton)
Changed:
<
<

Zpectrometer

>
>

Zpectrometer

Changed:
<
<

>
>


 <<O>>  Difference Topic ZpectProject (r1.26 - 09 Feb 2006 - KarenONeil)
Changed:
<
<

GBT Resource Requests for Cycle 1 (Q1 2006) (January 1 - Febuary 14, 2006)

>
>

GBT Resource Requests for Cycle 2 (Q1 2006) (February 15 - March 31, 2006)

Changed:
<
<

>
>


 <<O>>  Difference Topic ZpectProject (r1.25 - 31 Jan 2006 - KarenONeil)
Changed:
<
<

Links:

>
>

Documents:

Deleted:
<
<

Added:
>
>

  • http://www.astro.umd.edu/~harris/docs/freq_setup.pdf : describes how to assign values to the FITS keywords to provide the right velocity scales for CLASS FITS files, given the data available from the Caltech Submillimeter Observatory's telecope computer. We would need to modify this for the GBT, but at least it's a start.

  • http://www.astro.umd.edu/~mpound/wasp/dict.html : dictionary of the SDFITS keywords we use. Marc Pound generates these with a script that writes this html file as well as template header files and so on, which makes it easy to update and modify the list.

  • http://www.astro.umd.edu/~harris/microc_223.ps : The command language, options, and engineering tools, along with timing calculations for the spectrometer's internal micros. This will change in detail when we switch to new micros, but gives a flavor of that interface.

Links:

Added:
>
>

Added:
>
>

%META:FILEATTACHMENT{name="user_instrument_policy.doc" attr="h" comment="NRAO User Instrument Policy" date="1138746426" path="user_instrument_policy.doc" size="41984" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="phaseswitch.pdf" attr="h" comment="Pahse Switch information" date="1138747281" path="phaseswitch.pdf" size="35302" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="max353.pdf" attr="h" comment="Maxim analog switches" date="1138747323" path="max353.pdf" size="103476" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="hmc136.pdf" attr="h" comment="HMC 136 biphase modulator" date="1138747366" path="hmc136.pdf" size="134282" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="Zpect_interfaces_r1.pdf" attr="h" comment="First draft of zpectrometer interfaces doc" date="1138747408" path="Zpect_interfaces_r1.pdf" size="207741" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="zspecFinalcopy.doc" attr="h" comment="zpectrometer placment doc (from GBT)" date="1138747441" path="zspecFinalcopy.doc" size="689664" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.24 - 26 Jan 2006 - KarenONeil)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.23 - 18 Jan 2006 - KarenONeil)
Changed:
<
<

Zpectrometer Kick-off Meeting (14 October, 2005)

>
>

Zpectrometer Meetings


 <<O>>  Difference Topic ZpectProject (r1.22 - 04 Jan 2006 - NicoleRadziwill)
Changed:
<
<

  • 2006 May - Aug : Ka receiver software manger changes (A. Shelton)
  • 2006 May - Oct : GBT software control manager built (A. Shelton)
  • 2006 May - Oct : GBT config requirements, modifications, and scheduling blocks designed and built (A. Shelton)
>
>

  • 2006 May - Aug : Ka receiver software manger changes (Creager/A. Shelton)
  • 2006 May - Oct : GBT software control manager built (Creager/A. Shelton)
  • 2006 May - Oct : GBT config requirements, modifications, and scheduling blocks designed and built (SDD TBD)
Changed:
<
<

  • 2006/7 Nov - Feb : Data analysis software written (A. Baker/Shelton)
>
>

  • 2006/7 Nov - Feb : Data analysis software written (A. Baker/Radziwill)

 <<O>>  Difference Topic ZpectProject (r1.21 - 16 Dec 2005 - KarenONeil)
Changed:
<
<

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)

>
>

GBT Resource Requests for Cycle 1 (Q1 2006) (January 1 - Febuary 14, 2006)

Changed:
<
<

>
>

  • Electronics Division Request:
    • Jason Ray (5%); Roger Norrod (10%); One engineer for 2-3 weeks in January for work on the Zpectrometer placement problem
  • Mechanical Division Request?:
Changed:
<
<

>
>

Changed:
<
<

  • Antenna Access Request?:
>
>

  • Antenna Access Request?:
Changed:
<
<

  • Commissioning Time Request?:
>
>

  • Commissioning Time Request?:
Changed:
<
<

  • Additional Request Info?:
>
>

  • Additional Request Info?:

 <<O>>  Difference Topic ZpectProject (r1.20 - 03 Nov 2005 - KarenONeil)
Changed:
<
<

  • Electronics Division Request:
    • Jason Ray (5%); Galen Watts (0.5 dat), John Ford (0.5 day), Roger Norrod (5%); Mike Stennes (0.5 day)
  • Mechanical Division Request?:
>
>

Changed:
<
<

>
>

Changed:
<
<

  • Antenna Access Request?:
>
>

  • Antenna Access Request?:
Changed:
<
<

  • Commissioning Time Request?:
>
>

  • Commissioning Time Request?:
Changed:
<
<

  • Additional Request Info?:
>
>

  • Additional Request Info?:

 <<O>>  Difference Topic ZpectProject (r1.19 - 19 Oct 2005 - RogerNorrod)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.18 - 18 Oct 2005 - KarenONeil)
Added:
>
>

Current UMd Software documentation (Oct 17, 2005)

  • http://www.astro.umd.edu/~harris/docs/waspmath.pdf is a memo that explains the signal processing for the WASP spectrometers in autocorrelation mode. No major differences for cross-correlation mode, results for which are summarized in http://www.astro.umd.edu/~harris/kaband/rsi05.pdf. These document the algorithms that produce amplitude calibrated spectra. Another document of less direct interest is http://www.astro.umd.edu/~harris/docs/freq_setup.pdf, which describes how to assign values to the FITS keywords to provide the right velocity scales for CLASS FITS files, given the data available from the Caltech Submillimeter Observatory's telecope computer. We would need to modify this for the GBT, but at least it's a start.
  • http://www.astro.umd.edu/~mpound/wasp/dict.html is a dictionary of the SDFITS keywords we use. Marc Pound generates these with a script that writes this html file as well as template header files and so on, which makes it easy to update and modify the list. He would be happy to share it -- he's mpound "at" astro.umd.edu. (There are a few unusual items here: for instance the telescope's altitude, latitude, longitude, heading and speed are dynamic variables since we also support observations from NASA's SOFIA airborne observatory...)
  • The command language, options, and engineering tools, along with timing calculations for the spectrometer's internal micros is covered in http://www.astro.umd.edu/~harris/microc_223.ps. This will change in detail when we switch to new micros, but gives a flavor of that interface.

 <<O>>  Difference Topic ZpectProject (r1.17 - 17 Oct 2005 - KarenONeil)
Added:
>
>

(see also ZpectProjectSched for project deadlines)

Deleted:
<
<

Zpectrometer Kick-off Meeting (14 October, 2005)

Changed:
<
<

Attendees:

Karen O'Neil (GB), Amy Shelton (GB), Rich Lacasse (GB), Jason Ray (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd), Chris Carelli (Telecon), Ron Maddelena (GB)
>
>

Zpectrometer Kick-off Meeting (14 October, 2005)

Changed:
<
<

Preliminary Agenda - GB 137, Begins at 9am (General discussion where no speaker is named)

  • Zpectrometer Project Overview & Work Breakdown (Harris, UMd)(begin at 9am)
  • Hardware details (Intro by Norrod, GB, & General discussion)
    • Interface to GBT IF (signal taps, power levels, external phase switch)
    • LO frequencies (how to run at 44.25 GHz)
    • Physical placement of zpectrometer
    • RFI considerations
    • Internal phase calibration (Harris, UMd)
  • Fabrication & Testing Timeline
    • Overview of fabrication and test plans (Harris, UMd)
    • Lab tests in Md & preliminary GB tests
    • Lab tests in GB
  • Break (approximately 10:30am)
  • Software Details
    • Data acquisition software
      • Preliminary work and testing prototype (Rauch, UMd)
      • Full GBT integration
    • Data reduction software, data file format (Rauch, Zonak)
    • Amplitude calibration techniques (If time)
  • Budget (what NRAO needs to supply)
  • Maximizing the science output
    • How to get early science
    • When to open up use for general public
  • Schedule revision and task assignments
  • Lunch (approximately 12:30)
  • After lunch will be any follow-up meetings
  • "How Correlation Receivers Work" talk at 3pm
>
>

GBT Resource schedule and requests

Schedule of GB tasks:

  • 2005 Oct, Nov: Determine placement of Zpectrometer machine (R. Norrod)
  • 2006 May - Aug : Ka receiver software manger changes (A. Shelton)
  • 2006 May - Oct : GBT software control manager built (A. Shelton)
  • 2006 May - Oct : GBT config requirements, modifications, and scheduling blocks designed and built (A. Shelton)
  • 2006 Jun - Aug : Ka-band receiver modifications complete (sooner if possible) (G. Watts)
  • 2006 Late Sept/Early Oct : Place Zpectrometer on GBT (Norrod)
  • 2006 Oct - Dec : 10-20 hours of functional test on GBT (Harris/Norrod/O'Neil)
  • 2006/7 Nov - Feb : Data analysis software written (A. Baker/Shelton)
  • 2007 Feb - May : Science validation (should be through referee approved proposal)
  • 2007 Oct 01 : Limited call for outside observers (for Feb 1 observing season)
Changed:
<
<

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)

>
>

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)

Changed:
<
<

Links:

>
>

Budget Responsibilities

  • GBT: Receiver modifications, rack, installation, travel for NRAO people
  • UMd: Everything including RFI sheilded chasis, short cables (within one room), downconverter, power supplies, communications, phase cal system, travel for all UMd folks
  • If the decision is made to place the zpectrometer in the Jy lab and not in the turret house, GB would be responsible for the cost of the fiber cables. Hoewever, UMd will provide all monies available due to the much cheaper chasis, etc (which may even be built by GB in this case) which would be needed, to help defray the cable costs.

Links:


 <<O>>  Difference Topic ZpectProject (r1.16 - 11 Oct 2005 - KarenONeil)

 <<O>>  Difference Topic ZpectProject (r1.15 - 10 Oct 2005 - JohnFord)
Changed:
<
<

>
>

Changed:
<
<

Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd), Chris Carelli (Telecon), Ron Maddelena (GB)

>
>

Karen O'Neil (GB), Amy Shelton (GB), Rich Lacasse (GB), Jason Ray (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd), Chris Carelli (Telecon), Ron Maddelena (GB)

Changed:
<
<

    • Holly Chen (5%); Galen Watts (0.5 dat), John Ford (0.5 day), Roger Norrod (5%); Mike Stennes (0.5 day)
>
>

    • Jason Ray (5%); Galen Watts (0.5 dat), John Ford (0.5 day), Roger Norrod (5%); Mike Stennes (0.5 day)

 <<O>>  Difference Topic ZpectProject (r1.14 - 10 Oct 2005 - KarenONeil)
Changed:
<
<

Attendees (hopefully):

Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)
>
>

Attendees:

Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd), Chris Carelli (Telecon), Ron Maddelena (GB)
Changed:
<
<

Preliminary Agenda - GB 137

  • Zpectrometer overview (begin at 9am)
    • Project Overview - what the Zpectrometer is
    • Work breakdown - what Maryland and GBT have agreed to supply
  • Hardware details
    • Physical placement of zpectrometer
>
>

Preliminary Agenda - GB 137, Begins at 9am (General discussion where no speaker is named)

  • Zpectrometer Project Overview & Work Breakdown (Harris, UMd)(begin at 9am)
  • Hardware details (Intro by Norrod, GB, & General discussion)
Changed:
<
<

    • Internal phase calibration
>
>

    • LO frequencies (how to run at 44.25 GHz)
    • Physical placement of zpectrometer
Added:
>
>

    • Internal phase calibration (Harris, UMd)
Changed:
<
<

    • Fabrication in Md
    • Lab tests in Md & preliminary GB tests(?)
>
>

    • Overview of fabrication and test plans (Harris, UMd)
    • Lab tests in Md & preliminary GB tests
Changed:
<
<

      • Preliminary work and testing prototype
>
>

      • Preliminary work and testing prototype (Rauch, UMd)
Changed:
<
<

    • Data reduction software, data file format
    • Amplitude calibration techniques
>
>

    • Data reduction software, data file format (Rauch, Zonak)
    • Amplitude calibration techniques (If time)
Changed:
<
<

  • Lunch
>
>

  • Lunch (approximately 12:30)
Added:
>
>


 <<O>>  Difference Topic ZpectProject (r1.13 - 22 Sep 2005 - KarenONeil)

 <<O>>  Difference Topic ZpectProject (r1.12 - 22 Sep 2005 - PaulMarganian)
Changed:
<
<

  • "How Correlation Receivers Work" talk at 3pm
>
>


 <<O>>  Difference Topic ZpectProject (r1.11 - 21 Sep 2005 - KarenONeil)
Changed:
<
<

>
>

  • "How Correlation Receivers Work" talk at 3pm

 <<O>>  Difference Topic ZpectProject (r1.10 - 19 Sep 2005 - KarenONeil)
Changed:
<
<

    • Overall project
    • Schedule
  • Hardware Details
    • Interface to GBT IF (signal taps)
>
>

    • Project Overview - what the Zpectrometer is
    • Work breakdown - what Maryland and GBT have agreed to supply
  • Hardware details
Changed:
<
<

    • RFI considerations and tests
>
>

    • Interface to GBT IF (signal taps, power levels, external phase switch)
    • Internal phase calibration
    • RFI considerations
  • Fabrication & Testing Timeline
    • Fabrication in Md
    • Lab tests in Md & preliminary GB tests(?)
    • Lab tests in GB
Changed:
<
<

    • Software interface plan
    • Data reduction path
    • Calibration details
>
>

    • Data acquisition software
      • Preliminary work and testing prototype
      • Full GBT integration
    • Data reduction software, data file format
    • Amplitude calibration techniques
Added:
>
>

  • Maximizing the science output
    • How to get early science
    • When to open up use for general public

 <<O>>  Difference Topic ZpectProject (r1.9 - 14 Sep 2005 - KarenONeil)
Added:
>
>


TOC: No TOC in "Projects.ZpectProject"
Changed:
<
<

Zpectrometer Kick-off Meeting (14 October, 2005)

>
>

Zpectrometer Kick-off Meeting (14 October, 2005)

Attendees (hopefully):

Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)
Changed:
<
<

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)
>
>

Preliminary Agenda - GB 137

  • Zpectrometer overview (begin at 9am)
    • Overall project
    • Schedule
  • Hardware Details
    • Interface to GBT IF (signal taps)
    • Physical placement of zpectrometer
    • RFI considerations and tests
  • Break (approximately 10:30am)
  • Software Details
    • Software interface plan
    • Data reduction path
    • Calibration details
  • Budget (what NRAO needs to supply)
  • Schedule revision and task assignments
  • Lunch
  • After lunch will be any follow-up meetings
Changed:
<
<

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)

>
>

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)

Changed:
<
<

    • Holly Chen (5%); Galen Watts (5%), John Ford (0.5 day), Roger Norrod (5%); Mike Stennes (5%)
>
>

    • Holly Chen (5%); Galen Watts (0.5 dat), John Ford (0.5 day), Roger Norrod (5%); Mike Stennes (0.5 day)
Changed:
<
<

Links:

>
>

Links:


 <<O>>  Difference Topic ZpectProject (r1.8 - 14 Sep 2005 - KarenONeil)
Added:
>
>

GBT Resource Requests for Cycle 7 (Q4 2005) (October 1 - Novermber 16, 2005)


 <<O>>  Difference Topic ZpectProject (r1.7 - 17 Aug 2005 - KarenONeil)
Changed:
<
<

>
>

  • Project Scientist: Andy Harris (UMd)
Changed:
<
<

Zpectrometer Kick-off Meeting (Fall, 2005)

>
>

Zpectrometer Kick-off Meeting (14 October, 2005)

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), John Ford (GB), Richard Prestage (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)

Links:

Deleted:
<
<

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)
Changed:
<
<

%META:FILEATTACHMENT{name="zpectrometer_prop.pdf" attr="" comment="Zpectrometer Proposal" date="1123862795" path="zpectrometer_prop.pdf" size="367165" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="zpect_fab2.mpp" attr="" comment="Project Plan for Zpectrometer (12 August, 2005)" date="1123862828" path="zpect_fab2.mpp" size="169472" user="KarenONeil" version="1.1"}%

>
>

%META:FILEATTACHMENT{name="zpectrometer_prop.pdf" attr="h" comment="Zpectrometer Proposal" date="1123862795" path="zpectrometer_prop.pdf" size="367165" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="zpect_fab2.mpp" attr="h" comment="Project Plan for Zpectrometer (12 August, 2005)" date="1123862828" path="zpect_fab2.mpp" size="169472" user="KarenONeil" version="1.1"}%


 <<O>>  Difference Topic ZpectProject (r1.6 - 15 Aug 2005 - KarenONeil)
Changed:
<
<

>
>


 <<O>>  Difference Topic ZpectProject (r1.5 - 12 Aug 2005 - RichardPrestage)
Changed:
<
<

from a schedule o the critical path. Connect

>
>

from a schedule off the critical path. Connect


 <<O>>  Difference Topic ZpectProject (r1.4 - 12 Aug 2005 - KarenONeil)
Changed:
<
<

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), Roger Norrod (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)
>
>

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), Roger Norrod (GB), Mike Stennes (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)

 <<O>>  Difference Topic ZpectProject (r1.3 - 12 Aug 2005 - RichardPrestage)
Changed:
<
<

Zpectrometer's wide bandwidth bypasses this selection e ect and enables it to detect new classes of sources. In addition to nding precise redshifts, its spectra with velocity resolution

>
>

Zpectrometer's wide bandwidth bypasses this selection effect and enables it to detect new classes of sources. In addition to finding precise redshifts, its spectra with velocity resolution


 <<O>>  Difference Topic ZpectProject (r1.2 - 12 Aug 2005 - KarenONeil)
Changed:
<
<

>
>


 <<O>>  Difference Topic ZpectProject (r1.1 - 12 Aug 2005 - KarenONeil)
Added:
>
>

%META:TOPICINFO{author="KarenONeil" date="1123862940" format="1.0" version="1.1"}%

Zpectrometer


Strategic Value

We will construct the Zpectrometer, an ultra-wideband radio spectrometer for the Green Bank Telescope (GBT). Observations with this instrument are key to understanding the star formation, metal production, and structure formation histories of the Universe. The Zpectrometer covers the full 14 GHz-wide Ka-band with a set of analog lag correlation spectrometers in a multi-channel correlation radiometer architecture. The zpectrometer's bandwidth and stability, combined with the GBT's collecting area, enable sensitive and efficient spectral searches for molecules in high redshift galaxies. The instrument is optimized for observations of low-excitation spectral lines from the carbon monoxide (CO) molecule at redshifts of 1.88 < z < 3.43 and 4.76 < z < 7.87. This range of redshifts is of intense current interest because it may correspond to the era when most of the stars in the Universe formed and galaxies assembled.

All high-redshift radio molecular detections to date have started from optical redshifts. Zpectrometer's wide bandwidth bypasses this selection e ect and enables it to detect new classes of sources. In addition to nding precise redshifts, its spectra with velocity resolution of approximately 150 km s-1 probe kinematical signs of interaction and derive dynamical mass estimates. Both cold and warm gas emit low-J lines, and these observations are critical constraints on radiative transfer models of physical conditions

Personnel

  • GB Project Manager: KarenONeil
  • GB Project Engineer: AmyShelton
  • GB Project Scientist: KarenONeil
  • GB Project Team: KarenONeil, AmyShelton, Holy Chen, other TBD at kickoof meeting
  • UMd Project Team: Andy Harris (PI), Andrew Baker, Stephanie Zonak, Kevin Rauch

Scope and Overall Work Plan

This project has three main areas of responsibility, and each proposer will take lead responsibility for one: Harris (UMd) for spectrometer package fabrication and test, Baker (UMd) for data analysis software, and the GBT project group for interfaces with the GBT.

Fabricating the WASP2 correlators is largely a replication effort, and we will continue our collaboration with the University of Maryland's Physics department's Electronic Development Group and Mechanical Shop. The professional shops again will be responsible for the bulk of the fabrication. Harris' group will be responsible for microwave module fabrication and overall testing. The four-channel downconverter is a good project for a budding instrumentalist and will be a UMD student project with Harris' supervision. The UMD instrument team will also take responsibility for modifying the instrument software for the specific calibration cycles and header information at the GBT.

Baker will lead the data analysis software effort with the assistance of a UMD student. Baker, who will spend about a quarter of his time on this project, is supported as an external NRAO Jansky Fellow at the University of Maryland and receives no support from this grant.

The project team (described above and incorporating the UMd team) will ensure that the physical, electronic, and software interfaces match on the GBT and Zpectrometer. NRAO Green Bank will be responsible for the physical accommodation, including machine shop work and material for mounting, and will modify the Kaband front-end for the spectrometer. NRAO will not receive any funds from this proposal; scientist, engineer, and mechanic time will come from its operating budget.

The project timeline is an 18-month fabrication period followed by a number of test observing runs. The timeline is driven in part by an estimate of a reasonable funding profile [which was granted], but the current plan will have the zpectrometer on the telescope without delay in the winter 2006/2007 observing season. (Atmospheric water vapor is low in the winter, the best season for Ka-band observations.) A limited amount of engineering time will be available, but the bulk of the observing time will come from proposals to the normal GBT Proposal Selection Committee.

In detail, the project timeline is:

Year 1: Start all long-lead correlator items, principally the correlator boards and microwave modules. Test items with existing equipment and test setups as they become available throughout the year. Fabricate and test the downconverter, which contains long-lead items and whose student work benefits from a schedule o the critical path. Connect an existing WASP2 correlator to the Ka-band receiver for lab tests in Green Bank. Remeasure and if needed mitigate internal RFI. Use the lab data to test the new data processing software.

Year 2: Procure and modify chassis, design and fabricate correlator backplanes and phase-switch timing cards, fabricate or purchase ancillary electronics, and assemble the spectrometers. The spectrometer package should arrive in Green Bank in time for lab tests with the receiver in Fall 2006. The software groups have also requested a two-week period of concentrated joint interface work some 4-6 months before the spectrometers arrive in Green Bank. Install Zpectrometer on the GBT for first observations in Winter 2006-2007.

Year 3: After finishing the observing season, evaluate hardware and software performance with astronomical results. Modify Zpectrometer as needed and return to the GBT in Fall 2007 for the winter observing season. Prepare relevant documentation and support equipment for GBT staff.

Zpectrometer Kick-off Meeting (Fall, 2005)

  • Attendees (hopefully): Karen O'Neil (GB), Amy Shelton (GB), Holly Chen (GB), Galen Watts (GB), Brian Mason (GB), Roger Norrod (GB), Andy Harris (UMd), Andrew Baker (UMd), Stephanie Zonak (UMd), Kevin Rauch (UMd)

-- KarenONeil - 12 Aug 2005 %META:FILEATTACHMENT{name="zpectrometer_prop.pdf" attr="" comment="Zpectrometer Proposal" date="1123862795" path="zpectrometer_prop.pdf" size="367165" user="KarenONeil" version="1.1"}% %META:FILEATTACHMENT{name="zpect_fab2.mpp" attr="" comment="Project Plan for Zpectrometer (12 August, 2005)" date="1123862828" path="zpect_fab2.mpp" size="169472" user="KarenONeil" version="1.1"}%


Topic ZpectProject . { View | Diffs | r1.51 | > | r1.50 | > | r1.49 | More }
Revision r1.1 - 12 Aug 2005 - 16:09 GMT - KarenONeil
Revision r1.51 - 05 Oct 2007 - 17:33 GMT - GalenWatts
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.