Timeline for the remaining calibration work:

Required resources for the remaining calibration work:

The remaining work for a full calibration package for the GBT can be broken into the following categories:

SCAL determinations for C, Ku, Ka, Q, PF1 (4 bands), & PF2

C, Ku, and PF2 are now done - RJM 10/19/05

Non-linearities & DC Offsets:

Weather Forecasting:

GBTIDL - Continuum (not fully scoped):

GBTIDL - Spectral Line

GFM - Continuum

GFM - Spectral Line

Astrid

Air Mass Estimation

Aperture Efficiencies

Telescope Calibration Factors

Science Data Model

-- RonMaddalena - 19 Jul 2005

Attachment: sort Action: Size: Date: Who: Comment:
CalibrationProject.pdf action 144920 19 Jul 2005 - 18:29 RonMaddalena PDF of the MS Project Gantt chart
CalibrationProject.mpp action 245760 19 Jul 2005 - 18:30 RonMaddalena MS Project Timeline/Gantt chart

Topic CalibrationTimeline . { Edit | Attach | Ref-By | Printable | Diffs | r1.3 | > | r1.2 | > | r1.1 | More }
Revision r1.3 - 19 Oct 2005 - 13:43 GMT - RonMaddalena
Parents: TWikiUsers > RonMaddalena > SpecLineCalibration
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.