| Goal | Original Date | Modified Date | Status |
| Complete straw man proposal for dynamic scheduling system | 1 Jun, 2006 | 13 Jun, 2006 | Complete |
| Present proposal to the GB staff and outside observers for comments | 1 Jun, 2006 | 21 Jun, 2006 | Complete |
| Present modified plans to GB staff for comments | 01 Jan, 2007 | 15 Jan, 2007 | Complete |
| Site presentation for GB staff | 01 May, 2007 | 12 May, 2007 | Complete |
| Present plans to user's committee | 7 May, 2007 | 17 May, 2007 | Complete |
| Conceptual design review | 06 Jun, 2007 | 06 Jun, 2007 | Complete |
| Description of test plans complete | 01 Feb, 2007 | 01 Dec, 2007 | |
| Call for proposals (test period) | 01 Jun, 2007 | 01 Jan, 2008 | |
| Stage II tests begin | 15 Aug, 2007 | 01 Jun, 2008 | |
| Stage II tests complete | 30 Sep, 2007 | 30 Sep, 2008 | |
| Complete Stage II | 01 Oct, 2007 | 01 Oct, 2008 | |
| Preliminary design review | 01 Dec, 2007 | 01 Dec, 2008 | |
| Release Stage III software for general use | 01 Jun, 2008 | 01 Oct, 2009 | |
| Release Stage IV software for general use | 01 Oct, 2009 | 01 Oct, 2010 | |