NRAO Home  >  Green Bank  |  Wiki Topic:    GB > Observing > CommissioningMeetings > CommissioningMeeting06Dec22
   Changes | Index | Contents | Search | Go

GBT Operations & Commissioning Meeting

22 December 2006

AGENDA


Upcoming Activities -- Carl

Activities list


Scheduling Status -- Carl


Last Week
=========

Observations for proposals
   GBT04A-040, GBT06C-051, GBT06C-042, 
   GBT06B-044, GBT06C-032, GBT05B-011, 
   GBT05C-023, GBT06B-036, GBT06C-102, 
   GBT06C-025, GBT06C-049, GBT06C-016, 
   GBT06C-038, GBT04A-027, BB234     , 
   GBT06B-018, GBT06C-039, GBT06C-019, 
   GBT05C-019

Completed proposals
   GBT06C-042, GBT06C-102, GBT06C-019

Next Week
=========
Observations scheduled for **
  GC028      [F  ] John Conway
       Sensitive high frequency observations of the      
       compact sources in Arp 220                        
  GBT04A-040 [ P ] Steve Myers
       Anomalous Microwave Emission from Spinning Dust   
       Grains?                                           
  GBT06C-052 [F  ] Scott Ransom
       Continued Timing of the Binary and Millisecond    
       Pulsars in NGC6440 and NGC6441                    
  GBT06C-032 [  B] Peter Martin
       The Galactic foreground at the North Ecliptic Pole
  GBT06B-044 [F  ] Robert Ferdman
       Timing Binary and Millisecond Pulsars from the    
       Parkes Multibeam Survey                           
  GBT06A-015 [ P ] Sandrine Bottinelli
       The hot corinos of solar-type protostars          
  GBT06C-035 [ P ] Jim Braatz
       The Megamaser Cosmology Project: A Survey for H2O 
       Maser Disks in SDSS AGNs                          
  GBT06C-048 [F  ] Nissim Kanekar
       HI 21cm absorption in strong MgII and CI          
       absorbers in the redshift desert                  
  GBT06C-038 [F B] Jay Lockman
       GBT Mapping of HI Clouds in the Disk-Halo         
       Interface                                         
  GBT06C-049 [F  ] Karen Masters
       Mapping Matter in the Nearby Universe with 2MASS  
  GBT06C-039 [ P ] Jim Braatz
       The Megamaser Cosmology Project: Circumnuclear    
       Disk Accelerations                                
  GBT01A-005 [ P ] Barry Turner
       A High-resolution Spectral Survey Of Tmc-1 At     
       Q-band                                            
  BB231      [F  ] Jim Braatz
       The Megamaser Cosmology Project: Measuring        
       Distances to NGC6323 and Mrk 1419                 
  GBT05C-019 [F B] Tim Robishaw
       The Galactic Arachnid in the Ursa Major Loop      
** Scheduled as F-ixed, P-rimary, B-ackup

Contact Information for 01/04/2007 - 01/18/2007
=======================================
Proposal   PI                 Bands Email [NRAO contact]    
---------- ------------------ ----- --------------------
GBT07A-074 Jack Hewitt        X     j-hewitt@northwestern.edu [Ron Maddalena]
GBT06C-051 Lincoln Greenhill  K     greenhill@cfa.harvard.edu [Jim Braatz]
GBT06B-042 Nissim Kanekar     4     nkanekar@nrao.edu [Larry Morgan]
GBT06B-032 Steve Begin        S     sbegin@physics.ubc.ca [Scott Ransom]
GBT06B-033 Jason Hessels      8     jhessels@science.uva.nl [Scott Ransom]
GBT06B-044 Robert Ferdman     L     ferdman@phas.ubc.ca [Scott Ransom]
GBT06C-032 Peter Martin       L     pgmartin@cita.utoronto.ca [Jay Lockman]
GBT06B-034 Jacqueline van Gor L     jvangork@astro.columbia.edu [Frank Ghigo]
GBT07A-036 Yi-nan Chin        CX    einmann@astro.phys.tku.edu.tw [Jim Braatz]
GBT06A-013 Jim Braatz         U     jbraatz@nrao.edu [Jim Braatz]
GBT07A-015 Jeff Mangum        CU    jmangum@nrao.edu [Frank Ghigo]
GBT06C-012 Steve Curran       4     sjc@phys.unsw.edu.au [Carl Bignell]
GBT06C-035 Jim Braatz         K     jbraatz@nrao.edu [Jim Braatz]
GBT05C-023 Fernando Camilo    8     fernando@astro.columbia.edu [Scott Ransom]
GBT06C-013 Steve Curran       4     sjc@phys.unsw.edu.au [Carl Bignell]
GBT06A-015 Sandrine Bottinell Q     sandrine@ifa.hawaii.edu [Dana Balser]
GBT06A-049 Tony Readhead      B     acr@astro.caltech.edu [Brian Mason]
GBT06C-058 Gary Fuller        KUX   G.A.Fuller@manchester.ac.uk [Larry Morgan]
GBT06B-037 Joel Weisberg      L     jweisber@carleton.edu [Toney Minter]
GBT06C-026 Clive Dickinson    U     cdickins@astro.caltech.edu [Larry Morgan]
GBT06C-048 Nissim Kanekar     4     nkanekar@nrao.edu [Toney Minter]
GBT06C-038 Jay Lockman        L     jlockman@nrao.edu [Jay Lockman]
GBT06C-016 Fernando Camilo    S     fernando@astro.columbia.edu [Scott Ransom]
GBT05C-026 Tom Devlin         X     devlin@physics.rutgers.edu [Brian Mason]
GBT04A-027 Brian Mason        B     bmason@nrao.edu [Brian Mason]
GBT06B-018 Michael Kramer     L     mkramer@jb.man.ac.uk [Scott Ransom]
GBT06C-017 Miles Blanton      U     mcb39@physics.unc.edu [Frank Ghigo]
GBT06C-018 Ingrid Stairs      LS    istairs@astro.ubc.ca [Scott Ransom]
GBT06B-019 Toney Minter       L     tminter@nrao.edu [Toney Minter]
GBT01A-005 Barry Turner       Q     bturner@nrao.edu [Frank Ghigo]
GBT06C-008 Raghunathan Sriana 4     anand@iucaa.ernet.in [Toney Minter]

Scheduled hours [backup]
========================
Category/Month-> December  January   
    Astronomy ~  585 [072] 636 [477] 
  Maintenance ~   62        52 [072] 
  Test & Comm ~   47 [011]  57 [022] 
     Shutdown ~   52         0       
  Un-assigned ~    5         4       

Proposal Checkouts
==================
Awaiting checkout - 45
  Active checkout - 0
          On Hold - 15
         Schedule - 64
        Completed - 582


Current backlog [hours prior to 06C*] = 821
   [2001:2(1), 2002:0(4), 2003:19(1), 2004:84(21), 2005:469(22), 2006:247(14)]
   Backlog excluding 207 hrs of monitoring projects after 06C = 614
Total time to discharge [hours] = 3905
   Includes 295 hours of monitoring after trimester 06C
* Includes projects that are on hold for trimester 06C


Az Track, Antennae Report -- Bob


Observing News -- Ron

The big news this week was the lost time due to the repair of the track grout. We used the down time rather productively. The down time served as our maintenance for the week, we had some servo repairs. The big 'winner' was Ka-commissioning which used the telescope as a transit instrument. About 20 hrs of astronomy was pre-empted.

We supported 18 projects in 25 observing sessions including some rather successful CCB observations. PTCS tests this week were cut short to 9 hrs due to the weather, the remaining time went to observing. We had 22 hrs of maintenance (16 hrs was originally scheduled), 22 hrs of Ka-band commissioning (8 hrs originally scheduled). Except for the grout problems, we had few problems this week:


Microwave Electronics Status -- Roger

No serious operational problems were reported. There was some troubleshooting of the feed defroster. Also, a retrofit of the cryo pressure monitor circuit board was done and we expect this will prevent the occasional oscillation problem seen in the past.

Design work continues for the C-band integrated receiver package. PCB purchase is being finalized. Progress was made on the housing design. Documentation of the phase 1 work is being prepared.

Six of the eight IF channels now have the new buffered power dividers installed.


Digital Electronics Status -- Randy

Digital Group Status 16-DEC-06 THRU 22-DEC-06

***Operations, Problem Summary***

Bob Simon reported that the feed defroster hardware wasn't responding to a "turn off" software command; however, subsequent testing showed that everything was working as expected.

Active Surface Maintenance...

Two LVDT modules were repaired which re-activated a total of 32 actuators.

***Development***

Caltech Continuum Backend (CCB)...

Construction of CCB #3 is still underway with a newly revised completion date of 12-JAN-07. Efforts to complete CCB #3 by year-end were upset by unexpected events (i.e., a death in Jason's family and illness in Randy's family). The newly revised completion date is 12-JAN-07.

Spectrometer LTA Re-design...

Design of the new FPGA Adapter PCB is nearly finished. A panelized version of the circuit board which eliminates the need for any sort of post-production de-panelization fixture has been designed (the finished assemblies will simply be snapped apart and their edges "dressed" with a simple sanding operation). A special fixture to hold the surface mount pins (84 on each board!) in place during assembly is now being designed with an expected completion date of 05-JAN-07.

ALMA...

On-going efforts are continuing fairly smoothly on the ALMA front.

***Plans***

Randy


Software Status -- Amy

We are in week five of the eighth (and final) development cycle of 2006 which can be viewed at PlanOfRecordC82006. We are scheduled to release mid-February 2007. Items deemed ready for release before that time will be patched in after they have been fully tested.

Operational and user support was relatively light this week and included:

Modification Requests:


PTCS -- John and Richard


Pulsar Related -- Scott

Had a meeting with Rich Lacasse and Rick Fisher discussing the design requirements for the Berkeley iBob/Bee2 FPGA-based "test" pulsar backend. Basically it will be a Spigot replacement (i.e. search mode only) with the additional capability of recording full Stokes parameters (of course with twice the frequency resolution that means that the data rates are between 2-8 times more than the Spigot as it is used now!). Rich seemed to have been pretty impressed with what the Berkeley folks have done.

Yesterday I greatly improved the python tools for reading and playing with raw Spigot data. These improvements will be crucial for the remaining work that Ryan and I will do after the New Year on the 8-bit Spigot modes.

An very quick example, showing the bandpasses for L-band and S-band -- including the RFI that I've been talking about between 1625 and 1650MHz, is shown in the plot below. GBT_L+S_bandpasses_annotated.png


MIT/LL 43m Project -- Glen

We had normal spacecraft tracking this week. Tracking this week will end on Saturday at 5 AM.

On January 2, the folks from MIT/LL will drive to GB to start installation of their dewar.


Commissioning Plans -- Ron

We have now finished all tests that we originally planned. Most items were achieved on our original schedule. Many of the changes to the original plan were to relax the installation and removal or receivers. Some were to provide external groups with more test time then they had originally asked for.

During the course of Ka-band commissioning, we came to the conclusion that fast nodding of the telescope might be a way to get around Ka's baseline problem. This week we tried Brian's method for fast nodding using antenna trajectories within a single scan. In January, we'll test whether baselines are helped by using the subreflector to nod the beam of the telescope. The tests we performed during the grout repair were meant to determine the kind of baseline shapes we would see if we treated the Ka-band receiver as a total power device, rather than a correlation receiver.

Commissioning Summary & Milestones: Sept 1 - Dec 31:

Receiver Installation Schedules


Any other Business

-- CarlBignell - 21 Dec 2006

Topic CommissioningMeeting06Dec22 . { Edit | Attach | Ref-By | Printable | Diffs | r1.10 | > | r1.9 | > | r1.8 | More }
Revision r1.10 - 22 Dec 2006 - 14:29 GMT - ScottRansom
Parents: WebHome > CommissioningMeetings
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.