NRAO Home  >  Green Bank  |  Wiki Topic:    GB > Observing > CommissioningMeetings > CommissioningMeeting07Aug03
   Changes | Index | Contents | Search | Go

GBT Operations & Commissioning Meeting

03 August 2007

AGENDA


Upcoming Activities -- Carl

Activities List


Az Track, Antennae Report -- Bob

Only two welds remain to be completed as of this morning, along with a section of base plate to splice plate welds. Next week will see final height adjustments at night, machining of the top surfaces, and forming for grout installation. We still expect to be able to permit pointing runs mid-August.


Observing News -- Ron

Receiver Checkout -- Frank

Brief summary of the checkout of S- and X-band receivers, August 2-3, 2007. Frank, Jules, and Paul observing in Green Bank, Scott in C-ville, with Barry and Greg operating. No azimuth motion was possible, but we were allowed to set the elevation to anything above 30 degrees.

The plan was to watch the transits of several calibration sources from Condon's calibrator lists while collecting spectral line data.

The first problem was that the database telling the antenna which receiver was in which slot had not been updated, and also that the cabling file, although it had been updated, had not been re-loaded. Mark Clark came in and took care of these details.

At X-band, we failed to see a source transit. Our predictions of the correct elevation for transit seemed to be confirmed by the antenna readback of the J2000 position, which was within an arcminute of the correct declination. Nevertheless we never saw a good transit after 4 attempts. Otherwise, the X-band receiver seemed to be working ok as far as we could tell.

There was better luck at S-band; we did see sources transit. The RFI from the XMM/Sirius satellites was visible in the band. Observing a calibrator at narrow bands to avoid the satellites showed about the right antenna temperature.

Scott checked spigot observing with the S-band receiver, and reports that things seemed to be working. The sharper bandpass cutoff at the lower end was apparent, and he saw much reduced RFI.


Scheduling Status -- Carl

Last Week
=========

Observations for proposals
   GBT07B-012

Next Week
=========
Observations scheduled for **
  GBT07B-012 [F B] Dunc Lorimer
       Pulsar searching in the classroom using the GBT   
  GBT07B-035 [F  ] Sue Ann Heatherly
       WV Governor's School for Math and Science (GSMS)  
** Scheduled as F-ixed, P-rimary, B-ackup

Contact Information for 08/16/2007 - 08/30/2007
=======================================
Proposal   PI                 Bands Email [NRAO contact]    
---------- ------------------ ----- --------------------
GBT07B-011 Dunc Lorimer       3     Duncan.Lorimer@mail.wvu.edu [Toney Minter]
GBT07B-012 Dunc Lorimer       3     Duncan.Lorimer@mail.wvu.edu [Toney Minter]
GBT07B-017 Vlad Kondratiev    3     vlad.kondratiev@mail.wvu.edu [Toney Minter]
GBT07B-006 Fernando Camilo    S     fernando@astro.columbia.edu [Toney Minter]
GBT07B-008 Nissim Kanekar     3     nkanekar@nrao.edu [Frank Ghigo]
GBT07A-060 Julia Deneva       S     deneva@astro.cornell.edu [Scott Ransom]

Scheduled hours [backup]
========================
Category/Month-> August    September 
    Astronomy ~  181 [323] 314 [376] 
  Maintenance ~  189        21 [068] 
  Test & Comm ~  374       322 [030] 
  Un-assigned ~    0        93       

Proposal Checkouts #[hrs]*
=========================
Awaiting checkout - 0[0]
  Active checkout - 0[0]
          On Hold - 0[0]
         Schedule - 76[3221]
        Completed - 491[6289]
* All but completed queue applies to GBT only proposals


Current backlog of Reg & RRS proposals [hours prior to 07B*] = 1170
   [2005:369(14), 2006:358(18), 2007:444(21)]
   Backlog includes 59 hrs of monitoring projects
                    182 hrs of vlbi projects
Total time to discharge [hours] = 5195
   Includes 274 hours++ of monitoring (not Large or Spec) after trimester 07B
            1646 hours of Regular & RRS proposals 
            3317 hours of Large proposals 
            50 hours of Track Refurbishment proposals 
            182 hours of VLBI proposals 
* Includes projects that are on hold for trimester 07B
++ Time is counted in other break down as well. 07B


Microwave Electronics Status -- Steve

Operations

Development


Digital Electronics Status -- Randy

Operations, Problem Summary

None

Development

LTA tests continue on the bench successfully.

Plans


Servo Systems Status -- John and Bob

Operations, Problem Summary

Tests for the subreflector actuators will be attempted next week. It is suspected that they are not tracking commands properly.

Development

Testing of PLC interlock system upgrade continues. PLC logic program being tested along with analog control board. Tests should complete next week. Software for interfacing the CCU with the PLC is being developed.

Software Status -- Amy


Computing -- Chris

140ft network upgrade is complete. The link from the Jansky lab is now at 1Gbps instead of 100Mbps and a Cisco 3550 switch is in place.

Funds to upgrade the servo room switch have become available and a plans are being developed which will provide more network connections and a much faster switching fabric. If the parts can be delivered and configured in time I hope to get this installed by the end of August.


PTCS -- PTCS Team

Servo Systems: No progress

Pointing: Joe is ready to test the new M&C pointing model implementation w.r.t. Kim's model. I plan to have a pointing meeting mid-week of next week to schedule these tests, and our plans for the track recovery observations.

Holography: The vicinity of the optical camera mount should be an acceptable location for the holography reference receiver, at least in terms of opening angle w.r.t. the telescope structure. Steve has estimated the length and cost for the necessary low-temperature coefficient IF cable, and the loss in dB. Still need to work out the mechanical details, and a surveying strategy to measure the position of the horn. Ron Grider estimates that phase 1 of the Linux upgrade of the control software for the backend will be complete in about 2 weeks.


Pulsar Related -- Scott

Ran tests with the newly upgraded S-band receiver last night with the cold RFI filter. Test pulsars and pulsed cals looked just fine, as does the bandpass. I see no evidence of the nasty Iridium interference leaking through (and it was that interference that the new filter was intended to get rid of. The only bad thing is that is looks like we've lost about 60 MHz of usable BW. The plot below shows most all of what I've said graphically.

GBT_S_bandpasses.png


MIT/LL 43m Project -- Glen


Commissioning Plans -- Ron


Any other Business

-- RichardPrestage - 02 Aug 2007

Topic CommissioningMeeting07Aug03 . { Edit | Attach | Ref-By | Printable | Diffs | r1.11 | > | r1.10 | > | r1.9 | More }
Revision r1.11 - 03 Aug 2007 - 13:55 GMT - RonMaddalena
Parents: WebHome > CommissioningMeetings
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.