GBT Operations & Commissioning Meeting

26 January 2007

AGENDA


Upcoming Activities -- Carl

Activities List


Az Track, Antennae Report -- Bob


Observing News -- Ron

We supported 20 projects in 30 observing sessions. The telescope was scheduled for 12.5 hrs of maintenance. The weather was the big storey this week with regards to lost time. I'm now breaking up lost time into 3 categories:

The Spigot/EDT problem was discussed at last week's meeting. AutoPeakFocus? seemed to be confused and was setting the wrong initial parameters for a focus. It also picked a source that was too weak.


Scheduling Status -- Carl

Last Week
=========

Observations for proposals
   GBT07A-074, BG169     , GBT07A-001, 
   GBT06B-044, GBT06B-034, GBT07A-036, 
   GBT06C-012, GBT06A-004, GBT06B-036, 
   GBT07A-104, GBT06C-058, GBT06C-038, 
   GBT06C-016, GBT05C-026, GBT06C-017, 
   GBT07A-009, GBT05C-027, GBT06C-039, 
   GBT01A-005

Completed proposals
   GBT06A-004, GBT06C-039, GBT01A-005

Next Week
=========
Observations scheduled for **
  GBT07A-074 [ P ] Jack Hewitt
       Follow-Up of Radio Recomb Lines Associated with   
       Supernova Remnants                                
  GBT07A-098 [F B] Fernando Camilo
       Studying the magnetar XTE J1810-197               
  BG169      [F  ] Lincoln Greenhill
       Mapping the Accretion disks in the IC2560 and     
       NGC3393 AGN: Implications for Ho                  
  GBT07A-001 [F B] Alberto Bolatto
       A Search for HI Absorbers in a Sample of          
       Gravitationally Lensed Systems                    
  GBT07A-036 [  B] Yi-nan Chin
       Confirmation of Interstellar Benzonitrile         
       (C6H5CN) -- A Key Tracer of Benzene               
  GBT07A-003 [F B] Vincent Fish
       Probing circumstellar envelopes with isotopomers  
  GBT06B-034 [  B] Jacqueline van Gorkom
       Galaxy evolution in groups: HI properties of 80   
       2dfGRS-selected groups                            
  GBT07A-015 [ PB] Jeff Mangum
       Formaldehyde Densitometry of External Galaxies    
  GBT06B-024 [ P ] Jeff Mangum
       CCS Chronometry of Dense Cores                    
  GBT06C-012 [  B] Steve Curran
       A Wide-Band Search of the Source of the           
       Obscuration of Reddened Quasars                   
  BB229      [F  ] Andreas Brunthaler
       Measuring the orbits of M81 and M82               
  GBT02A-054 [  B] Ingrid Stairs

       High-resolution Studies of a Precessing Pulsar    
  GBT06B-036 [ P ] Jim Jackson
       Pre-stellar evolution in Infrared Dark Cloud Cores
  GBT07A-104 [  B] Peter Martin
       The Spider's Web from Ursa Major to Polaris       
  GBT06B-015 [ P ] Larry Morgan
       NH3 and CCS Mapping of Triggered Star Formation   
       Regions                                           
  GBT06C-037 [ P ] Charlie Lada
       Probing the Origin of Dense Cores and the Stellar 
       IMF                                               
  GBT06C-004 [ P ] Tony Remijan
       A Search for o-Benzyne (o-C6H4) and Phenyl (C6H5) 
       toward CRL 618                                    
  GBT05C-037 [F  ] Nissim Kanekar
       Measuring changes in fundamental constants with   
       redshifted OH  lines                              
  GBT06C-038 [F  ] Jay Lockman
       GBT Mapping of HI Clouds in the Disk-Halo         
       Interface                                         
  GBT06C-016 [F  ] Fernando Camilo
       Studying the magnetar XTE J1810-197               
  GBT05C-027 [ P ] Jeff Mangum
       An Exact Identification of High Densities in      
       Molecular Clouds                                  
  GBT07A-009 [F  ] D.J. Pisano
       HI Emission from Gravitationally Lensed Galaxies  
       at z~0.5                                          
** Scheduled as F-ixed, P-rimary, B-ackup

Contact Information for 02/08/2007 - 02/22/2007
=======================================
Proposal   PI                 Bands Email [NRAO contact]    
---------- ------------------ ----- --------------------
GBT07A-063 Amanda Kepley      L     kepley@astro.wisc.edu [Toney Minter]
GBT07A-030 Brian Mason        X     bmason@nrao.edu [Brian Mason]
GBT07A-074 Jack Hewitt        X     j-hewitt@northwestern.edu [Ron Maddalena]
GBT07A-031 Jim Braatz         K     jbraatz@nrao.edu [Jim Braatz]
GBT07A-020 Scott Schnee       K     schnee@astro.caltech.edu [Jim Braatz]
GBT07A-098 Fernando Camilo    S     fernando@astro.columbia.edu [Scott Ransom]
GBT06A-053 Scott Ransom       S     sransom@nrao.edu [Scott Ransom]
GBT06C-051 Lincoln Greenhill  K     greenhill@cfa.harvard.edu [Jim Braatz]
GBT06C-052 Scott Ransom       S     sransom@nrao.edu [Scott Ransom]
GBT07A-034 Jim Braatz         K     jbraatz@nrao.edu [Jim Braatz]
GBT07A-089 Fernando Camilo    8     fernando@astro.columbia.edu [Scott Ransom]
GBT06B-032 Steve Begin        S     sbegin@physics.ubc.ca [Scott Ransom]
GBT07A-001 Alberto Bolatto    L     bolatto@astro.berkeley.edu [Frank Ghigo]
GBT06C-020 Rachel Friesen     K     rfriesen@uvastro.phys.uvic.ca [Toney Minter]
GBT06A-056 Paul Kondratko     K     pkondrat@cfa.harvard.edu [Jim Braatz]
GBT06B-044 Robert Ferdman     L     ferdman@phas.ubc.ca [Scott Ransom]
GBT06B-033 Jason Hessels      8     jhessels@science.uva.nl [Scott Ransom]
GBT07A-036 Yi-nan Chin        C     einmann@astro.phys.tku.edu.tw [Jim Braatz]
GBT05C-043 Nissim Kanekar     Q     nkanekar@nrao.edu [Dana Balser]
GBT07A-015 Jeff Mangum        C     jmangum@nrao.edu [Frank Ghigo]
GBT07A-048 Larry Rudnick      L     larry@astro.umn.edu [Toney Minter]
GBT07A-104 Peter Martin       L     pgmartin@cita.utoronto.ca [Jay Lockman]
GBT06C-035 Jim Braatz         K     jbraatz@nrao.edu [Jim Braatz]
GBT07A-016 Jennifer Donovan   L     jen@astro.columbia.edu [Frank Ghigo]
BB227      Jim Braatz         K     jbraatz@nrao.edu []
GBT06C-003 Tony Remijan       K     aremijan@nrao.edu [Larry Morgan]
GBT06C-037 Charlie Lada       K     clada@cfa.harvard.edu [Frank Ghigo]
GBT06C-048 Nissim Kanekar     8     nkanekar@nrao.edu [Toney Minter]
BM253      Emmanuel Momjian   L     emomjian@naic.edu []
GBT06C-049 Karen Masters      L     kmasters@cfa.harvard.edu [Larry Morgan]
GBT06B-028 Ingrid Stairs      L     istairs@astro.ubc.ca [Scott Ransom]
GBT07A-080 Maura McLaughlin   3     maura.mclaughlin@mail.wvu.edu [Scott Ransom]
GBT06B-018 Michael Kramer     8     mkramer@jb.man.ac.uk [Scott Ransom]
GBT05C-027 Jeff Mangum        QUB   jmangum@nrao.edu [Dana Balser]
GBT06C-028 Brenda Matthews    K     brenda.matthews@nrc-cnrc.gc.ca [Ron Maddalena]
GBT03C-028 Fabian Walter      Q     walter@mpia.de [Dana Balser]

Scheduled hours [backup]
========================
Category/Month-> January   February  March     April     
    Astronomy ~  631 [067] 572 [470] 622 [558] 607 [309] 
  Maintenance ~   62 [004]  35 [047]  41 [059]  32 [051] 
  Test & Comm ~   51 [004]  65 [024]  60 [025]  42 [008] 
     Shutdown ~    0         0         0        14       
  Un-assigned ~    0         2        28        29       

Proposal Checkouts
==================
Awaiting checkout - 27
  Active checkout - 2
          On Hold - 16
         Schedule - 71
        Completed - 594


Current backlog [hours prior to 06C*] = 688
   [2002:0(4), 2003:19(1), 2004:75(21), 2005:446(22), 2006:148(13)]
Total time to discharge [hours] = 3455
   Includes 993 hours of monitoring after trimester 06C
   Includes 770 hours during Track Refurbishment
* Includes projects that are on hold for trimester 06C


Microwave Electronics Status -- Roger

No operational problems were reported.

Design work continues for the C-band integrated receiver package. The PCBs are scheduled to be delivered on Feb 16. The housing drawings were completed and released to the shop for fab.

Work on PF1 continued. The 340MHz cryo amp was replaced. Phase balancing for circular polarization and functional testing nears completion. Thermal cals are to be done but things are on track for installation next week.

Two of the updated Converter Module detector boards have been assembled, and testing waits for housings to be completed.

Bench testing of a two-channel IF system for the Lab Spectrometer nears completion, and we expect to be testing it with the spectrometer in the next couple of weeks.


Digital Electronics Status -- Randy

Digital Group Status 20-JAN-07 THRU 26-JAN-07

***Operations, Problem Summary***

No problems to report this week.

Active Surface Maintenance...

No work was done on the Active Surface this week.

***Development***

Caltech Continuum Backend (CCB)...

Spectrometer LTA Re-design...

In the interest of improved manufacturability and reliability, a decision was made to create a version of the FPGA Adapter PCBA which eliminates the series resistors and increases the PLCC 84 solder lands to a size consistent with IPC recommendations. The process of modifying the design should be complete by 02-FEB-07.

New Pulsar Backend...

Owing to the bad weather, it was decided to postpone our design review until a later date which is yet to be determined.

ALMA...

On-going efforts are continuing fairly smoothly on the ALMA front.

MISCELLANEOUS...

The Science Center's fire alarm system has been operating 24/7 without false alarms for two weeks now. It would seem that this issue has been resolved, so no further reports will be forthcoming unless the situation changes.

***Plans***

Randy


Software Status -- Amy

We are in week four of the first development cycle of 2007 which can be viewed at PlanOfRecordC12007. We are scheduled to release 14 February 2007.

We have two dates for integration tests: 6 or 8 Feb., 1630 to 2030, and 7 Feb, 1845 to 2245. In addition, we have regression testing scheduled for the 9th, 1800 to midnight. We are also reserving some maintenance days to serve as test time in order to ensure the smooth release of 7.1. We also performed testing on the new version on Thursday, January 25th as a precursor to the integration tests because this release involves many changes accumulated over several cycles of effort.

Operational and user support was relatively light this week and included:

Modification Requests:


PTCS -- PTCS team


Pulsar Related -- Scott


MIT/LL 43m Project -- Glen


Any other Business

Topic CommissioningMeeting07Jan26 . { Edit | Attach | Ref-By | Printable | Diffs | r1.8 | > | r1.7 | > | r1.6 | More }
Revision r1.8 - 26 Jan 2007 - 15:44 GMT - RogerNorrod
Parents: WebHome > CommissioningMeetings
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.

Observing.CommissioningMeeting07Jan26 moved from Observing.CommissioningMeeting07Jan25 on 25 Jan 2007 - 18:22 by AmyShelton - put it back