AGENDA


Upcoming Activities -- Carl

Activities List


Az Track, Antennae Report -- Bob

Work progresses a little slower and meticulously (and quieter!)after all the demolition has been completed.

140': Preston restarted all of the systems successfully last night following the transformer installation, and we are in the process of replacing the broken brake spring. That should finish up late today.


Observing News -- Ron


Scheduling Status -- Carl



Microwave Electronics Status -- Steve

Operations

Development


Digital Electronics Status -- Randy

Operations, Problem Summary

Development

Plans


Servo Systems Status -- John and Tim

No activity


Software Status -- Amy

We are in the first full week of the fourth development cycle of 2007 which can be viewed at PlanOfRecordC42007.

Operational and user support was relatively light this week and included:

Modification Requests:


Computing -- Chris


PTCS -- PTCS Team


Pulsar Related -- Scott

Not a whole lot of development to report this week. We've been continuing to take data for more than the scheduled amount of time for the drift scan project. And that has made us go though all of the group's disks slightly faster than we had expected (especially since we were scheduled for more time than we asked for!). But yesterday we started the process to order between 100-130 750GB drives. So assuming that the first batch shows up in time, that should help us quite a bit.

As far as the data taking goes, we've been observing in the "hacked-calibration" 8-bit mode that Ryan and I came up with. In general, it seems to be working quite well and we are seeing the known pulsars that we should be seeing. Hopefully next week we have some time to make "real" Spigot calibrations work.

The pulsar meeting I thought was quite a success. There were lots of good discussions and many of us have new ideas for future work and collaborations.

Finally, Paul Demorest showed up in C-ville this past week. He's getting settled in now and we're going to try to spin him up on the new pulsar backend over the next 2 weeks.

PS: I will not be at the meeting as I need to go to be at a Drs appt with my wife.


MIT/LL 43m Project -- Glen


Commissioning Plans -- Ron


Any other Business

-- RichardPrestage - 24 May 2007

Topic CommissioningMeeting07May25 . { Edit | Attach | Ref-By | Printable | Diffs | r1.7 | > | r1.6 | > | r1.5 | More }
Revision r1.7 - 25 May 2007 - 14:06 GMT - AmyShelton
Parents: WebHome > CommissioningMeetings
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.