| STEP | ACTION |
| 1 | Launch the Cleo IF Manager application. Select the Load Cabling List option under the File menu (brings up cabling file browser in the home/gbt/etc/config directory). Select and load the new cable file. |
| NOTE | If there are any syntax errors in the new file they will appear either as CLEO pop-up messages and/or messages in the CLEO Message window. If errors occur, inform the engineer so they can fix the file. The operator will then need to reload the cabling file. |
| 2 | Launch Cleo LO1 application. Turn the LO1 manager OFF then back ON. |
| 3 | Launch the Cleo IF Rack application. Go to the Managers menu and select Reset Parameters. |
| 4 | Inform the electronics division engineer that your part is complete. They will verify the cabling file update and advise if problems (if any) are noted. |