1. If the outage occurs during regular working hours, advise Rusty Taylor (2274/2286) in the Plant Maintenance Division, Mike Holstein in the business office, and Pete Chestnut (2296) or Bob Anderson (2205) in the Telescope Operations Division.

2. Other than normal working hours contact the following in the order listed:

3. Upon arrival at the site, one of those listed above will act as coordinator and determine the nature of the problem. If the problem is found to be a commercial power failure, the following steps should be taken:

4. If power failure is the result of accident, fire, disaster, etc., notify Johnny Samples (2215, home 636-2725) or alternate, Jody Bolyard (2223, home 456-5345).

5. From this point on the action taken will have to be determined by the coordinator. All personnel should carry portable radios, or be in radio contact.

6. Computers systems and network servers will likely go down depending on UPS or backup power generator and will need to be restarted once commercial power is reestablished. Therefore, the fiscal and computer divisions must be contacted, as follows:

7. In the event of a known extended power outage, the following steps should be taken:

8. Since a power outage may occur during severe rain, the generators at the Interferometer Control Building and 43meter telescope must be started as soon as possible in order to protect the HVAC systems, etc., from flooding. Notify Pete Chestnut (457-4457) or secondly Rusty Taylor (456-3125) so that the sump pumps may be switched over to generator power.

9. Upon restoration of power, the operator is to check GPS and 1PPS logs to assure that the clocks are okay. If not okay, call:

The restoration of power to the site should be the responsibility of the coordinator and the site electrician.

Extracted from the memo: Power Failure, Butch Wirt, April 14, 2003. Minor format changes made and POC's updated to reflect personnel changes.

-- DavidRose - 20 Feb 2008

Topic ObservatoryWidePowerFailure . { Edit | Attach | Ref-By | Printable | Diffs | r1.4 | > | r1.3 | > | r1.2 | More }
Revision r1.4 - 20 Feb 2008 - 16:28 GMT - DavidRose
Parents: WebHome > TelescopeOperations
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.