NRAO Home  >  Green Bank  |  Wiki Topic:    GB > Software > PlanOfRecordC62008 > ModificationRequest1C608
   Changes | Index | Contents | Search | Statistics | Go

Integrate GUPPI into the config_tool

Modification Request #1 (C06 2008)



1. Introduction

Even if you wrote an MR and it's in Tex or another format, it is important that you at least cut and paste your introduction/restatement of requirements onto the wiki page so that your information is searchable.

2. Background

3. Requirements

What are the implementation-independent requirements for this MR?

3.1 Mapping Configuration Keywords to Manager Parameters

config_tool Primary Keyword GUPPI Manager Parameter Default Value
backend N/A "Guppi"
restfreq ??? N/A
bandwidth bandwidth N/A

3.2 Defining the IF Path Between the Receiver and GUPPI

4. Design

What is your plan? How are you going to fulfill the requirements?

5. Add Any More Sections That Are Appropriate

6. Deployment Checklist

What has to get done to integrate this completely into the system. The generated checklist must be completed before Cycle Integration Testing begins.

Note - The questions below are just to get you thinking. Remove irrelevant questions. Answer relevant ones, but don't keep the question text. And, please take a moment to think of anything else that needs to happen during deployment.

7. Test Plan

Critical!! ChangeControlCommittee will be reviewing these. Please send a link to this MR to RonMaddalena along with a suggestion for two reviewers when it is ready for CCC review.

Don't forget to include/acquire any additional GBT test time needed outside integration/regression testing! Get your requests in early!

Important! If possible, you should conduct as many of your tests as possible in offline modes and/or with a simulator. We should constantly endeavor to minimize our use of telescope time for testing!

7.1 Internal Testing

This section covers things like unit testing, simulator testing, and any other tests required to make sure this MR is ready for sponsor/integration/regression testing.

7.2 Sponsor Testing

This section is for the sponsor. What do you need to do in order to ensure that the MR is complete and correct? These tests are the prerequisite for sign off for the "accepted/delivered by sponsor" item in the "signatures" section.

7.3 Integration/Regression Tests

What do the integration/regression testers need to do in order to test this MR.


Signatures

APPROVED: To the best of my knowledge, the request in this MR is complete. I have thought through this request, and believe it to be an important feature to implement or bug to fix.

ACCEPTED: I acknowledge that I have validated the completed code according to the acceptance tests.

Written symbol - name - date
Checked symbol - name - date
Approved by Sponsor symbol - name - date
Approved by CCC symbol - name - date
Accepted/Delivered by Sponsor symbol - name - date

Symbols:


CCC Discussion Area

Topic ModificationRequest1C608 . { Edit | Attach | Ref-By | Printable | Diffs | r1.2 | > | r1.1 | More }
Revision r1.2 - 28 Oct 2008 - 15:20 GMT - AmyShelton
Parents: PlanOfRecordC62008
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.