Improved Processing of Ka-band Pointing Data by GFM and PrePoint

Modification Request 2C707, October 2007



1. Introduction

The use of the CCB (Caltech Continuum Backend) with the Ka-band receiver will become more common in the near future. The primary PTCS pointing and OOF calibrations will be done in this mode. So it is important for GFM and PrePoint to handle the CCB data gracefully. Certain aspects of this observing mode are different from the usual cases for most of the other receivers in combination with the DCR:

2. Background

Previously the main concern was that GFM produce reasonable pointing corrections, which it does.

At the moment, when one runs gfm (or prepoint) on Ka-band CCB data, it looks by default for the XL polarization data on beam 1 and complains because it cannot find it. The only data processing options available in GFM are "X/Left" or "Y/Right". Regardless of which one you select, the same exact plots and fitted parameters result, but in neither case are the plots labeled correctly (they should be labeled "1R/2L" because this is the only combination that exists).

GFM/PrePoint ignores any noise cal data, and produces amplitudes in terms of raw counts; thus no information about system temperatures can be determined.

For Ka/CCB data, PrePoint produces an output file with two lines for each scan, labeled RCP and LCP, but in fact these two lines are identical. It only processes one of the four frequencies.

3. Requirements

How about the description from:

http://wiki.gb.nrao.edu/bin/view/Data/GbtFitsMonitorKA_DCR

To expand on the above, the specific things I know that need to be done are:

These comments probably have an impact on this MR but implications beyond it.

BSM 27nov07

4. Design

5. Deployment Checklist

6. Test Plan

6.1 Internal Testing

6.2 Sponsor Testing

6.3 Integration/Regression Tests


Signatures

APPROVED: I acknowledge that my request is fully contained in this MR, and if the SDD delivers exactly what I specified, I will be happy.

ACCEPTED: I acknowledge that I have validated the completed code according to the acceptance tests, and I am happy with the results.

Written - - - - -
Checked - - - - -
Approved by Sponsor - - - - -
Approved by CCC - - - - -
Accepted/Delivered by Sponsor - - - - -

Symbols:


CCC Discussion Area

Topic ModificationRequest2C707 . { Edit | Attach | Ref-By | Printable | Diffs | r1.6 | > | r1.5 | > | r1.4 | More }
Revision r1.6 - 27 Nov 2007 - 20:36 GMT - FrankGhigo
Parents: PlanOfRecordC72007
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.