Upgrade Weather 1 Manager

Modification Request #3 (C3 2006)



1. Introduction

We plan to install a humidity/temperature instrument at Weather 1, giving us full redundancy with Weather 2. Jason Ray has the instruments in hand, and will supervise the installation.

Advantages: Complete redundancy for refraction corrections and weather conditions. It allows us to take WT2 down for calibration or repair without impacting high-frequency observations.

Currently there are no spare fibers to WT2; installation of a six-fiber cable will allow the radio repeater installation as originally planned plus provide spare fibers, but the station will be out of service for a couple of days to do so. Work on WT2's fibers won't start until the after the WT1 upgrade.

This MR specifies the software changes necessary to enable the Weather1 Manager to provide humidity and temperature information. This MR complements the work being done in ModificationRequest4C306.

2. Requirements

The Weather1 Manager will need to read the humidity and temperature. (Note wind and pressure instruments are already there.)

Details:

3. Design

Manager

The Weather1Data structure must be augmented to include two new data members - one for humidity and one for temperature.

The monitor method of the Weather1Mgr class must be augmented to include the reading of humidity and temperature via the SIB/MCB with the appropriate addresses and scaling factors mentioned in the requirements section above.

DDL

The Weather1 Manager DDL must be augmented. Two new fields will be added to the Weather1 sampler: HUMIDITY and TEMPERATURE. Both fields will be of type float. The new fields will have units of none and Celsius respectively.

4. Deployment Checklist

What has to get done to integrate this completely into the system. This checklist must be completed before Cycle Integration Testing begins.

5. Test Plan


Signatures

APPROVED: I acknowledge that my request is fully contained in this MR, and if the SDD delivers exactly what I specified, I will be happy.

ACCEPTED: I acknowledge that I have validated the completed code according to the acceptance tests, and I am happy with the results.

Written DONE - RogerNorrod, JasonRay - 5Apr06
Checked DONE - AmyShelton - 06 Apr 2006
Approved by Sponsor DONE - JasonRay - 07 Apr 2006
Approved by CCC DONE - JohnFord - 10 Apr 2006
Accepted/Delivered by Sponsor DONE - JasonRay - 13 Apr 2006

Symbols:


CCC Discussion Area

Topic ModificationRequest3C306 . { Edit | Attach | Ref-By | Printable | Diffs | r1.10 | > | r1.9 | > | r1.8 | More }
Revision r1.10 - 13 Apr 2006 - 18:16 GMT - JasonRay
Parents: PlanOfRecordC32006
Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.