Change Spectrometer Warning Messages During Balance

Back to balancing overview



1. Introduction

Currently, the Spectrometer gives a warning message when the power levels are more than 0.5 dB outside the ideal range. This is not an accurate indicator of when an observer should be concerned about her power levels, nor does it provide any information on the severity of the problem. The current warning message is generated whenever the Spectrometer Manager has done a "Prepare" (e.g. after a balance command or when it enters the "Running" state) if the power levels, as measured by the duty cycles, are at least 0.5dB from the idea values, as calculated in Rick Fisher's memo. While this is useful, a better indicator would (1) not provide any message until the Spectrometer is 1dB outside the ideal range, and (2) provide an warning message if the spectrometer is more than 2.5 dB outside its ideal range.

2. Background

This MR is part of a series of MRs aimed at creating a production Balancing API in Python. For more information regarding this effort, please refer to the BalancingMetaMR.

3. Requirements

4. Design

The ScanStart balance option will be removed from the spectrometer as part of this MR.

5. Deployment Check List

6. Test Plan

Critical!! ChangeControlCommittee will be reviewing these.

Don't forget to include/acquire any additional GBT test time needed outside integration/regression testing! Get your requests in early!

Important! If possible, you should conduct as many of your tests as possible in offline modes and/or with a simulator. We should constantly endeavor to minimize our use of telescope time for testing!

6.1 Internal Testing

This section covers things like unit testing, simulator testing, and any other tests required to make sure this MR is ready for sponsor/integration/regression testing.

6.2 Sponsor Testing

6.3 Integration/Regression Tests

What do the integration/regression testers need to do in order to test this MR.


Signatures

APPROVED: I acknowledge that my request is fully contained in this MR, and if the SDD delivers exactly what I specified, I will be happy.

ACCEPTED: I acknowledge that I have validated the completed code according to the acceptance tests, and I am happy with the results.

Written DONE - KarenONeil - 14 Sep 2005
Checked symbol - product/version - date
Approved by Sponsor symbol - product/version - date
Approved by CCC symbol - product/version - date
Accepted/Delivered by Sponsor symbol - product/version - date

Symbols:


CCC Discussion Area

-- KarenONeil - 04 Aug 2005

Topic ModificationRequest9C505 . { Edit | Attach | Ref-By | Printable | Diffs | r1.11 | > | r1.10 | > | r1.9 | More }
Revision r1.11 - 08 Dec 2006 - 20:40 GMT - AmyShelton Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.