NRAO Home  >  Green Bank  |  Wiki Topic:    GB > Software > PlanOfRecordC12008
   Changes | Index | Contents | Search | Statistics | Go

Software Plan of Record

Cycle 1 2008 (January 1 - February 15, 2007)


Weeks

  • Week 1 1/1 - 1/4
  • Week 2 1/7 - 1/12
  • Week 3 1/14 - 1/19
  • Week 4 1/21 - 1/26
  • Week 5 1/28 - 2/2
  • Week 6 2/4 - 2/9
  • Week 7 2/11 - 2/15

Release date for M&C/Sparrow: February, 2008

Who's in the Box?
  • Amy - 1% Support, 60% Management, 5% Program Development, 10% Dynamic Scheduling, 3% RFI, 11% KFPA, 10% Leave
  • Bob - 10% Support, 60% KFPA, 10% Calibration, 10% Leave, 10% Administration
  • Joe - 3% Support, 57% PTCS, 10% Mustang, 10% GUPPI, 10% Leave, 10% Administration
  • Lihong - 45% RFI, 25% Research, 10% Integration Testing, 10% Leave, 10% Administration
  • Mark C. - 4% Support, 76% Dynamic Scheduling, 10% Leave, 10% Administration
  • Mark W. - 80% Mustang, 10% Leave, 10% Administration
  • Melinda - 75% Mustang, 5% PTCS, 10% Leave, 10% Administration
  • Mike - 1% Support, 79% Dynamic Scheduling, 10% Leave, 10% Administration
  • Paul - 1% Support, 75% Mustang, 4% Dynamic Scheduling, 10% Leave, 10% Administration
  • Pete - 80% PTCS, 10% Leave, 10% Administration
  • Ray - 5% Support, 75% Mustang, 10% Leave, 10% Administration
  • Ron G. - 70% PTCS, 10% Integration Testing, 10% Leave, 10% Administration
  • Ron D. - 25% Cicada (partnership with e2e division)

Use the order as a guideline in order to determine the relative priority of jobs.

Key for the "MR Status" column:

  • DONE (%Y%) means the MR has final sponsor sign-off
  • MOVED TO... (%M%) means the MR is awaiting final sponsor sign-off
  • PICK (%S%) means the MR is being implemented (has CCC approval)
  • ALERT! (%X%) means the MR needs CCC approval
  • REFACTOR (%P%) means the MR is either being written, checked, or needs initial sponsor approval
  • N/A means there is no MR for this task

Key for the "Task Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but ALS has evaluated results & progress is clearly on track

1. Operational/User Support Items Completed During C1 2008

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.


2. Commitments

The default/unsorted state reflects priority order for this cycle.

Project Task Info/MR Lead Sponsor,Team Notes MR Status Task Status
Dynamic Scheduling Dynamic Scheduling Support Dynamic Web MarkClark KarenONeil, MikeMcCarty, EricSessoms   N/A ok
Dynamic Scheduling Handle Fixed and Windowed Sessions ModificationRequest4C807 MarkClark KarenONeil, MikeMcCarty, EricSessoms Released as part of 0.3 DONE DONE
Dynamic Scheduling Long-Term Probability Generation ModificationRequest3C108 MarkClark KarenONeil, MikeMcCarty, EricSessoms Released as part of 0.3 DONE DONE
Dynamic Scheduling Create, Read, Update, and Delete ModificationRequest4C108 MarkClark KarenONeil, MikeMcCarty, EricSessoms Waiting for statistics code for statistics.
Release as part of 0.4
MOVED TO... PICK
Dynamic Scheduling Back Log Project Database Import ModificationRequest8C108 MikeMcCarty KarenONeil, MarkClark, EricSessoms We have received an acsii file dump from Carl's database and are working on the database import. The file dump did not contain source information, however Carl is working on getting this out of his database.
Waiting for initial sponsor approval.
REFACTOR  
Dynamic Scheduling Device Availability ModificationRequest9C108 MikeMcCarty KarenONeil, MarkClark, EricSessoms Running integration server for sponsor testing. Once we get sponsor approval we'll release version 0.5. MOVED TO... PICK
PTCS General PTCS Support N/A RichardPrestage, JohnFord JoeBrandt, RonGrider   N/A ok
PTCS Add DIO interface to Linux Holography Manager ModificationRequest12C507 RonGrider ToddHunter, JohnFord, PeteWhiteis Developing realtime tasks to capture data synchronous with ISR and send to manager, as well as receive data from manager and push it out to parallel card. Implementing code in existing Holography manager to interface with prototype realtime tasks. PICK  
PTCS Selecting "Gold Standard" sources for AutoPeak(Focus) ModificationRequest2C807 RonGrider FrankGhigo Patched into release 7.7 Friday, Jan 25. DONE DONE
PTCS Out-Of-Focus Holography Software Revival Get B Nikolic's OOF code running again on-site RonGrider ToddHunter Reading OOF system memos as background for upcoming software modifications to OOF system. Supported meeting to discuss application of OOF software to MUSTANG data obtained two weeks ago. N/A ok
PTCS Improve GFM's and PrePoint's processing of CCB peak/focus data. ModificationRequest2C707 RonGrider FrankGhigo   REFACTOR ok
PTCS Improve GFM's processing of peak/focus scans using the DCR with the KA-band receiver. ModificationRequest9C507 RonGrider FrankGhigo   REFACTOR ok
PTCS Modify Peak Finding Algorithm for Pointing/Focus Code ModificationRequest4C207 RonGrider FrankGhigo, JoeBrandt FrankGhigo and ToddHunter have settled on GaussianFilter as preferred method. However, since this approach changes the resultant pointing offset values, deployment of the selected approach will be postponed until after the new pointing model is implemented this summer (ModificationRequest1C407).
Deployment on HOLD - confirmed with ToddHunter 29 Nov 2007.
PICK ok
PTCS Active Surface Rework Needs MR MelindaMello JohnFord, PeteWhiteis     ok
PTCS Analysis of Trajectory Generation Problems TrajectoryAnalysis JoeBrandt JohnFord, RonGrider Investigating bug in Don's trajectory code, which causes a velocity overshoot in trajectories. N/A ok
PTCS Find/Fix Command Stream Glitches add link to analysis or eventual MR JoeBrandt JohnFord, RonGrider   REFACTOR ok
PTCS CCU Servo Interlock Update ModificationRequest03C042007 JoeBrandt JohnFord, TimWeadon Resolved issues from last test. Plan to begin sponsor testing on Friday. ALERT! ok
PTCS Create Pyrgeometer Manager ModificationRequest2C207 JoeBrandt JohnFord, RonGrider   REFACTOR ok
PennArrayReceiver General Mustang Support N/A MelindaMello BrianMason, RamonCreager, PaulMarganian, MarkWhitehead   N/A ok
PennArrayReceiver Mustang Meta-MR MasterMustangManagerMr MelindaMello BrianMason, RamonCreager, PaulMarganian MJM:1.31.2008: Tested and committed code changes for dynamic sizing of publisher structs.
PRM:2.14.2008: Tested, tested, tested this week. Found a number of subtle bugs. Brian can now bring up the Manager and tune the system from a script. Mostly what remains is to merge our sandboxes. Nothing on MRs below represents no new significant work done.
RC - 2008/02/07: Installed GPIB support on 2.6 hosts using 'linux-gpib' driver package. Modified HouseKeeping on spider for use with the new gpib driver & tested successfully.
REFACTOR ALERT!
PennArrayReceiver Spider Tests YGORMgrSpiderTestReports MelindaMello BrianMason, RamonCreager, PaulMarganian MJM: 1.31.08 Receiver was warm most of the week which precluded testing.
N/A ok
PennArrayReceiver PCI Initialization ModificationRequest3C607 MelindaMello BrianMason, RamonCreager, PaulMarganian PRM:2.14.2008: Tested, tested, tested this week. Found a number of subtle bugs. Brian can now bring up the Manager and tune the system from a script. Mostly what remains is to merge our sandboxes. REFACTOR  
PennArrayReceiver Mustang Crate Control ModificationRequest16C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian   ALERT!  
PennArrayReceiver Mustang Tower Control ModificationRequest14C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian   PICK  
PennArrayReceiver Mustang FITS Writer ModificationRequest18C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian   MOVED TO... PICK
PennArrayReceiver Parser   MelindaMello BrianMason, RamonCreager, PaulMarganian      
PennArrayReceiver High level parameters.
ModificationRequest1C108 MelindaMello BrianMason, RamonCreager, PaulMarganian RC-2008/02/14: Renamed the parameters; all HL parameters are prefixed with the letters hl. Solved Device Explorer ambiguity problem. Added Tower HL parameters. ALERT! MOVED TO...
PennArrayReceiver Manager startup ModificationRequest8C807 MelindaMello BrianMason, RamonCreager, PaulMarganian MJM 1.31.2008 sponsor approved MR. Coding has started and is progressing nicely. I have a question outsstanding with the sponsor concerning when he wants the config file re-read in the system.
REFACTOR  
PennArrayReceiver Crate Command Monitoring ModificationRequest3C807 MelindaMello BrianMason, RamonCreager, PaulMarganian   DONE DONE
PennArrayReceiver Data Monitoring ModificationRequest2C108 MelindaMello BrianMason, RamonCreager, PaulMarganian MR Started REFACTOR  
PennArrayReceiver Collect Detector Bias Curves ModificationRequest6C807 MelindaMello BrianMason, RamonCreager, PaulMarganian   REFACTOR  
PennArrayReceiver Data File Stream Upgrade ModificationRequest1XC507? MelindaMello AmyShelton, RamonCreager, PaulMarganian   REFACTOR ALERT!
KFPA Conceptual Software Design for Data Handling of KFPA KFPA Data Pipeline Design BobGarwood StevenWhite, AmyShelton   N/A ok
Cicada GUPPI: General Support N/A RonDuPlain JohnFord, AmyShelton     DONE
Cicada GPU R&D Presentation1, Presentation2 JoeBrandt JohnFord, RonDuPlain   N/A ok
Cicada Conceptual Design and Very-Expert-User Interface of GUPPI Software ModificationRequest6C108 RonDuPlain JohnFord, AmyShelton MR has sponsor approval; implementing DONE ok
RFI Known Sources Develop Project Plan RfiDataBase LihongYao CarlaBeaudet, Jules Harnett, AmyShelton RFI GUI design phase (II). N/A ok
RFI Known Sources Software Design RfiDocs LihongYao CarlaBeaudet, Jules Harnett, AmyShelton Have been spending time on SW release 8.1 integration test this week. Will focus on finishing the toy-model GUI form design next week. N/A ok
Data Reduction Evaluate GBT Data Handling Status & Future Options Work in Progress BobGarwood AmyShelton   N/A ok
Software CM&E Incrementing the Project Session Number ModificationRequest5C807 AmyShelton FrankGhigo   DONE DONE
Software CM&E IF Manager: Adding Two Backends for Phoenix ModificationRequest7C807 MarkClark FrankGhigo   DONE DONE
Software CM&E Script to Support Antenna Axis Rate Changes ModificationRequest7C108 JoeBrandt BobAnderson   DONE DONE
Integration Testing Release 8.1 SoftwareRelease81 RonGrider, LihongYao   Released 12 Feb 2008 N/A DONE


3. CM&E

Description Tests Submitter Notes Status
lpc transfer failures Occurs asynchronously, I know of no tests or means to cause the failure. MarkClark    
handling user catalog errors user/CatalogTest.testConstructors MarkClark    
Bug in Options dialog of GFM Start GFM. Open the Options dialog - remember all the default values. Dismiss it. Open the Options dialog. Check to see that the default values are still the same. AmyShelton Some observers complained that GFM was changing their processing options on them unasked when they interacted with the Options dialog. Found bug and fixed.  
Disallow execution of Scheduling Blocks when GBT not in 'Ready' state Place Scan Coordinator in state other than 'Ready' (e.g. Running) and try to submit a scheduling block via turtle (astrid). You should get a red warning message and no scheduling blocks should be allowed to execute. A green message will appear when the Scan Coordiantor state returns to 'Ready' and scheduling block execution should resume. AmyShelton This bug fix was introduced when an observer submitted a scheduling block when the Scan Coordinator was in the 'Aborting' state, which caused all kinds of issues with their observing that unfortunately went unnoticed.  
Switchover SCU to prima No specific tests required. JoeBrandt SCU now booting from prima. Documentation in Knowledge wiki updated.  

Topic PlanOfRecordC12008 . { Edit | Attach | Ref-By | Printable | Diffs | r1.91 | > | r1.90 | > | r1.89 | More }
Revision r1.91 - 05 Mar 2008 - 15:37 GMT - AmyShelton Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.