Software Plan of Record

Cycle 2 2005 (February 14 - March 31, 2005)

Weeks

  • Week 1 2/14 - 2/18
  • Week 2 2/21 - 2/25 (Monday Holiday)
  • Week 3 2/28 - 3/4
  • Week 4 3/7 - 3/11
  • Week 5 3/14 - 3/18 (Friday Holiday)
  • Week 6 3/21 - 3/25
  • Week 7 3/28 - 3/31

M&Cv5.2 Release - TBD around March 31, 2005

Who's in the Box?

  • PTCS - 100% Amy, 50% Joe
  • Penn Array - 50% Melinda
  • Data - 100% Paul, 50% Jim, 75% Bob
  • CM&E - 100% Ray, 100% Mark, 50% Joe, 50% Melinda
  • Science - 25% Bob, 50% Jim
  • Integration Tests - Ray

Key for the "Status" column:

1. Operational/Scientific Support Items Completed During C2 2005

2. Commitments

Project TASK MR Sponsor Lead Checker Notes Status
DataHandlingImprovements Work towards 5/30/2005 release as per project plan N/A RonMaddalena BobGarwood JimBraatz    
DataHandlingImprovements Work towards IDL deployment issues as specified in project plan N/A NicoleRadziwill PaulMarganian NicoleRadziwill See Status  
DataHandlingImprovements Resolve sdfits known issues as per project plan ModificationRequest6C205 RonMaddalena PaulMarganian NicoleRadziwill 11 of 13 issues coded and tested. SP issues not supported. See status DONE
DataHandlingImprovements Add SDFITS epoch keyword N/A KarenONeil PaulMarganian MelindaMello Tested by Tim Robishaw DONE
DataHandlingImprovements CLASS update for Gary Fuller N/A JimBraatz PaulMarganian JimBraatz done DONE
PennArrayReceiver Penn Array software project charter N/A BrianMason MelindaMello NicoleRadziwill Complete DONE
PennArrayReceiver Complete MR for M&C/IRC interfaces ModificationRequest5C105, ModificationRequest8C105 BrianMason MelindaMello NicoleRadziwill Complete DONE
PennArrayReceiver Write MR for Pennarray FITS skeleton ModificationRequest1C205? BrianMason MelindaMello NicoleRadziwill I am still investigating the IRC mechanisms that will enable me to specify the task. I don't want to write the MR incorrectly and commit myself to the wrong requirements or design.  
PTCS Put together order for equipment for vortex replacement. N/A NicoleRadziwill JoeBrandt NicoleRadziwill Purchase order submitted. DONE
PTCS Antenna trajectory data analysis investigation. Deliverable: Investigation results. AntennaTrajectorySubproject RichardPrestage JoeBrandt MelindaMello Document out for review.  
PTCS GFM items (40, 47, 48, 49, 50, 21, 22, 30, 25) from GbtFitsMonitorContinuumRequests See GbtFitsMonitorContinuumRequests RichardPrestage AmyShelton MarkClark Improvements to Item 40 as a result of sponsor testing are being made in ashelton's sandbox. Items 22, 30, 47, 49, & 50 are sponsor tested and in gfm-test. Item 48 has been dropped for this cycle because it is not as important as once thought. Items 21 and 25 will not be completed this cycle.  
PTCS Serve as a consultant to Dana to advise him in the upgrade/refactoring of PTCS observing scripts N/A RichardPrestage AmyShelton MarkClark   DONE
PTCS Create repository for PTCS software/scripts N/A RichardPrestage AmyShelton MarkClark Bojan is not ready for this yet. DONE
PTCS Active Surface Manager Upgrades: (1) Calculate Zernike polynomials as a function of elevation, (2) Replace F. Schwab's Zernike calculation algorithm with Bojan's ModificationRequest2C205?, ModificationRequest3C205? RichardPrestage AmyShelton MelindaMello This item was dropped. DONE
SoftwareCME Decouple LEDA from IF Manager. See IFManagerWorkOverview for more information. N/A NicoleRadziwill MarkClark AmyShelton   DONE
SoftwareCME IF Manager does not list cabling file devices PO#867 RonMaddalena MarkClark AmyShelton   DONE
SoftwareCME IF Manager should not report errors for non-selected backends PO#849 RichardPrestage MarkClark AmyShelton started, but tabled for this cycle  
SoftwareCME Investigate cfitsio memory leak in SDFITS SDFITSMemoryLeakInvestigationResults NicoleRadziwill MelindaMello PaulMarganian Completed Investigation SEE: SDFITSMemoryLeakInvestigationResults DONE
SoftwareCME Antenna should consider Beam C and 1 identical for single-beam receivers ModificationRequest9C205 RonMaddalena JoeBrandt RamonCreager Code and database changes on simulator. Testing.  
SoftwareCME Antenna should handle PF focus positions the same as for Gregorian. ModificationRequest10C205 RonMaddalena JoeBrandt RamonCreager I discussed this with Ron, and I think this task may be delayed.  
SoftwareCME Rate mismatch fault check in servo controller needs to detect number of motors faulted. (Lower priority) ModificationRequest11C205 RichardPrestage JoeBrandt RamonCreager Not started.  
SoftwareCME Add simplified Peak and Focus to Turtle ModificationRequest4C205 KarenONeil MarkClark AmyShelton   DONE
SoftwareCME Linux Migration according to project plan (DCR/LO1 over 2 cycles; vortex by mid April) N/A JohnFord RamonCreager JoeBrandt The test DCR seems to work, but troubles with getting the right timing signals (1PPS and 10MHz with the correct relationship) has beem problematic. We resolved to install the test DCR in the equipment room and just use the site timing signals. DcrLinuxDesign  
SoftwareCME Grail support for coop student project N/A RonDuPlain RamonCreager RonDuPlain Increased number of threads Grail can launch; added pre-allocated thread pool to service SOAP input DONE
SoftwareCME Ka Band configuration addition ModificationRequest7C205 FrankGhigo MelindaMello   Completed - patched in to 5.1 DONE
SoftwareCME Go from mc version of aips++ to glish standalone N/A NicoleRadziwill BobGarwood ???    
SoftwareCME Integration Tests PerformIntegrationTests MarkClark RamonCreager N/A See SddCalendar for dates.  

3. Background Tasks:

Project TASK MR Sponsor Lead Status/Notes Done
SoftwareCME Add addtl parameters/IF path info to gbtstatus. Target 5/15/2005. N/A ??? MelindaMello    

4. Tasks that will not be completed this cycle:

Project TASK MR Sponsor Lead Status/Notes Done

5. Future Things to Think About

Topic PlanOfRecordC22005 . { Edit | Attach | Ref-By | Printable | Diffs | r1.59 | > | r1.58 | > | r1.57 | More }