Software Plan of Record

Cycle 3 2007 (April 1 - May 15, 2007)


Weeks

  • Week 1 4/2 - 4/6
  • Week 2 4/9 - 4/13
  • Week 3 4/16 - 4/20
  • Week 4 4/23 - 4/27
  • Week 5 4/30 - 5/4
  • Week 6 5/7 - 5/11
  • Week 7 5/14 - 5/15

Release date for M&C/Sparrow: May 15, 2007

Who's in the Box?
  • Amy - 60% Management, 10% Business Office System, 10% Dynamic Scheduling, 20% Strategic Planning
  • Bob - 10% Support, 90% Data Reduction
  • Joe - 10% Support, 90% PTCS
  • Mark - 10% Support, 80% Dynamic Scheduling, 10% Leave
  • Melinda - 10% Support, 70% Dynamic Scheduling, 20% Integration Testing
  • Mike - 10% Support, 70% Business Office System, 20% Dynamic Scheduling
  • Paul - 10% Support, 40% Dynamic Scheduling, 40% Business Office System, 10% Vacation
  • Ray - 10% Support, 5% R&D, 65% Business Office System, 20% Vacation
  • Ron - 10% Support, 80% PTCS, 10% Vacation

Use the order as a guideline in order to determine the relative priority of jobs.

Key for the "Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but ALS has evaluated results & progress is clearly on track

1. Operational/User Support Items Completed During C3 2007

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.


2. Commitments

The default/unsorted state reflects priority order for this cycle.

Task Info/MR Lead Sponsor,Team Notes Status
Dynamic Scheduling Software Dynamic Web AmyShelton MelindaMello, PaulMarganian, MarkClark, MikeMcCarty We have a project page that displays the project and project account information in a form and saves changes made within the form. Most of the fields are properly validated. I think we both feel that having a non editable form that has the same "look and feel" as the editable one is a much better solution for the user. The user could view and then "choose" to edit the data.
We have agreed on a structure within the turbogears framework for our custom widgets and controllers.
MJM thinks we made good progress this week and are on a roll. smile
 
Evaluate GBT Data Handling Status & Future Options Work in Progress BobGarwood AmyShelton    
Complete Documentation of Cross-Polarization Changes Work in Progress BobGarwood KarenONeil    
General PTCS Support N/A RichardPrestage, JohnFord JoeBrandt, RonGrider [JB] Updated and deployed log_collator into integration for Frank to use/test.
[RG] Debugged PrePoint Focus problem with 'dynamic' flag.
[JB,RG] Supported telecon for new pointing model.
 
Update Pointing/Focus code to Handle Old Data Sets ModificationRequest3C207 RonGrider FrankGhigo, JoeBrandt In sponsor testing. PICK
Modify Peak Finding Algorithm for Pointing/Focus Code ModificationRequest4C207 RonGrider FrankGhigo, JoeBrandt MR approved. Investigating convolution approach.
[ This is a modification affecting all of GFM, not just for Pointing/Focus code. ]
 
Fix Inclinometer Data Collection Problems ModificationRequest1C207 JoeBrandt JohnFord, RonGrider MR being reviewed by CCC.  
Fix Accelerometer Timestamping/Data Collection ModificationRequest2C307 JoeBrandt JohnFord MR being reviewed by CCC.  
Analysis of Trajectory Generation Problems add link to analysis JoeBrandt JohnFord, RonGrider Continued work on the 'new' filter style preprocessor. Attended servo review wrote up a list of issues and discussed them with Tim.  
Find/Fix Command Stream Glitches add link to analysis or eventual MR JoeBrandt JohnFord, RonGrider    
SCCU Servo Changes ModificationRequest1C806 JoeBrandt JohnFord Although the code is working, we have found that commanded velocity spikes occur during normal observing. To date this has not been a problem since the hardware filters out the spikes. However with the hardware modifications coupled with this MR, the spikes will corrupt the intended operation of the friction compensation. John is working on modeling a different methods of deriving the velocity commands.  
Port Holography Manager to Linux ModificationRequest1C307   JohnFord Port Holography backend to Linux and replace the MCB with a parallel interface  
Create Pyrgeometer Manager ModificationRequest2C207 JoeBrandt JohnFord, RonGrider No Progress.  
Complete Pointing Processing Description Memo Should become PTCS/PN/23 - Add link to document JoeBrandt RichardPrestage No Progress.  
Business Office System BusinessOfficeSystem MikeMcCarty AmyShelton, RamonCreager, PaulMarganian See MR stati and To Do List
 
BOS - Meta MR linking other MRs and other issues ModificationRequest9C107 MikeMcCarty AmyShelton, RamonCreager, PaulMarganian Automated new user account setup is complete. Working on functionality to change passwords.  
BOS - User Management ModificationRequest5C107 MikeMcCarty AmyShelton, RamonCreager, PaulMarganian Writing unit tests.
Released in version 0.1 for Green Bank sponsor testing!
 
BOS - Database Migration ModificationRequest6C107 MikeMcCarty AmyShelton, RamonCreager, PaulMarganian Carl has agreed to help us by dumping the BARS tables we need to a text file.  
BOS - Reservation Management ModificationRequest7C107 MikeMcCarty AmyShelton, RamonCreager, PaulMarganian 100% of core requirements completed!
89 unit tests.
Released in version 0.1 for Green Bank sponsor testing!
 
BOS - Document Management ModificationRequest8C107 MikeMcCarty AmyShelton, RamonCreager, PaulMarganian Requirments Complete! >70 unit tests! Performing tests with different browsers before submitting to Sponsors for pre-testing preview. Also see To Do List  
Future Pulsar Backend FPGA Group Website RamonCreager RandyMcCullough, AmyShelton    
Integration Testing add link to testing page(s) here MelindaMello all    
Add encoder velocity to PrePoint output ModificationRequest3C307 RonGrider FrankGhigo In sponsor testing. PICK
Quadrant Detector Timestamp issues ModificationRequest5C307 JoeBrandt JohnFord New.  


3. CM&E

Description Tests Submitter Notes Status
PrePoint application doesn't apply '-d(ynamic)' flag correctly to Focus scans. Executed PrePoint application on TPTCSPNT_060818 project:
prepoint TPTCSPNT_060818 -h /home/archive/test-data/tape-0003/ -a -d -v
Compared output values for Focus scans of this run with saved output data from one month ago which contains correct values confirmed against old glish code.
RonGrider Error reported by FrankGhigo. Corrected PrePointExecutor.py file, Frank confirms the output values are now correct when using dynamic flag for focus scans.
Patched into Release 7.2
DONE
TimeStamp Library fix Run the unit test in the TimeStamp directory. JoeBrandt The TimeStamp library had a bug in the HrsMinSec(int, int, double) method. (Seconds were rounded in error.) DONE
emailNotifier multiple recipients bug fix Use emailNotifier to send a email to multiple recipients (using a list) and verify that the "to" email addresses appear correctly.
'email1@nrao.edu', 'email2@nrao.edu'
MikeMcCarty I've copied emailNotifier.py to sparrow/api/util/src
This includes a bug fix where the "To" header was format incorrectly.
['email1@nrao.edu', 'email2@nrao.edu']
DONE

4. Background Tasks

Task Info/MR Lead Sponsor,Team Notes Status
Fix Faulty Self-Test in Spectrometer ModificationRequest6C406 RamonCreager RandyMcCullough    
Correct boom deploy/retract under M&C control BoomDeployRetractProblem? JasonRay JoeBrandt, MelindaMello    
GBTIDL Autoflagger ModificationRequest2C506 BobGarwood RonMaddalena    
Investigate imaging for GBTIDL add link to investigation results here BobGarwood RonMaddalena    

5. Miscellaneous

Topic PlanOfRecordC32007 . { Edit | Attach | Ref-By | Printable | Diffs | r1.57 | > | r1.56 | > | r1.55 | More }
Revision r1.57 - 01 Aug 2007 - 20:07 GMT - AmyShelton Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.