Software Plan of Record

Cycle 7 2007 (October 1 - November 15, 2007)


Weeks

  • Week 1 10/1 - 10/5
  • Week 2 10/8 - 10/12
  • Week 3 10/15 - 10/19
  • Week 4 10/22 - 10/26
  • Week 5 10/29 - 11/2
  • Week 6 11/5 - 11/9
  • Week 7 11/12 - 11/15

Release date for M&C/Sparrow: November, 2007

Who's in the Box?
  • Amy - 55% Management, 15% Mustang, 10% Dynamic Scheduling, 20% Leave
  • Bob - 10% Support, 80% Data Reduction, 10% Leave
  • Joe - 10% Support, 60% PTCS, 10% R&D, 20% Leave
  • Lihong - 75% RFI, 25% Research
  • Mark - 10% Support, 70% Dynamic Scheduling, 10% Integration Testing, 10% Leave
  • Melinda - 10% Support, 75% Mustang, 5% PTCS, 10% Leave
  • Mike - 80% Dynamic Scheduling, 10% Business Office System, 10% Leave
  • Paul - 10% Support, 80% Mustang, 10% Leave
  • Ray - 10% Support, 80% Mustang, 10% Leave
  • Ron G. - 90% PTCS, 10% Leave
  • Ron D. - 25% Cicada (partnership with e2e division)

Use the order as a guideline in order to determine the relative priority of jobs.

Key for the "Task Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but ALS has evaluated results & progress is clearly on track

Key for the "MR Status" column:

  • DONE (%Y%) means the MR has final sponsor sign-off
  • MOVED TO... (%M%) means the MR is awaiting final sponsor sign-off
  • PICK (%S%) means the MR is being implemented (has CCC approval)
  • ALERT! (%X%) means the MR needs CCC approval
  • REFACTOR (%P%) means the MR is either being written, checked, or needs initial sponsor approval
  • N/A means there is no MR for this task

1. Operational/User Support Items Completed During C7 2007

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.


2. Commitments

The default/unsorted state reflects priority order for this cycle.

Project Task Info/MR Lead Sponsor,Team Notes MR Status Task Status
Dynamic Scheduling Create SRS for PST Administrative Functionality create Word document MikeMcCarty NicoleRadziwill, AmyShelton, CarlBignell Carl's document sent to Nicole. N/A DONE
Dynamic Scheduling Dynamic Scheduling Support Dynamic Web MarkClark KarenONeil, MikeMcCarty, EricSessoms   N/A DONE
Dynamic Scheduling Create Simplest End-to-End System ModificationRequest4C707 MarkClark KarenONeil, MikeMcCarty, EricSessoms We are offering to DSS testers an initial system which displays a web page for both manual and automatic scheduling of "open" sessions using simulated data as generated from DanaBalser test program. The system implements half of the possible scoring factors, but all of the weather scoring based on historical data from 2006. MOVED TO...  
Data Reduction Evaluate GBT Data Handling Status & Future Options Work in Progress BobGarwood AmyShelton Focusing on K-band FPA. N/A ok
KFPA Conceptual Software Design for Data Handling of KFPA design doc here BobGarwood StevenWhite, AmyShelton Organizing workshop to shape design. N/A ok
KFPA Workshop Workshop Wiki Page BobGarwood StevenWhite, AmyShelton Details being worked on. Everything should be in place by the end of next week. N/A ok
PTCS General PTCS Support N/A RichardPrestage, JohnFord JoeBrandt, RonGrider   N/A DONE
PTCS Add DIO interface to Linux Holography Manager ModificationRequest12C507 RonGrider JoeBrandt, ToddHunter, JohnFord MR approved by CCC. Reviewing documentation for new interface card, designing calling sequence to new card, then will design corresponding software module. Researching changes required to host on RTAI rather than plain Linux platform. PICK  
PTCS Out-Of-Focus Holography Software Revival Get B Nikolic's OOF code running again on-site RonGrider ToddHunter Moved working codebase from ToddHunter laptop to PTCS group location. Successfully executed Stage 3 OOF processing on existing OOF data (TPTCSPNT_050317). N/A  
PTCS Improve GFM's and prepoint's processing of CCB peak/focus data. ModificationRequest2C707 RonGrider FrankGhigo GFM should gracefully handle CCB data; PrePoint should output fits at all CCB frequency bands.
Identified changes to be made in PrePoint supporting this MR as part of 01 Nov operational support task.
REFACTOR  
PTCS Improve GFM's processing of peak/focus scans using the DCR with the KA-band receiver. ModificationRequest9C507 RonGrider FrankGhigo GFM should properly calibrate KA-band data taken with the DCR. REFACTOR  
PTCS Modify Peak Finding Algorithm for Pointing/Focus Code ModificationRequest4C207 RonGrider FrankGhigo, JoeBrandt FrankGhigo and ToddHunter have settled on GaussianFilter as preferred method. However, since this approach changes the resultant pointing offset values, deployment of the selected approach will be postponed until after the new pointing model is implemented this summer (ModificationRequest1C407).
Deployment on HOLD.
PICK  
PTCS Analysis of Trajectory Generation Problems TrajectoryAnalysis JoeBrandt JohnFord, RonGrider Putting together a document for a meeting late next week. N/A  
PTCS Find/Fix Command Stream Glitches add link to analysis or eventual MR JoeBrandt JohnFord, RonGrider   REFACTOR  
PTCS SCCU Servo Changes ModificationRequest1C806 JoeBrandt JohnFord Software released 12/11/07. DONE DONE
PTCS CCU Servo Interlock Update ModificationRequest03C042007 JoeBrandt JohnFord, TimWeadon Created and installed ROMS. Sponsor testing the software changes Thurs/Fri of this week. ALERT!  
PTCS Create Pyrgeometer Manager ModificationRequest2C207 JoeBrandt JohnFord, RonGrider Not started. REFACTOR ok
PennArrayReceiver General Mustang Support N/A MelindaMello BrianMason, RamonCreager, PaulMarganian   N/A DONE
PennArrayReceiver Mustang Meta-MR MasterMustangManagerMr MelindaMello BrianMason, RamonCreager, PaulMarganian MJM: Fixed bugs in parsing and fits routines.
Verified interface card parsing, but need a signal generator to finish testing.
My next job is finishing the coadd MR and coding it.
PRM: added intfc card data. All Publishing should be done! Hardly any work done this week due to Holiday and WVU Open House.
RC: Finished studying IRC time stamping and am implementing Time Stamping in the manager.
REFACTOR ALERT!
PennArrayReceiver Data File Stream Upgrade ModificationRequest1XC507? MelindaMello AmyShelton, RamonCreager, PaulMarganian   REFACTOR ALERT!
PennArrayReceiver Mustang Crate Control ModificationRequest16C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian MR Approved. Code passes internal tests. Commanding works with integrated tests. Working on startup issues with Brian. No recent work. Must fix bug with shifting commands that need to be offset. REFACTOR  
PennArrayReceiver Mustang Tower Control ModificationRequest14C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian MR Approved. Code passes internal tests. Commanding works with integrated tests. Working on startup issues with Brian. No recent work. PICK  
PennArrayReceiver Mustang FITS Writer ModificationRequest18C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian MR approved. FITS files being written over NSF for non-coadded data!!! Resolving system-wide issues regarding command and data offsets. Fixed problems encountered when LUT variables were changed. Now that all data is getting into FITS (including Intfc Card), need to do systematic tests, logging details about params with FITS file results, etc. REFACTOR  
PennArrayReceiver Parser   MelindaMello BrianMason, RamonCreager, PaulMarganian Adding timestamps to the data. RC N/A  
KaBandReceiver Indicate Subreflector Position in Data ModificationRequest4C507 BobGarwood RonMaddalena, MarkClark, MikeMcCarty   DONE DONE
KaBandReceiver Merge Zpectrometer code branch into main trunk ModificationRequest15C507 BobGarwood KarenONeil, AndrewBaker   DONE DONE
Cicada GPU R&D Presentation1, Presentation2 JoeBrandt JohnFord, RonDuPlain Cluster in place.
N/A ok
Cicada Software Support N/A RonDuPlain JohnFord, AmyShelton Working on design for backend control software. N/A DONE
RFI Known Sources Develop Project Plan RfiDataBase LihongYao CarlaBeaudet, Jules Harnett, AmyShelton RFI project proposal is looking good. Separated User Interfaces for RFI database registration/management and astronomers' report may be necessary. The key phase of the project is to develop a better and flexiable RFI database structure. N/A  
RFI Known Sources Software Design RfiDocs LihongYao CarlaBeaudet, Jules Harnett, AmyShelton Continue working on RFI database design and development. Will have a database schema done next week. N/A  
Zpectrometer Zpectrometer Commissioning Support ModificationRequest1C707 RamonCreager KarenONeil Made numerous small modifications as detailed in MR to the Zpectrometer Manager to accommodate the needs of the Zpectrometer Commissioning activities MOVED TO...  
Software CM&E Integration Testing SoftwareReportCentral AmyShelton MarkClark   N/A DONE
Continuing Education Attend Project Management Training N/A JoeBrandt, MarkClark, RamonCreager, MikeMcCarty   Attended 10/2,10/3 N/A DONE
Continuing Education Attend AstroGPU and SuperComputing 2007 N/A JoeBrandt, AmyShelton     N/A DONE
PTCS Add fields to PrePoint output. ModificationRequest5C707 RonGrider FrankGhigo Implemented, awaiting sponsor (offline) testing. MOVED TO... PICK
PennArrayReceiver CoAddition? MR ModificationRequest6C707 MelindaMello BrianMason Haven't heard back from sponsor. I'm immplementing the basic co addition algorithm which shouldn't require rework due to sponsor changes. REFACTOR  


3. CM&E

Description Tests Submitter Notes Status
lpc transfer failures Occurs asynchronously, I know of no tests or means to cause the failure. MarkClark I have added a log mechanism to gfm targeting the failure. ALERT!
handling user catalog errors user/CatalogTest.testConstructors MarkClark Development has started. ALERT!

Topic PlanOfRecordC72007 . { Edit | Attach | Ref-By | Printable | Diffs | r1.77 | > | r1.76 | > | r1.75 | More }
Revision r1.77 - 11 Dec 2007 - 13:06 GMT - JoeBrandt Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.