Cycle 8 2006 (November 16 - December 31, 2006)


Weeks

  • Week 1 11/16 - 11/17
  • Week 2 11/20 - 11/25
  • Week 3 11/27 - 12/01
  • Week 4 12/03 - 12/08
  • Week 5 12/10 - 12/15
  • Week 6 12/17 - 12/22
  • Week 7 12/25 - 12/29

Release date for M&C/Sparrow: February 15, 2007

Who's in the Box?
  • Amy - 70% Management, 30% Vacation
  • Bob - 10% Support, 10% Zpectrometer Support, 20% Spectrometer, 30% e2e, 30% Vacation
  • Joe - 10% Support, 10% PTCS, 40% CM&E, 40% Vacation
  • Mark - 10% Support, 45% Dynamic Scheduling, 25% EVLA, 20% Vacation
  • Melinda - 10% Support, 60% Dynamic Scheduling, 10% Balancing, 20% Vacation
  • Mike - 10% Support, 30% Business Office System, 25% Scheduling, 10% Documentation, 25% Vacation
  • Paul - 10% Support, 50% Dynamic Scheduling, 10% Business Office System, 10% e2e, 20% Vacation
  • Ray - 10% Support, 20% Zpectrometer, 30% CM&E, 40% Vacation
  • Ron - 10% Support, 60% PTCS, 10% Documentation, 20% Vacation

Use the order as a guideline in order to determine the relative priority of jobs.

Key for the "Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but ALS has evaluated results & progress is clearly on track

1. Operational/Scientific Support Items Completed During C8 2006

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.


2. Commitments

The default/unsorted state reflects priority order for this cycle.

Task Info/MR Lead Sponsor,Team Notes Status
Zpectrometer Commissioning Support N/A RamonCreager, BobGarwood KarenONeil    
Evolve Dynamic Scheduling Proposal Dynamic Web KarenONeil KarenONeil, MelindaMello, PaulMarganian, MarkClark Continued work on testcases in database. Done examining Weather: predicted winds vs. actual winds.
Generated data for the DSS Sim database and implemented selection rule based on new wind criteria. Wrote a wiki page on whats been implemented so far. Meetings..Meetings..Meetings.
Main.MelindaMello
We have begun the Object-Oriented Analysis which attempts to capture
the requirements as Object/Dynamic/Functinal Models. Progress will be tracked at WebHome. An initial object diagram exists. MarkClark
Initial version of software suite completed. PaulMarganian - placed Tsys predictions in database, confirmed wind speed profiles and weather station info.
 
Modify SDFITS and aips++ to correctly process Spectrometer cross-polarization data ModificationRequest2C706 BobGarwood BrianMason, KarenONeil, PaulMarganian This is done. I'll notify Robishaw so that he can test it out on his data. GFM works fine on this although I think we should change the Tsys calculation for xcorr data in the spectral line plug in.
Tim reports that it isn't correct, waiting on feedback as to what might be wrong.
 
SDFits Changes - Add target position and HIGH_CAL keywords to sdfits and other requested sdfits changes ModificationRequest3C706 BobGarwood KarenONeil, PaulMarganian Minor update to the MR after reflection on an e-mail from Robishaw (change in how the first 1024-lags will be used in x-corr case - checked but not fixed, just flagged if bad). Spent a lot of time tracking down historical COORDSYS usages - TRGTLONG and TRGTLAT now done.  
GBTIDL Changes necessary in support of related sdfits tool changes ModificationRequest8C706 BobGarwood KarenONeil, PaulMarganian    
Change scaling for the Autocorrelation Spectra in the Spectrometer ModificationRequest6C706 BobGarwood KarenONeil, PaulMarganian Done (except for documentation changes and release notes). Now in integration. GFM appears to work fine with these changes - note that because GFM displays total power values that these raw numbers are 2x larger than they were before these changes, as expected. Tim R. has verified that this is correct.  
Change GO fits file so that RA is in degrees ModificationRequest15C705 PaulMarganian KarenONeil, BobGarwood Code commited in CVS. Still must change GO FITS Documentation.  
Answer Questions Related to Track Model N/A JoeBrandt RichardPrestage Attended PTCS meetings.  
SCCU Servo Changes ModificationRequest1C806 JoeBrandt JohnFord MR updated and code ready for servo testing. Not yet signed.  
Upgrade PTCS Pointing Model Pre-Processing Software ModificationRequest5C706 RonGrider FrankGhigo, AmyShelton Enhancing peakdata module to become more complete prepoint application. Adjusting prepoint to use new code modules refactored earlier for this MR.
Updating prepoint's focus scan analysis / processing capabilities to the same level as peak scan capabilities.
 
General PTCS Support N/A N/A RichardPrestage, JohnFord Attended phase retrieval holography meetings with representatives from Goddard.  
Business Office System BusinessOfficeSystem PaulMarganian AmyShelton, MikeMcCarty After reviewing new 'cut & paste' method for entering info into PeopleSoft?, team is rewriting Project Charter, so we can resubmit idea to Bus. Office Management.
Main.MikeMcCarty attempt to simplify this method by using an HTML table instead of an Excel file, but PeopleSoft? did not paste the information into the cells correctly.
We're also still working on the Project Charter.
 
Assist CarlBignell in migrating from dbase to MySQL SchedulingSoftware MikeMcCarty CarlBignell The Scheduling Tools table on the VDBaseTools wiki has been completed. The Proposal Tools tables has been started.
No update.
 
Balancing Project - Project Charter Add link to charter here MelindaMello FrankGhigo Reviewed MRs and modified them with comments. Also provide FG with a list of 2 MRs that need to be written. One whould be written by me (SEcurity daemon) and the other one (IFRack) by the sponsor.  
Balancing Project - Get, Set, and Change Attenuators ModificationRequest8C505 MelindaMello FrankGhigo, RamonCreager    
Balancing Project - Converter Rack: Add Ability to Set Power Levels and to Balance to those Levels ModificationRequest4C505 MelindaMello FrankGhigo, RamonCreager    
Balancing Project - Change Spectrometer Warning Messages During Balance ModificationRequest9C505 MelindaMello FrankGhigo, RamonCreager    
Balancing Project - IF Rack: Change messages to indicate non-balance and non-linearity ModificationRequest10C505 MelindaMello FrankGhigo, RamonCreager    
Balancing Project - Multiple sampling for Balancing procedures to diminish RFI effects ModificationRequest11C505 MelindaMello FrankGhigo, RamonCreager    
E2E Common User Database PaulMarganian NicoleRadziwill, AmyShelton   For Details, see: https://wiki.nrao.edu/bin/view/Software/UserDatabaseSharedServicesDiscussion.
No progress since Oct. 23. It now appears that BOS v1.0 will not use this. How should we wrap up this work?
 
Participate in ALMA's Testing of CASA N/A BobGarwood NicoleRadziwill    
Attend EVLA Software Review N/A N/A MarkClark   DONE
Update Software Documentation SoftwareDocumentation? AmyShelton RonGrider, MikeMcCarty Reviewing updated M&C diagram. Starting software documentation "dashboard-like" wiki. Updated "level 0" notes (conf files, env vars, third party libs) for GFM, Turtle and other Astrid apps. Developing class-diagrams for these apps.
Discussion on document standards led to creating Project Charter template, see PcTemplate.
 
GFM not displaying proper frequency axis ModificationRequest2C806 PaulMarganian ? MR only lacks sequence diagram for design section, and Sponsor.  
Investigate & Fix Cause of Astrid Hang-ups ModificationRequest9C706 MarkClark JimBraatz, JoeBrandt Tested a preliminary 6.6.1 version, but found several problems. Items from first test are now resolved and will be re-tested 7 Dec. Test 07 Dec results
Still looking into cause of LPC/LFC zeroing. Ran into problem of hanging when going on-line (also seen by RonG). GFM appears to get into a loop refilling the first and second scan of the project when going on-line. Arg!
 


3. Refactored Code

Description Tests Submitter Notes Status
Scancoordinator core dump Fixed an issue where a string parameter of fixed size (scanLogEntry) was being copied from a smaller buffer. This caused a seg fault when the unmapped memory was accessed. JoeBrandt Merged into both integration and 6.6 source, but not yet patched into 6.6.  
Taskmaster core files Fixed Taskmaster to properly place core files into the cores directory. JoeBrandt Merged into both integration and 6.6 source, but not yet patched into 6.6.  
Misnamed FITS files Fixed the algorithm for computing device FITS filenames. Problem was seen with a starttime of 16:20:00.0 which was incorrectly computed as 16:19:00. JoeBrandt Updated into integration, but not 6.6. This will require a re-install of all FITS writing daemons.  

4. Background Tasks

Task Info/MR Lead Sponsor,Team Notes Status
Fix Faulty Self-Test in Spectrometer ModificationRequest6C406 RamonCreager RandyMcCullough    
Correct boom deploy/retract under M&C control BoomDeployRetractProblem? JasonRay JoeBrandt, MelindaMello    
GBTIDL Autoflagger ModificationRequest2C506 BobGarwood RonMaddalena Started.  
Investigate imaging for GBTIDL add link to investigation results here BobGarwood RonMaddalena    

5. Miscellaneous

Topic PlanOfRecordC82006 . { Edit | Attach | Ref-By | Printable | Diffs | r1.42 | > | r1.41 | > | r1.40 | More }
Revision r1.42 - 28 Dec 2006 - 20:38 GMT - JoeBrandt Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.