Software Plan of Record

Cycle 8 2007 (November 16 - December 31, 2007)


Weeks

  • Week 1 11/19 - 11/23
  • Week 2 11/26 - 11/30
  • Week 3 12/03 - 12/07
  • Week 4 12/10 - 12/14
  • Week 5 12/17 - 12/21
  • Week 6 12/24 - 12/28

Release date for M&C/Sparrow: February, 2008

Who's in the Box?
  • Amy - 55% Management, 15% Mustang, 10% Dynamic Scheduling, 20% Leave
  • Bob - 10% Support, 80% Data Reduction, 10% Leave
  • Joe - 10% Support, 60% PTCS, 10% R&D, 20% Leave
  • Lihong - 75% RFI, 25% Research
  • Mark - 10% Support, 70% Dynamic Scheduling, 20% Leave
  • Melinda - 10% Support, 75% Mustang, 5% PTCS, 10% Leave
  • Mike - 80% Dynamic Scheduling, 10% Business Office System, 10% Leave
  • Paul - 10% Support, 80% Mustang, 10% Leave
  • Ray - 10% Support, 80% Mustang, 10% Leave
  • Ron G. - 90% PTCS, 10% Leave
  • Ron D. - 25% Cicada (partnership with e2e division)

Use the order as a guideline in order to determine the relative priority of jobs.

Key for the "Task Status" column:

  • DONE (%Y%) means the task has been successfully completed
  • MOVED TO... (%M%) means the task has been completed and is awaiting integration tests
  • PICK (%S%) means the task has been completed and is awaiting sponsor tests
  • ALERT! (%X%) means the task will not be completed this cycle, but was expected to be completed
  • ok means that the task is not yet complete or ready for tests, but ALS has evaluated results & progress is clearly on track

Key for the "MR Status" column:

  • DONE (%Y%) means the MR has final sponsor sign-off
  • MOVED TO... (%M%) means the MR is awaiting final sponsor sign-off
  • PICK (%S%) means the MR is being implemented (has CCC approval)
  • ALERT! (%X%) means the MR needs CCC approval
  • REFACTOR (%P%) means the MR is either being written, checked, or needs initial sponsor approval
  • N/A means there is no MR for this task

1. Operational/User Support Items Completed During C8 2007

For each support item, please list the amount of effort involved as either: low, medium, or high. Guidelines for these rankings are as follows:

If multiple people are involved in an item, please list it only once. Effort estimates should reflect total time elapsed, i.e. how long did it take to fix the problem start to finish - not the sum total of each person's time.


2. Commitments

The default/unsorted state reflects priority order for this cycle.

Project Task Info/MR Lead Sponsor,Team Notes MR Status Task Status
Dynamic Scheduling Dynamic Scheduling Support Dynamic Web MarkClark KarenONeil, MikeMcCarty, EricSessoms   N/A  
Dynamic Scheduling Handle Fixed and Windowed Sessions ModificationRequest4C807 MarkClark KarenONeil, MikeMcCarty, EricSessoms Slipped one week to Dec 31, remaining work is completion of generation of simulated sessions and latencies in automatic scheduling of fixed and windowed sessions. ALERT!  
PTCS General PTCS Support N/A RichardPrestage, JohnFord JoeBrandt, RonGrider   N/A  
PTCS Add DIO interface to Linux Holography Manager ModificationRequest12C507 RonGrider JoeBrandt, ToddHunter, JohnFord Working on simple parallel port kernel module to get development environment properly configured. Supporting parallel port used on new DIO interface card. PICK  
PTCS Selecting "Gold Standard" sources for AutoPeak(Focus) ModificationRequest2C807 RonGrider FrankGhigo MR submitted to CCC. Implementation completed, will arrange for sponsor testing on simulator while waiting for CCC approval. ALERT! PICK
PTCS Out-Of-Focus Holography Software Revival Get B Nikolic's OOF code running again on-site RonGrider ToddHunter Code runs on site in manual mode. Will be examining second of three phases of data processing, to make it more automated, in short term. N/A  
PTCS Improve GFM's and PrePoint's processing of CCB peak/focus data. ModificationRequest2C707 RonGrider FrankGhigo   REFACTOR  
PTCS Improve GFM's processing of peak/focus scans using the DCR with the KA-band receiver. ModificationRequest9C507 RonGrider FrankGhigo   REFACTOR  
PTCS Modify Peak Finding Algorithm for Pointing/Focus Code ModificationRequest4C207 RonGrider FrankGhigo, JoeBrandt FrankGhigo and ToddHunter have settled on GaussianFilter as preferred method. However, since this approach changes the resultant pointing offset values, deployment of the selected approach will be postponed until after the new pointing model is implemented this summer (ModificationRequest1C407).
Deployment on HOLD - confirmed with ToddHunter 29 Nov 2007.
PICK  
PTCS Analysis of Trajectory Generation Problems TrajectoryAnalysis JoeBrandt JohnFord, RonGrider To date I have confirmed that the problems are not due to mis-estimations, but are more along the lines of the 'small-step' problem. The trajectory 'bumps' are actually being calculated by the trajectory algorithm itself. Given this, I am investigating alternate means to correct the velocity trajectory. N/A  
PTCS Find/Fix Command Stream Glitches add link to analysis or eventual MR JoeBrandt JohnFord, RonGrider   REFACTOR  
PTCS SCCU Servo Changes ModificationRequest1C806 JoeBrandt JohnFord Software complete. DONE  
PTCS CCU Servo Interlock Update ModificationRequest03C042007 JoeBrandt JohnFord, TimWeadon Ready to build and install ROM-ed code for acceptance (black-box) testing. ALERT!  
PTCS Create Pyrgeometer Manager ModificationRequest2C207 JoeBrandt JohnFord, RonGrider   REFACTOR  
PennArrayReceiver General Mustang Support N/A MelindaMello BrianMason, RamonCreager, PaulMarganian Verified astrid/mgr/spider communications in advance of observing.
Update IRC/Fits with new Bias board address.
Worked on determining why upenn GUI was sending incorrect data to IRC/Fits writer. We did determine the problem, but fixing it requires small code changes (which were done in my local area) but also requires Simon to not use older scripts. These scripts are used to sync up the hardware to known saved parameters and Simon felt that the the overhead in duplicating these scripts without the old values was not worth it. This problem should be fixed after observing runs and Simon has more time to re init his saved xml files.
Changed xml files in IRC/Fitsbecause of hardware address changes in lakeshore.
N/A  
PennArrayReceiver Mustang Meta-MR MasterMustangManagerMr MelindaMello BrianMason, RamonCreager, PaulMarganian MJM:12/20/07. Worked with Ray late last week on 2.6 driver/pci/kernel issues.
Worked on various MR checker/writer
RC - time stamp module is ready to test, though I'm not 100% happy with it so it may be reworked to include the 50MHz clock.
PRM - attempting to move forward on other higher-level issues until we can test on real hardware. Started new MR on Detector Bias Curves.
REFACTOR ALERT!
PennArrayReceiver Data File Stream Upgrade ModificationRequest1XC507? MelindaMello AmyShelton, RamonCreager, PaulMarganian   REFACTOR ALERT!
PennArrayReceiver Mustang Crate Control ModificationRequest16C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian Updated Crate Class to optimize number of serail port commads sent, to save state of ALL commands sent, and not sent commands if state is not changing - this is all prep work for the preliminary requirments for higher level parameters (there are no requirmenets in this MR for this). REFACTOR  
PennArrayReceiver Mustang Tower Control ModificationRequest14C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian No developments. Real Hardware here - tests waiting on hardware availability. PICK  
PennArrayReceiver Mustang FITS Writer ModificationRequest18C507 MelindaMello AmyShelton, RamonCreager, PaulMarganian Recorded metrics on performance for different writing speeds - may be able to shave off 5% of CPU time on writing non-coadded data if need be. Otherwise, this should be ready for sponsor approval. Included new keyword to support Firmware Feedback scans. No Progress. REFACTOR  
PennArrayReceiver Parser   MelindaMello BrianMason, RamonCreager, PaulMarganian   REFACTOR  
PennArrayReceiver Crate Command Monitoring ModificationRequest3C807 MelindaMello BrianMason, RamonCreager, PaulMarganian MR written and approved. Coding complete for this stage - will suppress periodic and well understood error messages after testing period - then will be ready for sponsor testing. No progress this week. REFACTOR  
PennArrayReceiver Collect Detector Bias Curves ModificationRequest6C807 MelindaMello BrianMason, RamonCreager, PaulMarganian MR started, along with proposed design. no feedback yet. No progress.    
KFPA Conceptual Software Design for Data Handling of KFPA design doc here BobGarwood StevenWhite, AmyShelton   N/A  
KFPA Workshop Workshop Wiki Page BobGarwood StevenWhite, AmyShelton Done. N/A DONE
Cicada GPU R&D Presentation1, Presentation2 JoeBrandt JohnFord, RonDuPlain Working on some questions to send to Rick Fisher concerning a GPU signal processing/RFI mitigation project. Investigated some oddities about one of our 10Gig network cards. N/A  
Cicada Software Support N/A RonDuPlain JohnFord, AmyShelton   N/A  
RFI Known Sources Develop Project Plan RfiDataBase LihongYao CarlaBeaudet, Jules Harnett, AmyShelton Had the 2nd RFI database design review meeting with Carla. N/A  
RFI Known Sources Software Design RfiDocs LihongYao CarlaBeaudet, Jules Harnett, AmyShelton Modifying RFI database SW design schema after the 2nd review meeting. Learning more about database design, and using MS Visio tool. N/A  
Data Reduction Evaluate GBT Data Handling Status & Future Options Work in Progress BobGarwood AmyShelton   N/A  
Continuing Education Attend AstroGPU and SuperComputing 2007 N/A JoeBrandt, AmyShelton     N/A DONE
WVU Collaborations WVUOpenHouse13Nov07 N/A AmyShelton PaulMarganian, MikeMcCarty   N/A DONE
Software CM&E ModificationRequest5C807 Incrementing the Project Session Number AmyShelton FrankGhigo   ALERT! PICK
PennArrayReceiver Manager startup and other high level issues. ModificationRequest8C807 MelindaMello BrianMason, RamonCreager, PaulMarganian Started MR. Waiting on more feedback.    
PennArrayReceiver Spider Tests YGORMgrSpiderTestReports MelindaMello BrianMason, RamonCreager, PaulMarganian      


3. CM&E

Description Tests Submitter Notes Status
lpc transfer failures Occurs asynchronously, I know of no tests or means to cause the failure. MarkClark I have added a log mechanism to gfm targeting the failure.  
handling user catalog errors user/CatalogTest.testConstructors MarkClark Development has started.  
Added script for changing antenna slew rates No tests required. JoeBrandt Described here  

Topic PlanOfRecordC82007 . { Edit | Attach | Ref-By | Printable | Diffs | r1.51 | > | r1.50 | > | r1.49 | More }
Revision r1.51 - 24 Jan 2008 - 15:18 GMT - JoeBrandt Content copyright © 1999-2007 by the contributing authors.
All material on this collaboration platform is the property of the contributing authors.